Question

In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract...

In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract price of $22,000,000. The estimated construction costs were $15,500,000. The project was completed on time during the 2917 year. The following information is available for the three year period of the construction project. 2015 2016 2017 Costs Incurred to Date $6,188,000 $12,360,000 $15,875,000 Estimated Costs to Complete 9,282,000 3,090,000 -- Billings to Date 6,400,000 18,890,000 22,000,000 Collections to Date 5,100,000 17,110,000 21,630,000 Required 1. Compute the amount of gross profit to be recognized for each of the three years using the percentage of completion. 2. Prepare all necessary journal entries for the 2015, 2016, and 2017 years using the percentage of completion method. 3. Compute gross profit to be recognized for the three years of 2015, 2016, and 2017 using the completed contract method. 4. For each of the three years of 2015, 2016, and 2017: a. Prepare the Income Statement section for Big Boss Construction reporting percentage of completion information. b. Prepare the Balance Sheet section for Big Boss Constriction reporting percentage of completion information.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
  1. Recognition of Gross Profit under the Percentage of completion method

Particulars

       Year 2015(FIG IN $)

     Year 2016(FIG IN $)

      Year 2017(FIG IN $)

Contract Price

22000000

22000000

22000000

Cost incurred

To date

6188000

12360000

15875000

Add:estimated

Cost to complete

9282000

15470000

3090000

15450000

-

15875000

Total Estimated

Profit

6530,000

65,50,000

61,25,000

Percentage completed

Till date

40%

80%

100%

Total Gross Profit

Recognized

26,12,000

52,40,000

61,25,000

2.

Journal entries under percentage of completion method

Particulars

Debit($)

Credit( $)

Debit($)

Credit($)

Debit($)

Credit($)

Cost incurred to

Date

Construction in

Progress(CIP)

6188000

12360000

15875000

Accounts payable

6188000

12360000

15875000

Billing to date

Accounts Receivable

6400000

18890000

22000000

   Billing on CIP

6400000

18890000

22000000

Receiving Payament

Cash

5100000

17110000

21630000

   Accounts Receivable

5100000

17110000

21630000

Recording Revenue

Billing on CIP

6400000

18890000

22000000

Construction revenue a/c

6400000

18890000

22000000

Recording Expenses

Cost of construction

6188000

12360000

15875000

Construction in progress(CIP)

        

6188000

12360000

15875000

3.Recognition of Gross Profit under the completion contract method

Particulars

       Year 2015(fig in$)

     Year 2016(fig in $)

      Year 2017(fig in $)

Contract Price

22000000

22000000

22000000

Cost incurred

To date

6188000

12360000

15875000

Add:estimated

Cost to complete

9282000

15470000

3090000

15450000

-

15875000

Total Estimated

Profit

6530,000

65,50,000

61,25,000

Percentage completed

Till date

40%

80%

100%

Total Gross Profit

Recognized

Not applicable

Not applicable

61,25,000

4. a) INCOME STATEMENT SECTION

Particulars

Year 2015(fig in$)

Year 2016(fig in$)

Year 2017(fig in$)

Sales

8800000

17600000

22000000

Less : Cost of goods sold

6188000

12360000

15875000

Gross profit

2612000

5240,000

61,25,000

b. BALANCE SHEET":

Current liabilities

CIP

lESS: bILLINGS ON

construction

Add a comment
Know the answer?
Add Answer to:
In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Fender period. Construction Company receives a contract to construct a building over a 3 year Information...

    Fender period. Construction Company receives a contract to construct a building over a 3 year Information relating to the performance of the contract is summarized as follows: 2015 2016 2017 S 16,000,000 Cumulative construction costs incurred to date Estimated costs to complete Billings during the year Cash collected during the year 6,000,000 8,000,000 6,000,000 3,000,000 8,000,000 7,000,000 4,000,000 5,000,000 Required: 1. How much is Fender Construction charging to build this athletic stadium? In other words, what is the contract price...

  • On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2016, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2017, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2017 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2018 after additional costs of...

  • King Corporation started the construction of a building during 2017 at a contract price of $5,000,000....

    King Corporation started the construction of a building during 2017 at a contract price of $5,000,000. The contract to build was non-cancellable and they managed to complete the project in 2019 as anticipated. Billings are nonrefundable and under the terms of the project, King sends billings to the vendor as revenues are earned. The following additional information is available: 2017 2018 2019 Costs to-date $ 800,000 $2,500,000 $4,800,000 Estimated costs to complete $2,400,000 $2,500,000 $0 Required: a. Calculate the amount...

  • The contract price for a 3-year construction contract is $100 The actual cost and estimated costs...

    The contract price for a 3-year construction contract is $100 The actual cost and estimated costs for each vear are given below: Items 2016 2017 2018 Actual cost incurred each year $10 Estimated cost to complete $40 Under Percentage of Completion method (You first prepare the table I showed you in the class to make your calculations easier) S20 $30 1. Compute Actual cost incurred to date 2. Compute total estimated cost for each year 3. Compute estimated gross profit...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2020 after additional costs of...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began in 2016 and was completed in 2017. Data relating to the contract are summarized below: 2016 2017   Costs incurred during the year $ 360,000 $ 2,155,000   Estimated costs to complete as of 12/31 1,440,000 0   Billings during the year 500,000 1,770,000   Cash collections during the year 280,000 1,825,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

  • On February 1, 2021. Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021. Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2.475,000 cash was collected. The project was completed in 2023 after additional costs of...

  • During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job...

    During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...

  • Question 1 During 2017, Nash Company started a construction job with a contract price of $1,580,000....

    Question 1 During 2017, Nash Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available. 20172018 2019 Costs incurred to date Estimated costs to complete Billings to date Collections to date $366,300 $802,270 $1,080,000 623,700 296,730 297,000 906,000 1,580,000 270,000 802,000 1,427,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 Gross profit recognized in...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT