Percentage completion method | 2017 | 2018 | 2019 | |
Cost incurred in till previous year | 0 | 366300 | 802270 | |
ADD | Cost incurred during the year | 366300 | 435970 | 277730 |
Total cost incurred till date | 366300 | 802270 | 1080000 | |
ADD | Estimated cost to be incurred | 623700 | 296730 | 0 |
Total estimated cost to be incurred | 990000 | 1099000 | 1080000 | |
Percentage of completion (A) | 37% | 73.00% | 100% | |
(cost incurred till date /total estimated cost ) | ||||
Total revenue (B) | 1580000 | 1580000 | 1580000 | |
Total revenue recognized (A *B) | 584600 | 1153400 | 1580000 | |
Less | Revenue recognized in previous year | 0 | 584600 | 1153400 |
revenue recognized in current year | 584600 | 568800 | 426600 | |
2017 | 2018 | 2019 | ||
Revenue | 584600 | 568800 | 426600 | |
Less | Cost incurred | 366300 | 435970 | 277730 |
Gross profit | 218300 | 132830 | 148870 | |
2018 | ||||
1 | Construction in progress | 435970 | ||
Accounts payable | 435970 | |||
2 | Contracts receivable | 609000 | (906000-297000) | |
Progress billings | 609000 | |||
3 | Construction in progress | 148630 | ||
Construction expense | 435970 | |||
Construction revenue | 584600 | |||
4 | Cash | 532000 | ||
Contract receivable | 532000 | |||
Question 1 During 2017, Nash Company started a construction job with a contract price of $1,580,000....
During 2020, Pronghorn Company started a construction job with a contract price of $1,580,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $424,200 $820,500 $1,077,000 Estimated costs to complete 585,800 273,500 –0– Billings to date 297,000 894,000 1,580,000 Collections to date 273,000 816,000 1,419,000 Instructions: Complete a chart analyzing the above information showing revenue, the % of completion every year and the amount of gross profit to be recognized each...
During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...
During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 $366,300 623,700 297,000 270,000 2021 $831,440 262,560 894,000 816,000 2022 $1,067,000 -0- 1,590,000 1,417,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...
During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 -0- Billings to date 301,000 268,000 892,000 816,000 1,590,000 1,427,000 Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...
During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 -0- 1,610,000 Billings to date 301.000 897,000 271,000 1428,000 Collections to date 817,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used $ Gross profit recognized in 2017 $ Gross profit...
During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 A) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ 258,000 Gross...
During 2017, Crane Company started a construction job with a contract price of $ 1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $ 366,300 $ 772,100 $ 1,063,000 Estimated costs to complete 623,700 330,900 –0– Billings to date 300,000 909,000 1,610,000 Collections to date 271,000 807,000 1,424,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017...
During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete 2020 2021 2022 $410,000 $901,180 $1,067,000 590,000 197,820 -0- 297,000 903,000 .590,000 271,000 805,000 1,434,000 Billings to date Collections to date ✓ Your answer is correct Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...
During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2022 2020 2021 Costs incurred to date $404,000 $830,680 $1,069,000 Estimated costs to complete -0 606,000 262,320 Billings to date 300,000 906,000 1,600,000 Collections to date 272,000 810,000 1,416,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...
During 2020, Martinez Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...