King Corporation started the construction of a building during 2017 at a contract price of $5,000,000. The contract to build was non-cancellable and they managed to complete the project in 2019 as anticipated. Billings are nonrefundable and under the terms of the project, King sends billings to the vendor as revenues are earned. The following additional information is available:
2017 2018 2019
Costs to-date $ 800,000 $2,500,000 $4,800,000
Estimated costs to complete $2,400,000 $2,500,000 $0
Required:
a. Calculate the amount of revenue to be recognized each year using the percentage of completion method. (2017, 2018 & 2019)
b. Calculate the amount of gross profit/loss that should be recognized (2017, 2018 & 2019) each year using the percentage-of-completion method
c. What is the amount of gross profit/loss that should be recognized each year under the completed-contract method?
a)
2017 | 2018 | 2019 | |
cost to date [A] | 800000 | 2500000 | 4800000 |
Estimated cost to complete [B] | 2400000 | 2500000 | 0 |
Total cost [C] = [A+B] | 3200000 | 5000000 | 4800000 |
% Of completion [ A/C] |
800000/3200000 .25 OR 25% |
2500000/5000000 .50 OR50% |
100% |
a)
2017 | 2018 | 2019 | |
Total Revenue to be recognized till date [Total contract revenue * % of completion] | 5000000*25%= 1250000 | 5000000*50% =2500000 | 5000000*100%= 5000000 |
less:Revenue recognized in prior year/period | 0 | -1250000 | -2500000 |
Revenue to be recognized in current period | 1250000 | 1250000 | 2500000 |
b)
2017 | 2018 | 2019 | |
Revenue recognized in current period | 1250000 | 1250000 | 2500000 |
less:cost incurred during the current period | -800000 | -1700000 [2500000-800000] | -2300000 [4800000-2500000] |
Gross profit | 450000 | -450000 | 200000 |
*:cost incurred during the current period =Total cost incurred till date - cost incurred till prior period.
c)In case of completed contract method ,revenue is recognized only at time of completion of contract.
2017 | 2018 | 2019 | |
Gross profit and loss | 0 | 0 | 5000000-4800000=200000 |
King Corporation started the construction of a building during 2017 at a contract price of $5,000,000....
During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...
During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 -0- 1,610,000 Billings to date 301.000 897,000 271,000 1428,000 Collections to date 817,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used $ Gross profit recognized in 2017 $ Gross profit...
Question 1 During 2017, Nash Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available. 20172018 2019 Costs incurred to date Estimated costs to complete Billings to date Collections to date $366,300 $802,270 $1,080,000 623,700 296,730 297,000 906,000 1,580,000 270,000 802,000 1,427,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 Gross profit recognized in...
During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 A) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ 258,000 Gross...
Exercise 18-33 During 2017, Marin Company started a construction yob with a contract price of $1,610,000. The job was completed in 2019. The following information is available, 2017 2018 2019 Costs incurred to date $405,900 $766,500 51,076,000 Estimated costs to complete 584,100 328,500 Brings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage of completion method is used. Gross proft recognized in 2017 Gross...
During 2017, Crane Company started a construction job with a contract price of $ 1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $ 366,300 $ 772,100 $ 1,063,000 Estimated costs to complete 623,700 330,900 –0– Billings to date 300,000 909,000 1,610,000 Collections to date 271,000 807,000 1,424,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017...
During 2020, Pharoah Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $373,700 $902,000 $1,070,000 Estimated costs to complete 636,300 198,000 –0– Billings to date 303,000 899,000 1,620,000 Collections to date 273,000 807,000 1,412,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amountenter...
On February 1, 2017, Marsh Contractors agreed to construct a building at a contract price of $5,720,000. Marsh estimated total construction costs would be $3,936,000 and the project would be finished in 2019. Information relating to the costs and billings for this contract is as follows: 2017 2018 2019 Total costs incurred to date $1,476,000 $2,592,000 $4,560,000 Estimated costs to complete 2,460,000 1,728,000 -0- Customer billings to date 2,120,000 3,936,000 5,520,000 Collections to date 1,920,000 3,420,000 5,420,000 Fill in the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Brief Exercise 6-33 a, b1-ci (Part Level Submission) During 2020, Flounder Corporation started a construction job with a contract price of $5.74 million. Flounder ran into severe technical difficulties during construction but managed to complete the job in 2022. The contract is non-cancellable. Under the terms of the contract, Flounder sends billings as revenues are earned. Billings are non-refundable. The following information is available: 2020 $ 820,000 4,305,000 Costs incurred to date Estimated costs to complete 2021 $2,870,000 2,870,000 2022...