Question

On February 1, 2017, Marsh Contractors agreed to construct a building at a contract price of...

On February 1, 2017, Marsh Contractors agreed to construct a building at a contract price of $5,720,000. Marsh estimated total construction costs would be $3,936,000 and the project would be finished in 2019. Information relating to the costs and billings for this contract is as follows:

2017 2018 2019
Total costs incurred to date $1,476,000 $2,592,000 $4,560,000
Estimated costs to complete 2,460,000 1,728,000 -0-
Customer billings to date 2,120,000 3,936,000 5,520,000
Collections to date 1,920,000 3,420,000 5,420,000


Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and for completed-contract accounting, show the gross profit that should be recorded for 2017, 2018, and 2019.

Percentage-of-Completion
Gross Profit
Completed-Contract
Gross Profit
2017 $

2017 $

2018 $

2018 $

2019 $

2019 $

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

  • Working for Percentage of Completion method

Working

Year end 2017

Year end 2018

Year end 2019

A

Contract Price

$       5,720,000.00

$       5,720,000.00

$          5,720,000.00

B

Cost Incurred to Date

$       1,476,000.00

$       2,592,000.00

$          4,560,000.00

C

Estimated cost yet to be incurred to complete the contract

$       2,460,000.00

$       1,728,000.00

$                                -  

D = B+C

Total Cost

$       3,936,000.00

$       4,320,000.00

$          4,560,000.00

E = (B/D) x 100

% of Completion

37.50%

60.00%

100.00%

F = A x E

Revenue to date

$       2,145,000.00

$       3,432,000.00

$          5,720,000.00

G

Revenue of Previous year

$                            -  

$       2,145,000.00

$          3,432,000.00

H = F - G

Net Revenue this year

$       2,145,000.00

$       1,287,000.00

$          2,288,000.00

I (=B)

Cost to date

$       1,476,000.00

$       2,592,000.00

$          4,560,000.00

J

Cost to date of previous year

$                            -  

$       1,476,000.00

$          2,592,000.00

K = I - J

Net Cost for the year

$       1,476,000.00

$       1,116,000.00

$          1,968,000.00

L = H - K

Gross Profits

$           669,000.00

$          171,000.00

$              320,000.00

  • Requirements

Percentage-of-Completion
Gross Profit

Completed-Contract
Gross Profit

2017

$ 669000

phpMLlOcS.png

2017

$0

phpeejAyx.png

2018

$ 171000

phpoXPG8X.png

2018

$ 0

phpIj8UJw.png

2019

$ 320000

phpwQ6BrM.png

2019

$ 1160000 [$5720000 – 4560000 cost incurred]

php6VnxBs.png

Add a comment
Know the answer?
Add Answer to:
On February 1, 2017, Marsh Contractors agreed to construct a building at a contract price of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Ex. 18-127-Percentage-of-completion and completed-contract methods. On February 1, 2012, Marsh Contractors agreed to construct a building...

    Ex. 18-127-Percentage-of-completion and completed-contract methods. On February 1, 2012, Marsh Contractors agreed to construct a building at a contract price of $5,400,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2014. Information relating to the costs and billings for this contract is as follows: 2014 2012 $1,500,000 2,500,000 2,200,000 2,000,000 2013 $4,600,000 $2,640,000 1,760,000 4,000,000 3,500,000 Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date -0-...

  • King Corporation started the construction of a building during 2017 at a contract price of $5,000,000....

    King Corporation started the construction of a building during 2017 at a contract price of $5,000,000. The contract to build was non-cancellable and they managed to complete the project in 2019 as anticipated. Billings are nonrefundable and under the terms of the project, King sends billings to the vendor as revenues are earned. The following additional information is available: 2017 2018 2019 Costs to-date $ 800,000 $2,500,000 $4,800,000 Estimated costs to complete $2,400,000 $2,500,000 $0 Required: a. Calculate the amount...

  • Question 1 During 2017, Nash Company started a construction job with a contract price of $1,580,000....

    Question 1 During 2017, Nash Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available. 20172018 2019 Costs incurred to date Estimated costs to complete Billings to date Collections to date $366,300 $802,270 $1,080,000 623,700 296,730 297,000 906,000 1,580,000 270,000 802,000 1,427,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 Gross profit recognized in...

  • During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job...

    During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...

  • During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 -0- 1,610,000 Billings to date 301.000 897,000 271,000 1428,000 Collections to date 817,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used $ Gross profit recognized in 2017 $ Gross profit...

  • Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It is estimated that the complex will take 3 years to construct. Additional information follows. Estimated cost of complex Contract price AA 600,000 900,000 The following data pertain to the construction period. 2019 610,000 $ 6100 A 2017 270,000 330,000 270,000 240,000 2018 450,000 150,000 550,000 500,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $...

  • During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 A) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ 258,000 Gross...

  • Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $895,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $268,200 $482,760 $605,000 Estimated costs to complete 327,800 113,240 –0– Progress billings to date 267,000 552,000 895,000 Cash collected to date...

  • Black Sea Construction Company has a contract to construct a $6,000,000 oil rig at an estimated...

    Black Sea Construction Company has a contract to construct a $6,000,000 oil rig at an estimated cost of $5,300,000. The contract is to start in July 2017, and the oil rig is to be completed in October 2019. The following data pertain to the construction period. 2017    2018    2019 Costs to date $1,325,000 $3,720,000 $6,300,000 Estimated costs to complete 3,975,000 2,480,000 — Progress billings during the year 1,200,000 3,200,000 1,600,000 Cash collected during the year 1,000,000 2,340,000 2,660,000 What amount...

  • On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabr...

    On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT