On February 1, 2017, Marsh Contractors agreed to construct a
building at a contract price of $5,720,000. Marsh estimated total
construction costs would be $3,936,000 and the project would be
finished in 2019. Information relating to the costs and billings
for this contract is as follows:
2017 | 2018 | 2019 | ||||
Total costs incurred to date | $1,476,000 | $2,592,000 | $4,560,000 | |||
Estimated costs to complete | 2,460,000 | 1,728,000 | -0- | |||
Customer billings to date | 2,120,000 | 3,936,000 | 5,520,000 | |||
Collections to date | 1,920,000 | 3,420,000 | 5,420,000 |
Fill in the correct amounts on the following schedule. For
percentage-of-completion accounting and for completed-contract
accounting, show the gross profit that should be recorded for 2017,
2018, and 2019.
Percentage-of-Completion Gross Profit |
Completed-Contract Gross Profit |
|||||
2017 | $
|
2017 | $
|
|||
2018 | $
|
2018 | $
|
|||
2019 | $
|
2019 | $
|
Answer
Working |
Year end 2017 |
Year end 2018 |
Year end 2019 |
|
A |
Contract Price |
$ 5,720,000.00 |
$ 5,720,000.00 |
$ 5,720,000.00 |
B |
Cost Incurred to Date |
$ 1,476,000.00 |
$ 2,592,000.00 |
$ 4,560,000.00 |
C |
Estimated cost yet to be incurred to complete the contract |
$ 2,460,000.00 |
$ 1,728,000.00 |
$ - |
D = B+C |
Total Cost |
$ 3,936,000.00 |
$ 4,320,000.00 |
$ 4,560,000.00 |
E = (B/D) x 100 |
% of Completion |
37.50% |
60.00% |
100.00% |
F = A x E |
Revenue to date |
$ 2,145,000.00 |
$ 3,432,000.00 |
$ 5,720,000.00 |
G |
Revenue of Previous year |
$ - |
$ 2,145,000.00 |
$ 3,432,000.00 |
H = F - G |
Net Revenue this year |
$ 2,145,000.00 |
$ 1,287,000.00 |
$ 2,288,000.00 |
I (=B) |
Cost to date |
$ 1,476,000.00 |
$ 2,592,000.00 |
$ 4,560,000.00 |
J |
Cost to date of previous year |
$ - |
$ 1,476,000.00 |
$ 2,592,000.00 |
K = I - J |
Net Cost for the year |
$ 1,476,000.00 |
$ 1,116,000.00 |
$ 1,968,000.00 |
L = H - K |
Gross Profits |
$ 669,000.00 |
$ 171,000.00 |
$ 320,000.00 |
Percentage-of-Completion |
Completed-Contract |
|||||
2017 |
$ 669000 |
2017 |
$0 |
|||
2018 |
$ 171000 |
2018 |
$ 0 |
|||
2019 |
$ 320000 |
2019 |
$ 1160000 [$5720000 – 4560000 cost incurred] |
On February 1, 2017, Marsh Contractors agreed to construct a building at a contract price of...
Ex. 18-127-Percentage-of-completion and completed-contract methods. On February 1, 2012, Marsh Contractors agreed to construct a building at a contract price of $5,400,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2014. Information relating to the costs and billings for this contract is as follows: 2014 2012 $1,500,000 2,500,000 2,200,000 2,000,000 2013 $4,600,000 $2,640,000 1,760,000 4,000,000 3,500,000 Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date -0-...
King Corporation started the construction of a building during 2017 at a contract price of $5,000,000. The contract to build was non-cancellable and they managed to complete the project in 2019 as anticipated. Billings are nonrefundable and under the terms of the project, King sends billings to the vendor as revenues are earned. The following additional information is available: 2017 2018 2019 Costs to-date $ 800,000 $2,500,000 $4,800,000 Estimated costs to complete $2,400,000 $2,500,000 $0 Required: a. Calculate the amount...
Question 1 During 2017, Nash Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available. 20172018 2019 Costs incurred to date Estimated costs to complete Billings to date Collections to date $366,300 $802,270 $1,080,000 623,700 296,730 297,000 906,000 1,580,000 270,000 802,000 1,427,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 Gross profit recognized in...
During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...
During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 -0- 1,610,000 Billings to date 301.000 897,000 271,000 1428,000 Collections to date 817,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used $ Gross profit recognized in 2017 $ Gross profit...
Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It is estimated that the complex will take 3 years to construct. Additional information follows. Estimated cost of complex Contract price AA 600,000 900,000 The following data pertain to the construction period. 2019 610,000 $ 6100 A 2017 270,000 330,000 270,000 240,000 2018 450,000 150,000 550,000 500,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $...
During 2017, Pearl Company started a construction job with a
contract price of $1,610,000. The job was completed in 2019. The
following information is available.
2017
2018
2019
Costs incurred to date
$434,300
$859,560
$1,073,000
Estimated costs to complete
575,700
242,440
–0–
Billings to date
301,000
897,000
1,610,000
Collections to date
271,000
817,000
1,428,000
A) Compute the amount of gross profit to be recognized each
year, assuming the percentage-of-completion method is used.
Gross profit recognized in 2017 $ 258,000
Gross...
Cheyenne Construction Company has entered into a contract
beginning January 1, 2017, to build a parking complex. It has been
estimated that the complex will cost $596,000 and will take 3 years
to construct. The complex will be billed to the purchasing company
at $895,000. The following data pertain to the construction
period.
2017
2018
2019
Costs to date
$268,200
$482,760
$605,000
Estimated costs to
complete
327,800
113,240
–0–
Progress billings to
date
267,000
552,000
895,000
Cash collected to date...
Black Sea Construction Company has a contract to construct a $6,000,000 oil rig at an estimated cost of $5,300,000. The contract is to start in July 2017, and the oil rig is to be completed in October 2019. The following data pertain to the construction period. 2017 2018 2019 Costs to date $1,325,000 $3,720,000 $6,300,000 Estimated costs to complete 3,975,000 2,480,000 — Progress billings during the year 1,200,000 3,200,000 1,600,000 Cash collected during the year 1,000,000 2,340,000 2,660,000 What amount...
On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...