Computation of Percentage of cost of Completion | |||
2016 | 2017 | 2018 | |
Cost incurred in Previous Year | $0 | $10 | $30 |
Cost incurred during the year | $10 | $20 | $80 |
Total Cost Incurred till date | $10 | $30 | $110 |
Estmiated cost to Complete at end of of year | $40 | $30 | $0 |
Total Estimated Cost of Completion | $50 | $60 | $0 |
% of Cost of Completion | 20% | 50% | 100% |
( Cost incurred as on /Total cost of Completion) |
Statement showing Revenue recogniztion for each year | |||
2016 | 2017 | 2018 | |
Contract Price | $100.00 | ||
% of Cost of Completion | 20% | 50% | 100% |
Revenue recognised to be recognized as on (a) | $20 | $50 | $100 |
Revenue recognized in previous year (b) | $0 | $20 | $50 |
Revenue recognized in Current year (a-b) | $20 | $30 |
$50 |
1. Actual Cost Incurred :$110
2. Estimated Cost for each year
2016: $50
2017: $$60
2018: $0
3&6. Statement showing Gross Profit for each year | ||||
2016 | 2017 | 2018 | Total | |
Revenue recognized in Current year | $20 | $30 | $50 | $100 |
Cost Incurred in Current Year | $10 | $20 | $80 | $110 |
Gross Profit | $10 | $10 | -$30 | -$10 |
4. As shown above:-
5: As shown Above
The contract price for a 3-year construction contract is $100 The actual cost and estimated costs...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...
Fender period. Construction Company receives a contract to construct a building over a 3 year Information relating to the performance of the contract is summarized as follows: 2015 2016 2017 S 16,000,000 Cumulative construction costs incurred to date Estimated costs to complete Billings during the year Cash collected during the year 6,000,000 8,000,000 6,000,000 3,000,000 8,000,000 7,000,000 4,000,000 5,000,000 Required: 1. How much is Fender Construction charging to build this athletic stadium? In other words, what is the contract price...
Contract Information 2018 2019 2020 $ 1,530,000 $ 7,100,000 $ 540,000 Actual construction costs incurred during the year Estimated costs to complete Progress billings made during the year Cash collections during the year 0 7,280,000 4,400,000 3,110,000 460,000 3,900,000 3,110,000 1,030,000 3,110,000 Dulu TUNIC 2018 2019 2020 Cumulative square feet completed 16,800 25,200 42,000 Anglee Builders accepts a contract with Norton Stores to construct a strip mall on Route 3 on January 2, 2018. The builder accepts a fixed fee...
On February 1, 2018, Arrow Construction Company entered into a
three-year construction contract to build a bridge for a price of
$8,060,000. During 2018, costs of $2,020,000 were incurred with
estimated costs of $4,020,000 yet to be incurred. Billings of
$2,520,000 were sent, and cash collected was $2,270,000.
In 2019, costs incurred were $2,520,000 with remaining costs
estimated to be $3,630,000. 2019 billings were $2,770,000 and
$2,495,000 cash was collected. The project was completed in 2020
after additional costs of...
During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...
King Corporation started the construction of a building during 2017 at a contract price of $5,000,000. The contract to build was non-cancellable and they managed to complete the project in 2019 as anticipated. Billings are nonrefundable and under the terms of the project, King sends billings to the vendor as revenues are earned. The following additional information is available: 2017 2018 2019 Costs to-date $ 800,000 $2,500,000 $4,800,000 Estimated costs to complete $2,400,000 $2,500,000 $0 Required: a. Calculate the amount...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 -0- 1,610,000 Billings to date 301.000 897,000 271,000 1428,000 Collections to date 817,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used $ Gross profit recognized in 2017 $ Gross profit...
During 2017, Pearl Company started a construction job with a
contract price of $1,610,000. The job was completed in 2019. The
following information is available.
2017
2018
2019
Costs incurred to date
$434,300
$859,560
$1,073,000
Estimated costs to complete
575,700
242,440
–0–
Billings to date
301,000
897,000
1,610,000
Collections to date
271,000
817,000
1,428,000
A) Compute the amount of gross profit to be recognized each
year, assuming the percentage-of-completion method is used.
Gross profit recognized in 2017 $ 258,000
Gross...
Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows:...