Question

The contract price for a 3-year construction contract is $100 The actual cost and estimated costs for each vear are given below: Items 2016 2017 2018 Actual cost incurred each year $10 Estimated cost to complete $40 Under Percentage of Completion method (You first prepare the table I showed you in the class to make your calculations easier) S20 $30 1. Compute Actual cost incurred to date 2. Compute total estimated cost for each year 3. Compute estimated gross profit to date for each year (actual in 2018) 4. Compute the percentage of completion to date (cumulative) 5. How much revenue to be recognized each year 6. How much gross profit to be recognized each year Under Percentage of Completion method: 1. How much revenue recognized for each year 2. How much gross profit to be recognized each year
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Computation of Percentage of cost of Completion
2016 2017 2018
Cost incurred in Previous Year $0 $10 $30
Cost incurred during the year $10 $20 $80
Total Cost Incurred till date $10 $30 $110
Estmiated cost to Complete at end of of year $40 $30 $0
Total Estimated Cost of Completion $50 $60 $0
% of Cost of Completion 20% 50% 100%
( Cost incurred as on /Total cost of Completion)
Statement showing Revenue recogniztion for each year
2016 2017 2018
Contract Price $100.00
% of Cost of Completion 20% 50% 100%
Revenue recognised to be recognized as on (a) $20 $50 $100
Revenue recognized in previous year (b) $0 $20 $50
Revenue recognized in Current year (a-b) $20 $30

$50

1. Actual Cost Incurred :$110

2. Estimated Cost for each year

2016: $50

2017: $$60

2018: $0

3&6. Statement showing Gross Profit for each year
2016 2017 2018 Total
Revenue recognized in Current year $20 $30 $50 $100
Cost Incurred in Current Year $10 $20 $80 $110
Gross Profit $10 $10 -$30 -$10

4. As shown above:-

5: As shown Above

Add a comment
Know the answer?
Add Answer to:
The contract price for a 3-year construction contract is $100 The actual cost and estimated costs...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...

  • Fender period. Construction Company receives a contract to construct a building over a 3 year Information...

    Fender period. Construction Company receives a contract to construct a building over a 3 year Information relating to the performance of the contract is summarized as follows: 2015 2016 2017 S 16,000,000 Cumulative construction costs incurred to date Estimated costs to complete Billings during the year Cash collected during the year 6,000,000 8,000,000 6,000,000 3,000,000 8,000,000 7,000,000 4,000,000 5,000,000 Required: 1. How much is Fender Construction charging to build this athletic stadium? In other words, what is the contract price...

  • Contract Information 2018 2019 2020 $ 1,530,000 $ 7,100,000 $ 540,000 Actual construction costs incurred during...

    Contract Information 2018 2019 2020 $ 1,530,000 $ 7,100,000 $ 540,000 Actual construction costs incurred during the year Estimated costs to complete Progress billings made during the year Cash collections during the year 0 7,280,000 4,400,000 3,110,000 460,000 3,900,000 3,110,000 1,030,000 3,110,000 Dulu TUNIC 2018 2019 2020 Cumulative square feet completed 16,800 25,200 42,000 Anglee Builders accepts a contract with Norton Stores to construct a strip mall on Route 3 on January 2, 2018. The builder accepts a fixed fee...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2020 after additional costs of...

  • During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job...

    During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...

  • King Corporation started the construction of a building during 2017 at a contract price of $5,000,000....

    King Corporation started the construction of a building during 2017 at a contract price of $5,000,000. The contract to build was non-cancellable and they managed to complete the project in 2019 as anticipated. Billings are nonrefundable and under the terms of the project, King sends billings to the vendor as revenues are earned. The following additional information is available: 2017 2018 2019 Costs to-date $ 800,000 $2,500,000 $4,800,000 Estimated costs to complete $2,400,000 $2,500,000 $0 Required: a. Calculate the amount...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...

  • During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 -0- 1,610,000 Billings to date 301.000 897,000 271,000 1428,000 Collections to date 817,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used $ Gross profit recognized in 2017 $ Gross profit...

  • During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 A) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ 258,000 Gross...

  • Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to...

    Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows:...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT