Percentage of Completion Method
2016 2017 2018
(A) Costs incurred to date 2610000 3162000 2230800
Estimated future costs 6390000 2028000 0
(B) Estimated total costs 9000000 5190000 2230800
Progress billings to date 2100000 3672000 4228000
Cash collected to date 1850000 3000000 5150000
(C) Est. total gross profit (10000000 - B) 1000000 4810000 7769200
(D) Percent Complete (A/B) 29% 61% 100%
Rev. Recog. to Date (10000000*D) 2900000 6100000 10000000
Current Yr. Revenue Recognized 2900000 3200000 3900000
Total GP Recognized to Date (C*D) 1000000 2934100 7769200
Current Yr. Gross Profit Recognized 1000000 1934100 4835100
(a).Percentage of completion
2016 = 29%
2017 = 61%
2018 = 100%
Amount of revenue recognized in 2016 = 2900000
Amount of Gross Profit recognized in 2016 = 1000000
(c).CIP/Billings are presented as an asset in the Balance Sheet. Construction Work-in-Progress is a long-term asset account in which the costs of constructing long-term assets are recorded. The account Construction Work-in-Progress will have a debit balance and will be reported on the balance sheet as part of a company's “ Property, Plant and Equipment “
.
.
.
.
ALL THE BEST !!!
In 2016, Pioneer Construction Company entered into a contract to construct a road for Denton County...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,610,000 6,390,000 2,100,000 1,850,000 $3,162,000 2,028,000 3,672,000 3,000,000 $2,230,800 4,228,000 5,150,000...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...
Question Three: In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara Countyfor $10,000,000. The road was completed in 201 contract is as follows: 8. Information related to the 2018 2016 2,400,000 3,600,000 2,200,00 5,600,000 2,000,000 4,000,000 4,000,000 ,800,000 3,600,000 4,600,000 2017 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2,000,000 Westgate recognizes revenue over time according to percentage of...
show working please
et to search No results < > Options 6C - LT Contracts Saved Help Save Ti ne following information applies to the questions displayed below In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,238,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year...
In 2016, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2018. Information related to
the contract is as follows:
I NEED HELP RESOLVING THE EMPTY 8 BOXES BELOW
(4&5).
4. Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your...
in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 2,110,000 3,736,000 4,154,000 Cash collections during the year 1,855,000 3,500,000 4,645,000 Westgate...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,490,000 5,810,000 2,030,000 1,815,000 2019 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 3....
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,059,000 $ 2,627,000 $ 2,655,400 Estimated costs to complete as of year-end 5,041,000 2,414,000 0 Billings during the year 2,190,000 2,496,000 5,314,000 Cash collections during the year 1,895,000 2,400,000 5,705,000 Westgate recognizes revenue over time according to...