Question

In 2016, Pioneer Construction Company entered into a contract to construct a road for Denton County for S10,000,000. The road was completed in 2018. Information related to the contract is as follows: 2017 $2,610,000 S3,162,000 $2,230,800 2,028,000 2,100,000 3,672,000 4,228,000 1,850,000 3,000,000 5,150,000 2016 2018 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year 6,390,000 0 Cash collections during the year Pioneer recognizes revenue over time according to percentage of completion. Calculate the % of completion, amount of revenue and gross profit to be recognized in 2016. Calculate the balance in CIP a/c at the end of 2016. Are CIP/Billings presented as an asset or liability in the balance sheet at the end of 2016. a) b) c) a) Percentage of Completion
media%2F0f4%2F0f430ac0-a8ff-4219-a223-36
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Percentage of Completion Method

                                                                   2016           2017           2018

(A) Costs incurred to date                          2610000     3162000    2230800

Estimated future costs                                6390000    2028000     0

(B) Estimated total costs                            9000000     5190000     2230800

Progress billings to date                             2100000     3672000     4228000

Cash collected to date 1850000     3000000     5150000

(C) Est. total gross profit (10000000 - B) 1000000     4810000     7769200

(D) Percent Complete (A/B) 29%            61%            100%

Rev. Recog. to Date (10000000*D)            2900000     6100000     10000000

Current Yr. Revenue Recognized 2900000     3200000     3900000

Total GP Recognized to Date (C*D)           1000000     2934100     7769200

Current Yr. Gross Profit Recognized 1000000     1934100     4835100

(a).Percentage of completion

2016 = 29%

2017 = 61%

2018 = 100%

Amount of revenue recognized in 2016 = 2900000

Amount of Gross Profit recognized in 2016 = 1000000

(c).CIP/Billings are presented as an asset in the Balance Sheet. Construction Work-in-Progress is a long-term asset account in which the costs of constructing long-term assets are recorded. The account Construction Work-in-Progress will have a debit balance and will be reported on the   balance sheet   as part of a company's “ Property, Plant and Equipment “

.

.

.

.

ALL THE BEST !!!

Add a comment
Know the answer?
Add Answer to:
In 2016, Pioneer Construction Company entered into a contract to construct a road for Denton County...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Constr...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,610,000 6,390,000 2,100,000 1,850,000 $3,162,000 2,028,000 3,672,000 3,000,000 $2,230,800 4,228,000 5,150,000...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...

  • Question Three: In 2016, the Westgate Construction Company entered into a contract to construct a road...

    Question Three: In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara Countyfor $10,000,000. The road was completed in 201 contract is as follows: 8. Information related to the 2018 2016 2,400,000 3,600,000 2,200,00 5,600,000 2,000,000 4,000,000 4,000,000 ,800,000 3,600,000 4,600,000 2017 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2,000,000 Westgate recognizes revenue over time according to percentage of...

  • show working please et to search No results < > Options 6C - LT Contracts Saved...

    show working please et to search No results < > Options 6C - LT Contracts Saved Help Save Ti ne following information applies to the questions displayed below In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,238,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year...

  • In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows: I NEED HELP RESOLVING THE EMPTY 8 BOXES BELOW (4&5). 4. Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your...

  • in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:                                      2018                         2019                            2020 Cost incurred during the year    $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end         5,609,000 2,054,000 0 Billings during the year    2,110,000               3,736,000                   4,154,000 Cash collections during the year                            1,855,000    3,500,000 4,645,000 Westgate...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,490,000 5,810,000 2,030,000 1,815,000 2019 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 3....

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,059,000 $ 2,627,000 $ 2,655,400 Estimated costs to complete as of year-end 5,041,000 2,414,000 0 Billings during the year 2,190,000 2,496,000 5,314,000 Cash collections during the year 1,895,000 2,400,000 5,705,000 Westgate recognizes revenue over time according to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT