2021 | 2022 | 2023 | |
Revenue | $ 2,900,000 | $ 4,500,000 | $ 2,600,000 |
Gross profit | $ 290,000 | $ 1,338,000 | $ 369,200 |
Working
Working | 2021 | 2022 | 2023 | |
A | Contract Price | $ 10,000,000 | $ 10,000,000 | $ 10,000,000 |
B | Cost Incurred to Date | $ 2,610,000 | $ 5,772,000 | $ 8,002,800 |
C | Estimated cost yet to be incurred to complete the contract | $ 6,390,000 | $ 2,028,000 | $ 0 |
D = B+C | Total Cost | $ 9,000,000 | $ 7,800,000 | $ 8,002,800 |
E = (D/B) x 100 | % of Completion | 29% | 74% | 100% |
F = A x E | Revenue to date | $ 2,900,000 | $ 7,400,000 | $ 10,000,000 |
G | Revenue of Previous year | $ 0 | $ 2,900,000 | $ 7,400,000 |
H = F - G | Net Revenue this year | $ 2,900,000 | $ 4,500,000 | $ 2,600,000 |
I | Cost to date | $ 2,610,000 | $ 5,772,000 | $ 8,002,800 |
J | Cost to date of previous year | $ 0 | $ 2,610,000 | $ 5,772,000 |
K = I - J | Net Cost for the year | $ 2,610,000 | $ 3,162,000 | $ 2,230,800 |
L = H - K | Gross Profits | $ 290,000 | $ 1,338,000 | $ 369,200 |
show working please et to search No results < > Options 6C - LT Contracts Saved...
please demonstate working and calculations ext to search No results > Options - 6C - LT Contracts Help Save & Exit Check Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,600,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below. Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 2022 $ 348,800 $1,995,800 1,392,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,610,000 6,390,000 2,100,000 1,850,000 $3,162,000 2,028,000 3,672,000 3,000,000 $2,230,800 4,228,000 5,150,000...
lis the jorrnal entries for 2021,2022,2023 Saved Help I Contracts Required information (The following information applies to the questions displayed below) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,239,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000...
olued HW 1 Saved Help (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: of 5 cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,604,000 5,796,000 2,040,000 1,820,000 2023 $1,940,400 2022 $4,032,000...
urgent plz olued HW 1 Saved Help (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: of 5 cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,604,000 5,796,000 2,040,000 1,820,000 2023 $1,940,400...
Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,926,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000 1,840,000 2022 $2,300,000 2,660,000 2,860,000 2,800,000 5,060,000 5,360,000 Westgate recognizes revenue over time according to percentage of completion. Problem...
! Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000...