Question
lis the jorrnal entries for 2021,2022,2023
Saved Help I Contracts Required information (The following information applies to the questions displayed below) In 2021, the
Her 6C - LT Contracts Required information U JU U RELY JUSTRU ES REVO LUDUR no entry is required for a transaction/event, sel
Required information in the journal below, complete the necessary journal entries for the year 2022 (Credit Various accounts
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Calculations :

1)

2021 2022 2023
Beginning work in process cost 0 2610000 5772000
Cost incurred during the year 2610000 3162000 2230800
Total cost incurred till date (A) 2610000 5772000 8002800
Estimate cost to complete (B) 6390000 2028000 0
Total cost of project [C=A+B] 9000000 7800000 8002800
% of completion [A/C] 2610000/9000000= 29%

5772000/7800000

74%

8002800/8002800

100%

2)

2021 2022 2023
Contract revenue 10000000 10000000 10000000
less:Total cost to complete -9000000 -7800000 -8002800
Gross profit 1000000 2200000 1997200
% of Gross profit to be recognized till date 1000000*29%= 290000 2200000*74%= 1628000 1997200*100%=1997200
less:Gross profit recognized in earlier years 0 -290000 -1628000
Gross profit to be recognized in current year 290000 1338000 369200

2a)

Date Account title Debit credit
1 construction in progress 2610000
Various accounts payable 2610000
2 Accounts receivable 2100000
Billings on construction contract 2100000
3 cash 1850000
Accounts receivable 1850000
4 construction expense 2610000
construction in progress 290000
revenue from long term contract (10000000*29%) 2900000

2b)

Date Account title Debit credit
1 construction in progress 3162000
Various accounts payable 3162000
2 Accounts receivable 3672000
Billings on construction contract 3672000
3 cash 3000000
Accounts receivable 3000000
4 construction expense 3162000
construction in progress 1338000
revenue from long term contract 4500000

2c)

Date Account title Debit credit
1 construction in progress 2230800
Various accounts payable 2230800
2 Accounts receivable 4228000
Billings on construction contract 4228000
3 cash 5150000
Accounts receivable 5150000
4 construction expense 2230800
construction in progress 369200
revenue from long term contract 2600000
5 (on completing the project) Billings on construction contract 10000000
construction in progress 10000000
Add a comment
Know the answer?
Add Answer to:
lis the jorrnal entries for 2021,2022,2023 Saved Help I Contracts Required information (The following information applies...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • U solo. Il does not indicate Required information [The following information applies to the questions displayed...

    U solo. Il does not indicate Required information [The following information applies to the questions displayed below) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,238,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,619,000 6,390,000 2,100,000 1,850,000 2022...

  • Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...

  • Return to question Required information (The following information applies to the questions displayed below! Part 2...

    Return to question Required information (The following information applies to the questions displayed below! Part 2 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: points 2023 $3,849,200 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,581,000 6,319,000 2,090,000...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Constr...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,610,000 6,390,000 2,100,000 1,850,000 $3,162,000 2,028,000 3,672,000 3,000,000 $2,230,800 4,228,000 5,150,000...

  • show working please et to search No results < > Options 6C - LT Contracts Saved...

    show working please et to search No results < > Options 6C - LT Contracts Saved Help Save Ti ne following information applies to the questions displayed below In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,238,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year...

  • The following information applies to the questions displayed below .] In 2021, the Westgate Construction Company...

    The following information applies to the questions displayed below .] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:     2021 2022 2023 Cost incurred during the year $2,550,000   $4,250,000   $ 1,870,000  Estimated costs to complete as of year-end 5,950,000     1,700,000     0  Billings during the year 2,050,000    4,750,000    3,200,000  Cash collections during the year   1,825,000     4,100,000    4,075,000   Westgate recognizes...

  • The journal has to be done for all years! ! Required information (The following information applies...

    The journal has to be done for all years! ! Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,424, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,204,000 5,396,000 2,140,000 1,870,000 2022 $3,192,000 2,204,000 3,256,000 3,200,000 4,604,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT