Calculations :
1)
2021 | 2022 | 2023 | |
Beginning work in process cost | 0 | 2610000 | 5772000 |
Cost incurred during the year | 2610000 | 3162000 | 2230800 |
Total cost incurred till date (A) | 2610000 | 5772000 | 8002800 |
Estimate cost to complete (B) | 6390000 | 2028000 | 0 |
Total cost of project [C=A+B] | 9000000 | 7800000 | 8002800 |
% of completion [A/C] | 2610000/9000000= 29% |
5772000/7800000 74% |
8002800/8002800 100% |
2)
2021 | 2022 | 2023 | |
Contract revenue | 10000000 | 10000000 | 10000000 |
less:Total cost to complete | -9000000 | -7800000 | -8002800 |
Gross profit | 1000000 | 2200000 | 1997200 |
% of Gross profit to be recognized till date | 1000000*29%= 290000 | 2200000*74%= 1628000 | 1997200*100%=1997200 |
less:Gross profit recognized in earlier years | 0 | -290000 | -1628000 |
Gross profit to be recognized in current year | 290000 | 1338000 | 369200 |
2a)
Date | Account title | Debit | credit |
1 | construction in progress | 2610000 | |
Various accounts payable | 2610000 | ||
2 | Accounts receivable | 2100000 | |
Billings on construction contract | 2100000 | ||
3 | cash | 1850000 | |
Accounts receivable | 1850000 | ||
4 | construction expense | 2610000 | |
construction in progress | 290000 | ||
revenue from long term contract (10000000*29%) | 2900000 |
2b)
Date | Account title | Debit | credit |
1 | construction in progress | 3162000 | |
Various accounts payable | 3162000 | ||
2 | Accounts receivable | 3672000 | |
Billings on construction contract | 3672000 | ||
3 | cash | 3000000 | |
Accounts receivable | 3000000 | ||
4 | construction expense | 3162000 | |
construction in progress | 1338000 | ||
revenue from long term contract | 4500000 | ||
2c)
Date | Account title | Debit | credit |
1 | construction in progress | 2230800 | |
Various accounts payable | 2230800 | ||
2 | Accounts receivable | 4228000 | |
Billings on construction contract | 4228000 | ||
3 | cash | 5150000 | |
Accounts receivable | 5150000 | ||
4 | construction expense | 2230800 | |
construction in progress | 369200 | ||
revenue from long term contract | 2600000 | ||
5 (on completing the project) | Billings on construction contract | 10000000 | |
construction in progress | 10000000 |
lis the jorrnal entries for 2021,2022,2023 Saved Help I Contracts Required information (The following information applies...
U solo. Il does not indicate Required information [The following information applies to the questions displayed below) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,238,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,619,000 6,390,000 2,100,000 1,850,000 2022...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...
Return to question Required information (The following information applies to the questions displayed below! Part 2 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: points 2023 $3,849,200 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,581,000 6,319,000 2,090,000...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,610,000 6,390,000 2,100,000 1,850,000 $3,162,000 2,028,000 3,672,000 3,000,000 $2,230,800 4,228,000 5,150,000...
show working please et to search No results < > Options 6C - LT Contracts Saved Help Save Ti ne following information applies to the questions displayed below In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,238,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year...
The following information applies to the questions displayed below .] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $2,550,000 $4,250,000 $ 1,870,000 Estimated costs to complete as of year-end 5,950,000 1,700,000 0 Billings during the year 2,050,000 4,750,000 3,200,000 Cash collections during the year 1,825,000 4,100,000 4,075,000 Westgate recognizes...
The journal has to be done for all years! ! Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,424, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,204,000 5,396,000 2,140,000 1,870,000 2022 $3,192,000 2,204,000 3,256,000 3,200,000 4,604,000...