Question

Return to question Required information (The following information applies to the questions displayed below! Part 2 of 5 In 2

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks!
Westgate Construction Company
Ans to 1 and 2 Calculation of Gross Profit
Particulars 2021 2022 2023
Contract Price         10,000,000       10,000,000         10,000,000 A
Cost Incurred during the year           2,581,000          2,347,000           3,049,200 C
Cost Incurred to date           2,581,000          4,928,000           7,977,200
(Cost incurred to date of the present year less Cost incurred to date of the previous year)
Estimated cost to complete           6,319,000          2,772,000                         -   D
Estimated total cost           8,900,000          7,700,000           7,977,200 E=C+B
(Cost Incurred to date+ Estimated cost to complete )
Percentage complete 29.00% 64.00% 100.00% F=B/E
(Cost Incurred to date/Estimated total cost)
Revenue to be recognized           2,900,000          3,500,000           3,600,000 G
(Contract Price*Percentage complete)- revenue previously recognized
Year 2021: 29% completed. Revenue recognized = 29% x $ 10,000,000 = $ 2,900,000.
Year 2022: 64% completed. Revenue recognized = 64% x $ 10,000,000 – $ 2,900,000 (previously recognized) = $ 3,500,000.
Year 2023: 100% completed. Revenue recognized = 100% x $ 10,000,000 – $ 2,900,000- $ 3,500,000 (previously recognized) = $ 3,600,000.
Gross Profit/(Loss)              319,000          1,153,000              550,800 H=G-C
Billings during the year     2,090,000.00    2,838,000.00     5,072,000.00
Cash collections during the year     1,845,000.00    2,900,000.00     5,255,000.00
2021 2022 2023
Journal Entries Debit $ Credit $ Debit $ Credit $ Debit $ Credit $
Costs Incurred CIP (Work-in-progress) 2,581,000 2,347,000     3,049,200
Cash 2,581,000 2,347,000     3,049,200
Billing Accounts Receivable 2,090,000 2,838,000     5,072,000
Billing on CIP 2,090,000 2,838,000     5,072,000
Receiving Payments Cash 1,845,000 2,900,000     5,255,000
Accounts Receivable 1,845,000 2,900,000     5,255,000
Period end adjustments for Revenue Construction Expense 2,581,000 2,347,000     3,049,200
(Gross Profit entry) CIP (Work-in-progress)      319,000 1,153,000        550,800
Construction Revenue 2,900,000 3,500,000     3,600,000
Completing the Project Billing on CIP 10,000,000
CIP (Work-in-progress) 10,000,000
Add a comment
Know the answer?
Add Answer to:
Return to question Required information (The following information applies to the questions displayed below! Part 2...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $3,849,200 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,581,000 6,319,000 2,890,000 1,845,000 2022 $2,347,000 2,772,000 2,838,000 2,900,000 5,072,000 5,255,000...

  • 13 Return to question Part 3 of 5 Required information [The following information applies to the...

    13 Return to question Part 3 of 5 Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 10 points 2023 $3,049,200 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,581,000...

  • Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,424, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,204,000 5,396,000 2,140,000 1,870,000 2022 $3,192,000 2,204,000 3,256,000 3,200,000 4,604,000...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...

  • [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...

    [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...

  • he following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...

    he following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 2,110,000 3,736,000 4,154,000 Cash collections during the year 1,855,000...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...

  • The following information applies to the questions displayed below .] In 2021, the Westgate Construction Company...

    The following information applies to the questions displayed below .] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:     2021 2022 2023 Cost incurred during the year $2,550,000   $4,250,000   $ 1,870,000  Estimated costs to complete as of year-end 5,950,000     1,700,000     0  Billings during the year 2,050,000    4,750,000    3,200,000  Cash collections during the year   1,825,000     4,100,000    4,075,000   Westgate recognizes...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...

  • lis the jorrnal entries for 2021,2022,2023 Saved Help I Contracts Required information (The following information applies...

    lis the jorrnal entries for 2021,2022,2023 Saved Help I Contracts Required information (The following information applies to the questions displayed below) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,239,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT