Question

Griffin Constructors, Inc. has consistently used the percentage-of-completion method of recognizing income. In 2018, Gri...

Griffin Constructors, Inc. has consistently used the percentage-of-completion method of recognizing income. In 2018, Griffin started work on a $49,000,000 construction contract that was completed in 2019. The following information was taken from Griffin's 2018 accounting records:

Progress billings $15,400,000

Costs incurred 14,700,000

Collections 9,600,000

Estimated costs to complete 29,400,000

How much was the Company over/under billed for the year ended December 31, 2018 (round percentage complete to 2 decimal points (example .513655555 = .51))?

a. 770,000

b. 1,633,333

c. 9,100,000

d. 5,800,000

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

% of completion of 2018 = Cost incurred / Total estimated cost = $14,700,000 / ($14,700,000 + $29,400,000) = 0.33

Revenue to be recognized for 2018 = $49,000,000*0.33 = $16,170,000

Over/Under billing for 2018 = Revenue to be recognized - Progress billing = $16,170,000 - $15,400,000 = $770,000

Hence option a is correct.

Add a comment
Know the answer?
Add Answer to:
Griffin Constructors, Inc. has consistently used the percentage-of-completion method of recognizing income. In 2018, Gri...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started...

    Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017 and 2018 are as follows:                                             2017                                    2018 Current year construction costs                                       $3,300,000                             $ 620,000 Estimated remaining costs to complete                              600,000                                   -0- Current year billings                                                            3,100,000                              1,400,000 Current year collections                                                    3,000,000                                1,500,000 Required: Calculate the following amounts for each method:               Completed Percentage-of Contract Completion                                   2017      2018    2017    2018 a) Gross Profit                                                                                              $             $           $          ...

  • Exercise 18-36 Coronado Construction Company uses the percentage-of-completion method of accounting. In 2017, Coronado began work...

    Exercise 18-36 Coronado Construction Company uses the percentage-of-completion method of accounting. In 2017, Coronado began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 -0- Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017...

  • Exercise 18-36 Marin Construction Company uses the percentage of completion method of accounting in 2017, Marin...

    Exercise 18-36 Marin Construction Company uses the percentage of completion method of accounting in 2017, Marin began work under contract E2-02, which provided for a contract price of 52,195,000. Other details follow 2017 2018 Costs incurred during the year 5695,310 $1,404,000 Estimated costs to complete, as of December 31921,690 0 Billings to date 426,000 2,195,000 Collections during the year 352,000 1,475,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in...

  • Question: Question:1.    When the percentage-of-completion method of accounting for long-term contracts, the percentage of completion used to...

    Question: Question:1.    When the percentage-of-completion method of accounting for long-term contracts, the percentage of completion used to recognize gross profit in the first year usually is determined by measuring: a. costs incurred in the first year, divided by estimated remaining costs to complete the project. b. costs incurred in the first year, divided by estimated total cost of the completed project. c. costs incurred in the first year, divided by estimated gross profit. d. none of the above.    2.As of...

  • Riverbed Construction Company uses the percentage-of-completion method of accounting. In 2017, Riverbed began work under contract...

    Riverbed Construction Company uses the percentage-of-completion method of accounting. In 2017, Riverbed began work under contract #E2-D2, which provided for a contract price of $2,195,000. Other details follow: 2017 2018 Costs incurred during the year $695,310 $1,404,000 Estimated costs to complete, as of December 31 921,690 –0– Billings to date 426,000 2,195,000 Collections during the year 352,000 1,475,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $ Revenue...

  • Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract...

    Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract #E2-D2, which provided for a contract price of $2,227,000. Other details follow: 2017 2018 Cost incurred during the year $660240 $1422000 Estimated costs to complete, as of December 31 911760 0 Billings to date 425000 2227000 Collections during the year 347000 1523000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $______________ Revenue...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,490,000 5,810,000 2,030,000 1,815,000 2019 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 3....

  • in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to...

  • Sunland Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion...

    Sunland Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1250000 each quarter. The total contract price is $18546000 and Sunland estimates total costs of $17900000. Sunland estimates that the building will take 3 years to complete, and commences construction on January 2, 2018 At December 31, 2019, Sunland Construction estimates that it is 80% complete with the building: however, the estimate of total...

  • Bob Ltd signs a contract on 1 April 2018 to build an office building. The construction...

    Bob Ltd signs a contract on 1 April 2018 to build an office building. The construction is scheduled to commence 1 July 2018 and the estimated date of completion is 30 June 2021. The cost of the building is estimated to be $155m and the total contract price is fixed at $180m. The following data relates to the construction period: For the year ended 30 June 2019 2020 2021 $’000 $’000 $’000 Costs to date 46,500 108,500 155,000 Estimated Costs...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT