Question

When using the percentage of completion method, the company - recognizes revenues and gross profit each...

When using the percentage of completion method, the company

- recognizes revenues and gross profit each period during the contract.

- accumulates construction costs only in an inventory account (Construction in Process).

- accumulates progress billings in an inventory account (Construction in Process).

- recognizes revenues and gross profit only when the contract is completed.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer- When using the percentage of completion method, the company= recognizes revenues and gross profit each period during the contract.

Explanation- When using the percentage of completion method, the company accumulates construction costs plus gross profit earned to date in an inventory account.

Add a comment
Know the answer?
Add Answer to:
When using the percentage of completion method, the company - recognizes revenues and gross profit each...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Assurning a long-term construction project makes an overall profit, during the interim years, percentage of...

    1. Assurning a long-term construction project makes an overall profit, during the interim years, percentage of completion method accounting has impact on construction company's: Income Statement ONLY X Balance Sheet ONLY BOTH Income Statement and Balance Sheet None of the above 2. When a company write-off a bad debt under GAAP, it has impact on this company's: Income Statement ONLY Balance Sheet ONLY BOTH Income Statement and Balance Sheet Cash Flow Statement ONLY х 3. For a construction company working...

  • Question: Question:1.    When the percentage-of-completion method of accounting for long-term contracts, the percentage of completion used to...

    Question: Question:1.    When the percentage-of-completion method of accounting for long-term contracts, the percentage of completion used to recognize gross profit in the first year usually is determined by measuring: a. costs incurred in the first year, divided by estimated remaining costs to complete the project. b. costs incurred in the first year, divided by estimated total cost of the completed project. c. costs incurred in the first year, divided by estimated gross profit. d. none of the above.    2.As of...

  • Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started...

    Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017 and 2018 are as follows:                                             2017                                    2018 Current year construction costs                                       $3,300,000                             $ 620,000 Estimated remaining costs to complete                              600,000                                   -0- Current year billings                                                            3,100,000                              1,400,000 Current year collections                                                    3,000,000                                1,500,000 Required: Calculate the following amounts for each method:               Completed Percentage-of Contract Completion                                   2017      2018    2017    2018 a) Gross Profit                                                                                              $             $           $          ...

  • Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract...

    Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract #E2-D2, which provided for a contract price of $2,227,000. Other details follow: 2017 2018 Cost incurred during the year $660240 $1422000 Estimated costs to complete, as of December 31 911760 0 Billings to date 425000 2227000 Collections during the year 347000 1523000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $______________ Revenue...

  • C) Compute the amount of gross profit to be recognized each year, assuming the completed-contract method...

    C) Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used. During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2017 $434,300 575,700 301,000 271,000 2018 $859,560 242,440 897,000 817,000 2019 $1,073,000 -0- 1,610,000 1,428,000 Prepare all necessary journal entries for 2018. (Credit...

  • Hollywood Construction Company recognizes revenue over time according to percentage of completion for its long term...

    Hollywood Construction Company recognizes revenue over time according to percentage of completion for its long term construction contracts. During 2018 Hollywood began work on a $3,000,000 foed-fee construction contract which was completed in 2021. The accounting records disclosed the following data at year-end: Estimated costs to complete at end of year $1,800,000 1,100,000 400,000 Cumulative contract costs incurred S 200,000 1,100,000 2,000,000 2018 2019 2020 For the 2020 year, Hollywood should have recognized gross profit on this contract of

  • Exercise 18-36 Coronado Construction Company uses the percentage-of-completion method of accounting. In 2017, Coronado began work...

    Exercise 18-36 Coronado Construction Company uses the percentage-of-completion method of accounting. In 2017, Coronado began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 -0- Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017...

  • Exercise 18-36 Marin Construction Company uses the percentage of completion method of accounting in 2017, Marin...

    Exercise 18-36 Marin Construction Company uses the percentage of completion method of accounting in 2017, Marin began work under contract E2-02, which provided for a contract price of 52,195,000. Other details follow 2017 2018 Costs incurred during the year 5695,310 $1,404,000 Estimated costs to complete, as of December 31921,690 0 Billings to date 426,000 2,195,000 Collections during the year 352,000 1,475,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in...

  • Question6. Long-term contract based on percentage of completion method (32 (4) Prepare journal entry to record...

    Question6. Long-term contract based on percentage of completion method (32 (4) Prepare journal entry to record gross profit for 2017(6 points) (5) Show at end of 2017 and 2018, what are the balance af CIP ( points) points) lim's Construction Co. has a $85,000,000 contract to build a new football stadium The project began on January 1, 2016 with an expected completion date of October 31, 2018. The following table provides infomation gathered during the construction period. Jim uses the...

  • Bramble Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Bramble Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $272,700 $466,620 $618,000 Estimated costs to complete 333,300 139,380 –0– Progress billings to date 273,000 546,000 902,000 Cash collected to date...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT