Eagle Eye Company produces two types of lenses–L7 and L9.
Single Indirect-Cost Pool System ABC System
Total direct costs. $77,500 $58,000
Total indirect costs $37,500. (a)
Total costs assigned to L7. $62,000. $49,500
Total costs assigned to L9. (b) $65,500
What is the total indirect costs (a) under ABC system?
Can you please explain step by step?
Thank you
ABC System | |||
Total cost assigned to L7 | $ 49,500 | ||
Add: | Total cost assigned to L9 | $ 65,500 | |
Total Cost | $ 1,15,000 | ||
Less: | Direct cost | $ -58,000 | |
Indirect cost (a) | $ 57,000 | ||
Therefore, (a) = $57,000 | |||
Eagle Eye Company produces two types of lenses–L7 and L9. Single Indirect-Cost Pool System ABC System...
b. The company's ABC system uses two indirect-cost pools. One cost pool is for set up costs and the other for advertising, Zany Brainy allocates set up costs to the two lamps based on setup labour-hours and advertising costs based on the direct manufacturing labour-hours. Under ABC system, determine total product cost per unit of each of the company's two products. (25 marks) Answer following questions based on the scenario of Zany Brainy: Zany Brainy Corp. manufactures two types of...
Page Break Header a. The company's simple (traditional) costing system uses a single indirect- cost pool and allocates costs to the two lamps on the basis of direct manufacturing labour-hours. Under this traditional system, determine total product cost per unit of each of the company's two products. (10 marks) b. The company's ABC system uses two indirect-cost pools. One cost pool is for set up costs and the other for advertising, Zany Brainy allocates set up costs to the two...
Zany Brainy Corp. manufactures two types of lamps, Home size and Industry size lamps. Company produces 15,000 Home size lamp and 5,000 Industry size lamps. Following is the data provided about these two products: Home size lamp Industry size lamp Total Direct Materials per unit $7 $12 Direct manufacturing labour rate per unit $12.00 $12.00 Direct labour hours per unit 0.50 0.6 Set up costs $120,000 Lamps produced per patch 200 50 Set up hour per patch 1 3 Quality...
Julio produces two types of calculator, standard and deluxe. The company is currently using a traditional costing system with machine hours as the cost driver but is considering a move to activity-based costing. In preparing for the possible switch, Julio has identified two cost pools: materials handling and setup. The collected data follow: Number of machine hours Number of material moves Number of setups Standard Model 26,100 605 65 Deluxe Model 31,100 905 555 Total estimated overhead costs are $347.760,...
Julio produces two types of calculator, standard and deluxe. The company is currently using a traditional costing system with machine hours as the cost driver but is considering a move to activity-based costing. In preparing for the possible switch, Julio has identified two cost pools: materials handling and setup. The collected data follow: Standard Model Deluxe Model Number of machine hours 26,600 31,600 Number of material moves 630 930 Number of setups 100 580 Total estimated overhead costs are $406,120,...
Pre-Built Problems a Julio produces two types of calculator, standard and deluxe. The company is currently using a traditional costing system with machine hours as the cost driver but is considering a move to activity-based costing. In preparing for the possible switch, Julio has identified two cost pools: materials handling and setup. The collected data follow Number of machine hours Number of material moves Number of setups Total estimated overhead costs are $368.360, of which $189.800 is assigned to the...
Julio produces two types of calculator, standard and deluxe. The company is currently using a traditional costing system with machine hours as the cost driver but is considering a move to activity-based costing. In preparing for the possible switch, Julio has identified two cost pools: materials handling and setup. The collected data follow. Number of machine hours Number of material moves Number of setups Standard Model 25,000 550 80 Deluxe Model 30,000 850 500 Total estimated overhead costs are $303,560,...
Julio produces two types of calculator, standard and deluxe. The company is currently using a traditional costing system with machine hours as the cost driver but is considering a move to activity-based costing. In preparing for the possible switch, Julio has identified two cost pools: materials handling and setup. The collected data follow: Number of machine hours Number of material moves Number of setups Standard Model Deluxe Model 27,000 32,000 650 950 120 600 Total estimated overhead costs are $394,160,...
E4-14 (Algo) Assigning Costs Using Traditional System, ABC System (LO 4-1, 4-3, 4-4,4-5) Julio produces two types of calculator, standard and deluxe. The company is currently using a traditional costing system with machine hours as the cost driver but is considering a move to activity-based costing. In preparing for the possible switch, Julio has identified two cost pools materials handling and setup. The collected data follow: Standard Model 26,800 Deluxe Model 31,800 Number of machine hours Number of material moves...
Jullo produces two types of calculator, standard and deluxe. The company is currently using a traditional costing system with machine hours as the cost driver but is considering a move to activity-based costing. In preparing for the possible switch, Julio has Identified two cost pools: materials handling and setup. The collected data follow: Number of machine hours Number of material moves Number of setups Standard Model 25,7ee 585 85 Deluxe Model 30,7ee 885 535 Total estimated overhead costs are $362,930,...