J K L M N 1 al Break even point = (Fixed cost+depreciation)/ Contribtion margin Depreciation = 650000 75 - 130000 Contribution margin = Revenue per unit - Variable per cost per unit So, break even point = (845000-130000)/(56-26) break even point - 32500 units 5 7 6-1) Base-case cash flows = [[|(Selling price - Variable cost) x Quantity - Fixed Costs] X (1-Tax rate)]. (Tax ratex depreciation) Base-case cash flows = [[|(56 -26) x 47000) - 845000) x (1-35/4)] + (357x 130000) Base-case cash flows 412750 Present value of cash flows - Cash flows x ((1-1/(1+r) thr) Present value of cash flows : 412750 x ((1-1/(1+10%)*5)/10%) Present value of cash flows : 1564647.2 NPV = (Present value of cash inflows) - (initial cost of project) NPV = 1564647-650000 NPV = 914647 19 -21 Final sales - Initial sales - 500 Final sales - 47000 - 500 Base-case cash flows = [[|(56 - 26) x 46500) - 845000) x (1-35/2)] + (357 x 130000) Base-case cash flows 403000 Present value of cash flows = 403000 x ((1-1/(1+10%)*5)/107) Present value of cash flows 1527687.07 NPV = (Present value of cash inflows) - (initial cost of project) NPV = 1527687.07 - 650000 = 877687.07 ANPV/AQ = (Final NPY - initial NPV)/(Final Sales - Initial Sales) ANPV/AQ = (877687.07 - 914647)/(46500 - 47000) ANPV/AQ- 73.92 36959.93 33 6-3) 34 decline in NPV = Initial NPV - Final NPV = 914647-877687.07 = NPV decline by 36959.93 35 36 C Please upload part C as a separate question; only + parts per question Please unload 37
please answer the full question nework i We are evaluating a project that costs $650,000, has...
Problem 9-1 Sensltivity Analysis and Break-Even Point We are evaluating a project that costs $650,000, has a five-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 47,000 units per year. Price per unit is $56, variable cost per unit is $26, and fixed costs are $845,000 per year. The tax rate is 35 percent, and we require a return of 10 percent on this project....
We are evaluating a project that costs $571.800. has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project Sales are projected at 80,000 units per year Price per unit is $40, variable cost per unit is $25. and fixed costs are $685,000 per year. The tax rate is 23 percent, and we require a return of 11 percent on this project 0-1. Calculate the accounting break-even point (Do...
We are evaluating a project that costs $660,000, has a five-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 69,000 units per year. Price per unit is $58, variable cost per unit is $38, and fixed costs are $660,000 per year. The tax rate is 35 percent, and we require a return of 12 percent on this project. a-1 Calculate the accounting break-even point. (Do...
We are evaluating a project that costs $611,800, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 85,000 units per year. Price per unit is $42, variable cost per unit is $29, and fixed costs are $700,000 per year. The tax rate is 21 percent, and we require a return of 10 percent on this project. a-1.Calculate the accounting break-even point. (Do not...
We are evaluating a project that costs $848,000, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 62,000 units per year. Price per unit is $40, variable cost per unit is $20, and fixed costs are $636,000 per year. The tax rate is 35 percent, and we require a return of 20 percent on this project. a. Calculate the accounting break-even point. (Do...
We are evaluating a project that costs $848,000, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 62,000 units per year. Price per unit is $40, variable cost per unit is $20, and fixed costs are $636,000 per year. The tax rate is 35 percent, and we require a return of 20 percent on this project. a. Calculate the accounting break-even point. (Do...
We are evaluating a project that costs $744,000, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 45,000 units per year. Price per unit is $60, variable cost per unit is $20, and fixed costs are $744,000 per year. The tax rate is 35 percent, and we require a return of 18 percent on this project. a. Calculate the accounting break-even point. (Do...
We are evaluating a project that costs $874,800, has a nine-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 85,000 units per year. Price per unit is $55, variable cost per unit is $39. and fixed costs are $765,000 per year. The tax rate is 24 percent, and we require a return of 11 percent on this project a-1.Calculate the accounting break-even point. (Do not...
We are evaluating a project that costs $500,000, has a life of 8 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 50,000 units per year. Price per unit is $40, variable cost per unit is $25, and fixed costs are $600,000 per year. The tax rate is 22 percent and we require a return of 12 percent on this project. a. Calculate the accounting break-even...
We are evaluating a project that costs $729,600. has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 90.000 units per year. Price per unit is $47, variable cost per unit is $34, and fixed costs are $725.000 per year. The tax rate is 21 percent, and we require a return of 11 percent on this project. G-1. Calculate the accounting break-even point. (Do...