Question

We are evaluating a project that costs $611,800, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 85,000 units per year. Price per unit is $42, variable cost per unit is $29, and fixed costs are $700,000 per year. The tax rate is 21 percent, and we require a return of 10 percent on this project. a-1.Calculate the accounting break-even point. (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) a- What is the degree of operating leverage at the accounting break-even point? (Do 2. not round intermediate calculations and round your answer to 3 decimal places, e.g, 32.161.) b-1.Calculate the base-case cash flow and NPV. (Do not round intermediate calculations. Round your cash flow answer to the nearest whole number, e.g., 32. Round your NPV answer to 2 decimal places, e.g., 32.16.) b- What is the sensitivity of NPV to changes in the quantity sold? (Do not round 2. intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) c. What is the sensitivity of OCF to changes in the variable cost figure? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)

60,569units 9.009 Break-even point a DOL 2. 2. DO b Cash flow NPV 2.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

b-1.Base-case cash flows = [ { ( Selling Price - Variable Cost) x Quantity - Fixed Costs} x ( 1 - T ) ] + Depreciation x T = [ $ { 42.00 - 29.00 ) x 85,000 - 700,000 } x ( 1 - 0.21 ) ] + $ 87,400 x 0.21 = $ 319,950 + $ 18,354 = $ 338,304.

NPV = Base-case cash flows x [ { 1 - ( 1 / 1.10 ) 7 } / 0.10 ] - Initial Investment = $ 338,304 x 4.8684 - $ 611,800 = $ 1,035,199.19

b-2. If we increase quantity sold to 86,000 units,

Cash flows = [ { $ 13 x 86,000 - 700,000 } x 0.79 } + $ 18,354 = $ 348,574.

NPV = $ 348,574 x 4.8684 - $ 611,800 = $ 1,085,197.66

Sensitivity of NPV to change in quantity sold = $ ( 1,085,197.66 - 1,035,199.19) / 1,000 = 49.99 times.

c. If variable cost decreases by $ 1,

Operating cash flows = [ { ( 42 - 28) x 85,000 - 700,000 } x 0.79} x 0.79 ] + $ 18,354 = $ 405,454

Change in Operating cash flows = $ 405,454 - $ 338,304 / - $ 85,000 = $ 67,150 / - $ 85,000 = - 0.79 times

Add a comment
Know the answer?
Add Answer to:
We are evaluating a project that costs $611,800, has a seven-year life, and has no salvage...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • We are evaluating a project that costs $571.800. has a six-year life, and has no salvage...

    We are evaluating a project that costs $571.800. has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project Sales are projected at 80,000 units per year Price per unit is $40, variable cost per unit is $25. and fixed costs are $685,000 per year. The tax rate is 23 percent, and we require a return of 11 percent on this project 0-1. Calculate the accounting break-even point (Do...

  • We are evaluating a project that costs $660,000, has a five-year life, and has no salvage...

    We are evaluating a project that costs $660,000, has a five-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 69,000 units per year. Price per unit is $58, variable cost per unit is $38, and fixed costs are $660,000 per year. The tax rate is 35 percent, and we require a return of 12 percent on this project. a-1 Calculate the accounting break-even point. (Do...

  • We are evaluating a project that costs $874,800, has a nine-year life, and has no salvage...

    We are evaluating a project that costs $874,800, has a nine-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 85,000 units per year. Price per unit is $55, variable cost per unit is $39. and fixed costs are $765,000 per year. The tax rate is 24 percent, and we require a return of 11 percent on this project a-1.Calculate the accounting break-even point. (Do not...

  • We are evaluating a project that costs $874,800, has a nine-year life, and has no salvage!...

    We are evaluating a project that costs $874,800, has a nine-year life, and has no salvage! value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 85,000 units per year. Price per unit is $55, variable cost per unit is $39. and fixed costs are $765,000 per year. The tax rate is 24 percent, and w equire a return of 11 percent on this project. 3.57 points 8-1.Calculate the accounting break-even point....

  • We are evaluating a project that costs $729,600. has an eight-year life, and has no salvage...

    We are evaluating a project that costs $729,600. has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 90.000 units per year. Price per unit is $47, variable cost per unit is $34, and fixed costs are $725.000 per year. The tax rate is 21 percent, and we require a return of 11 percent on this project. G-1. Calculate the accounting break-even point. (Do...

  • We are evaluating a project that costs $848,000, has an eight-year life, and has no salvage...

    We are evaluating a project that costs $848,000, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 62,000 units per year. Price per unit is $40, variable cost per unit is $20, and fixed costs are $636,000 per year. The tax rate is 35 percent, and we require a return of 20 percent on this project. a. Calculate the accounting break-even point. (Do...

  • We are evaluating a project that costs $744,000, has a six-year life, and has no salvage...

    We are evaluating a project that costs $744,000, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 45,000 units per year. Price per unit is $60, variable cost per unit is $20, and fixed costs are $744,000 per year. The tax rate is 35 percent, and we require a return of 18 percent on this project. a. Calculate the accounting break-even point. (Do...

  • We are evaluating a project that costs $848,000, has an eight-year life, and has no salvage...

    We are evaluating a project that costs $848,000, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 62,000 units per year. Price per unit is $40, variable cost per unit is $20, and fixed costs are $636,000 per year. The tax rate is 35 percent, and we require a return of 20 percent on this project. a. Calculate the accounting break-even point. (Do...

  • We are evaluating a project that costs $690,000, has a five-year life, and has no salvage...

    We are evaluating a project that costs $690,000, has a five-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 71,000 units per year. Price per unit is $75, variable cost per unit is $50, and fixed costs are $790,000 per year. The tax rate is 35 percent, and we require a return of 15 percent on this project. a. Calculate the accounting break-even point. (Do...

  • We are evaluating a project that costs $800,000, has an eight-year life, and has no salvage...

    We are evaluating a project that costs $800,000, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 60,000 units per year. Price per unit is $40, variable cost per unit is $20, and fixed costs are $800,000 per year. The tax rate is 35 percent, and we require a return of 10 percent on this project. a. Calculate the accounting break-even point. (Do...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT