There are two investment proposals. We will select that proposal which provides us maximum benefit and less cost as the case may be.
Proposal 1 Annual cost ($)
15 hand labor 15000
Other costs 20000
Total cost 35000
6-year cost 210000
Proposal 2 Cost of machinery 22000
Interest is paid on capital borrowed fund 4400
Labor cost for 6 labor 9000
Total cost 13400
6-year cost 80400
- Salvage VALUE -800
Maintainance cost 1800
capital repayment 22000
Net cost for the project 103400
It is better to opt proposal 2 as it is required less investment as compare with proposal 1
Add a comment
Know the answer?
Add Answer to:
7. On an investment company there are two alternatives to execute the civil work for a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Mrs. Leskoshe, VP of operations at ADM, has to make a decision between two investment alternatives....

    Mrs. Leskoshe, VP of operations at ADM, has to make a decision between two investment alternatives. First investment is to invest on Machine-A and second investment is to invest on Machine-B. Mrs. Leskoshe asked the operations manager Tim Long to provide necessary information for evaluating the two alternatives. After some research, Tim Long produces necessary information in the following table: Initial Cost Labor cost per year Maintenance cost per year Salvage value Machine A $15,000 $2,000 $4,000 Machine B $20,000...

  • A company is considering two investment alternatives. Alternative A is a new machine that costs $50,000...

    A company is considering two investment alternatives. Alternative A is a new machine that costs $50,000 and will last for ten years with no salvage value. It will save the company $5479 per year and the savings will increase by $2050 each year. Alternative B is a is a machine that will cost $75,000 and last 10 years. The salvage value at the end of 10 years is $25,000. It will save $11352 per year. Find the present worth of...

  • A company is considering two investment alternatives Alternative A is a new machine that costs $50,000...

    A company is considering two investment alternatives Alternative A is a new machine that costs $50,000 and will last for ten years with no salvage value. It will save the company $9445 per year. Alternative B is a is a machine that will cost $75,000 and last 10 years. The salvage value at the end of 10 years is $25,000. It will save $12390 per year Find the Annual worth of each alternative if the company as a MARR of...

  • My Not A company is considering two investment alternatives. Alternative A is a new machine that...

    My Not A company is considering two investment alternatives. Alternative A is a new machine that costs $50,000 and will last for ten years with no salvage value. It will save the company $8445 per year. Alternative B is a is a machine that will cost $75,000 and last 10 years. The salvage value at the end of 10 years is $25,000. It will save $11743 per year Find the Annual worth of each alternative if the company as a...

  • 7. A company has two products: Basic and Deluxe. It uses activity-based costing and has prepared...

    7. A company has two products: Basic and Deluxe. It uses activity-based costing and has prepared the following analysis showing budgeted costs and activities. 16,000 units, Annual production of Basic is 28.00 Annual production of Deluxe is - 12,000 units. Product Basie Product Deluxe Total Activity Cost Pool Budgeted Overhead Cost $ 170,000 Machining 600 Machine hours 1400 Machine Hours 800 Machine Hours 600 setups 800 setups 1400 Setups S 145,000 Setups 450 Batches 1100 Batches 650 Batches $ 160,000...

  • Harbour Company makes two models of electronic tablets, the Home and the Work. Basic production information...

    Harbour Company makes two models of electronic tablets, the Home and the Work. Basic production information follows: Home Work Direct materials cost per unit $ 44 $ 71 Direct labor cost per unit 18 34 Sales price per unit 365 574 Expected production per month 800 units 350 units Harbour has monthly overhead of $180,010, which is divided into the following cost pools: Setup costs $ 79,050 Quality control 65,760 Maintenance 35,200 Total $ 180,010 The company has also compiled...

  • Check my work Keller Company makes two models of battery-operated boats, the Sandy Beach and the...

    Check my work Keller Company makes two models of battery-operated boats, the Sandy Beach and the Rocky River. Basic production information follows: Sandy Beach Direct materials cost per unit $18.60 Direct labor cost per unit 14.80 Sales price per unit 83.40 Expected production per month 1,230 units Rocky River $ 26.40 18.30 105.00 930 units Keller has monthly overhead of $13,493, which is divided into the following cost pools: Setup costs Quality control Maintenance Total $ 3, 250 6, 283...

  • Way Cool produces two different models of air conditoners. The company produces the mechanical systems in...

    Way Cool produces two different models of air conditoners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow Process Activity Components Changeover Machining Setup 120 Overhead Driver Quantity Cost Number of $500,000 800 batches 279,000 Machine hours 6,000 225,000 Number of setups $1,004,000 $ 180, 300 Welding hours 3,000...

  • 5 Harbour Company makes two models of electronic Home and the Work. Basic production Information follows:...

    5 Harbour Company makes two models of electronic Home and the Work. Basic production Information follows: Direct materials cost per unit Direct labor cost per unit Sales price per unit Expected production per month 365 23 155 3 74 e units s Harbour hos monthly overhead of $188.980, which is divided into the following cost pool: $ 85,68 58, See Setup costs Quality control Maintenance Total The company has also complied the following information about the chosen cost drivers work...

  • Harbour Company makes two models of electronic tablets, the Home and the Work. Basic production Information...

    Harbour Company makes two models of electronic tablets, the Home and the Work. Basic production Information follows: Direct materials cost per unit Direct labor cost per unit Sales price per unit Expected production per month Home Work $ 40 $ 71 20 360 582 670 units 430 units Harbour has monthly overhead of $173,925, which is divided into the following cost pools: Setup costs Quality control Maintenance Total $ 80,850 55, 675 37, 400 $173.925 The company has also compiled...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT