Extended Learning Exercise. You have been asked to prepare a quick estimate of the construction cost for a coal-fired electricity generating plant and facilities. A work breakdown structure (levels one through three) is shown in the table below EE! Click the icon to view the work breakdown structure Click the icon to view the available information What is your estimated 2019 cost for building the coal-fired generating facility? Summarize your calculations in a cost estimating worksheet, and state the assumptions you make Summarize your calculations in a cost estimating worksheet, and state the assumptions you make. (Round the factors for elements 1.2-3, 1.4 to four decimal places and the labor factor to the nearest whole number. Round costs to the nearest ten thousands dollars.) Element Code Units/Factor Price/Unit Subtotal Totals 620 $1,800 $3,100,000 1.2-3 $121,000,000 $5,100,000 1.5.1-3 labor $62 material:s $15,000,000 1.5.4 620 $1,300 3% The total estimated costPROJECT: Coal-Fired Electricity Generating Plant and Facilities Title Line No. 001 002 003 004 005 006 007 008 009 010 011 012 013 014 015 016 017 018 019 020 021 022 023 024 025 026 027 028 029 030 031 WBS Element Code Coal-fired power plant Site Land improvements Roads, parking, and paved areas Railroads Boiler Furnace Pressure vessel Heat exchange system Generators Boier support system Coal transport system Coal pulverizing system Instrumentation and control Ash disposal system Transformers and distribution Coal storage facility Stockpile reclaim system Rail car dump Coal handling equipment Support facilities and equipment Hazardous waste systems Support equipment Utilities and communications system Security systems Project integration Project management Environmental management Project safety Quality assurance Test, start-up, and transition management 1.2 1.2.1 1.2.2 1.2.3 1.2.4 1.3.1 1.3.2 1.3.3 1.3.4 1.3.5 1.4.1 1.4.2 1.4.3 1.5.1 1.5.2 1.5.3 1.5.4 1.9.1 1.9.2 1.9.3 1.9.4 1.9.5

A coal-fired generating plant twice the size of the one you are estimating was built in 1996 The 1996 boiler (1.2) and boiler support system (1.3) cost $121 million. The cost index for boilers was 121 in 1996, it is 489 in 2019. The cost capacity factor for similar boilers and support systems is 0.91. The 620-acre site is on property you already own, but improvements (1.1.1) and roads (1.1.2) will cost $1,800 per acre, and railroads (1.1.3) will cost $3,100,000 Project integration (1.9) is projected to cost 3% of all other construction costs. The security systems (1.5.4) are expected to cost $1,300 per acre, according to recent (2019) construction of similar plants. All other support facilities and equipment (1.5) elements equipment elements for two similar generating plants. Their experience is expected to reduce labor requirements substantially: a 92% learning curve can be assumed. Viscount built the support facilities and equipment on their first job in 90,000 hours. For this project, Viscounts labor will be billed to you at $62 per hour. Viscount estimates that materials for the construction of the support facilities and equipment elements (except 1.5.4) will cost you $15,000,000 The coal storage facility (1.4) for the coal-fired generating plant built in 1996 cost $5.1 milion. Although your plant is smaller, you require the same size coal storage facility as the 1996 plant. You assume you can apply the cost index for similar boilers to the coal storage facility

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Lets calculate the estimate as per the work breakdown structure:

1.1

site

1.1.1

land improvements

2000

600

1200000

1.1.2

roads, parking, and paved areas

1.1.3

railroads

3000000

3000000

Size of the property = 600 acres

Land improvements, roads, parking, and paved areas cost 2000 $ per acre.

Land improvements, roads, parking, & paved areas cost (for 600 acre property) = 2000x600 = $ 1200000

Railroads will cost $ 3000000

1.2

boiler

110000000

4.472727

492000000

0.535887

263656271.8

1.2.1

furnace

1.2.2

pressure vessel

1.2.3

heat exchange system

1.2.4

generators

1.3

boiler support system

1.3.1

coal transport system

1.3.2

coal pulverizing system

1.3.3

instrumentation and control

1.3.4

ash disposal system

1.3.5

transformers and distribution

In 1993, cost of boiler and boiler support system in a coal fired generating plant twice the size of the one you are estimating was $ 110000000

In 2016, cost of boiler and boiler support system in a coal fired generating plant twice the size of the one you are estimating is = 110000000x(492/110) = 110000000x4.472727 = $ 492000000

where cost index for boilers in 2016 is 492 and cost index for boilers in 1993 was 110. Therefore, cost index is 4.472727

In 2016, cost of boiler and boiler support system in a coal fired generating plant half the size of the 1993 plant is determined by the formula

C2 = C1{Q2/Q1}^a

Where C2 = Cost at desired size

C1=Cost at reference size in today’s date=$492000000

Q2=Capacity at desired size=1

Q1=Capacity at reference size=2

a=Cost Capacity Factor=0.9

Therefore C2=492000000x0.535887=$263656271.8

1.4

coal storage facility

5000000

4.472727

22363636.36

1.4.1

stockpile reclaim system

1.4.2

rail car dump

1.4.3

coal handling equipment

Cost of coal storage facility in 1993 = $ 5000000

Cost of same size coal storage facility in 2016 = 5000000x4.472727 = $ 22363636.36

where cost index in 2016 is 492 and cost index in 1993 was 110. Therefore, cost index is 4.472727

1.5

support facilities and equipment

85500

60

5130000

15000000

20130000

1.5.1

hazardous waste systems

1.5.2

support equipment

1.5.3

utilities and communication systems

1.5.4

security systems

1500

600

900000

Total number of hours required to build support facilities and equipment =95000*90% = 85500 hours

Labor cost per hour to build support facilities and equipment = $ 60 per hour

Total labor cost to build support facilities and equipment = 85500x60= $ 5130000

Cost of material for the construction of support facilities and equipment = 15000000

Total cost for the construction of support facilities and equipment = $ 20130000

Costs of security systems = 1500x600 = $ 900000

1.9

project integration

3%

31693636

950809.0909

1.9.1

project management

1.9.2

environmental management

1.9.3

project safety

1.9.4

quality assurance

1.9.5

test, start-up, and transition management

Project integration cost = 3% of all other construction costs.

Assuming all other construction costs include = construction cost of coal storage facility + construction cost of support facilities and equipment + construction cost of railroads + construction cost of Land improvements, roads, parking, and paved areas.

Therefore all other construction costs = $ 31693636

Project integration costs = 3%(31693636) = $950809.0909

Adding all the costs, we get

Estimated 2016 cost for building the coal fired generating faciliity = 1200000+3000000+263656271.8+22363636.36+20130000+900000+950809.0909 = $ 312200717.2

Add a comment
Know the answer?
Add Answer to:
Extended Learning Exercise. You have been asked to prepare a quick estimate of the construction cost...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A Lump of Coal for Christmas You have recently been promoted to audit senior at an...

    A Lump of Coal for Christmas You have recently been promoted to audit senior at an international accounting firm, lontana Power Company (MPC), a NYSE client. You were asked to a major portion of the work at Western Energy Co. (WECо), a wholly-owned subsidiary of MPC. Most of the audit work has already been done, but you must stu trip to the site to complete a few procedures. There are some serious audit issues to contend with this year, but...

  • You have been hired as new analyst at Foxconn Interconnect Technology Limited (FIT) and have been...

    You have been hired as new analyst at Foxconn Interconnect Technology Limited (FIT) and have been asked to evaluate the new manufacturing plant to produce new state of art internet security system. Suppose that FIT is considering expanding its wireless home networking appliance, called EasyNet, that will provide both the hardware and the software necessary to run an entire home from any Internet connection. EasyNet will also control new Internet-capable stereos, digital video recorders, heating and air-conditioning units, major appliances,...

  • Suppose you have been hired as a financial consultant to Defense Electronics, Inc. (DEI), a large, publicly traded firm that is the market share leader in radar detection systems (RDSs). The company i...

    Suppose you have been hired as a financial consultant to Defense Electronics, Inc. (DEI), a large, publicly traded firm that is the market share leader in radar detection systems (RDSs). The company is looking at setting up a manufacturing plant overseas to produce a new line of RDSs. This will be a five-year project. The company bought some land three years ago for $2.9 million in anticipation of using it as a toxic dump site for waste chemicals, but it...

  • Summary should briefly analyze the central problems and issues of the case and provide some analysis...

    Summary should briefly analyze the central problems and issues of the case and provide some analysis and suggestions. Thank you. Lean Initiatives and Growth at Orlando Metering Company It was late August 2002 and Ed Cucinelli, vice president of Orlando Metering Company (OMC), sat in his office on a late Saturday morning. He had come in to prepare for some strategic planning meetings that were scheduled for the upcoming week. As he noticed the uncommon silence in the building, Ed...

  • I have this case study to solve. i want to ask which type of case study...

    I have this case study to solve. i want to ask which type of case study in this like problem, evaluation or decision? if its decision then what are the criterias and all? Stardust Petroleum Sendirian Berhad: how to inculcate the pro-active safety culture? Farzana Quoquab, Nomahaza Mahadi, Taram Satiraksa Wan Abdullah and Jihad Mohammad Coming together is a beginning; keeping together is progress; working together is success. - Henry Ford The beginning Stardust was established in 2013 as a...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT