Question

A project that costs $2,800 to Install will provide annual cash flows of $780 for each of the next 6 years. a Calculate the N
0 0
Add a comment Improve this question Transcribed image text
Answer #1
a
Project
Discount rate 0.1
Year 0 1 2 3 4 5 6
Cash flow stream -2800 780 780 780 780 780 780
Discounting factor 1 1.1 1.21 1.331 1.4641 1.61051 1.771561
Discounted cash flows project -2800 709.0909 644.6281 586.0255 532.7505 484.3186 440.2897
NPV = Sum of discounted cash flows
NPV Project = 597.1
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
b. Accept project as NPV is positive
c
Project
IRR is the rate at which NPV =0
IRR 0.169940258
Year 0 1 2 3 4 5 6
Cash flow stream -2800 780 780 780 780 780 780
Discounting factor 1 1.16994 1.36876 1.601368 1.8735045 2.191888 2.564378
Discounted cash flows project -2800 666.7007 569.8588 487.0836 416.33206 355.8575 304.1673
NPV = Sum of discounted cash flows
NPV Project = 6.91653E-07
Where
Discounting factor = (1 + IRR)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 17%
Accept project as IRR is more than discount rate
Add a comment
Know the answer?
Add Answer to:
A project that costs $2,800 to Install will provide annual cash flows of $780 for each...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A project that costs $3,100 to install will provide annual cash flows of $810 for each...

    A project that costs $3,100 to install will provide annual cash flows of $810 for each of the next 6 years. a. Calculate the NPV if the opportunity cost of capital is 11%? (Do not round intermediate calculations. Round your answer to 2 decimal places.)   NPV $    b. Is this project worth pursuing? Yes No c. What is the project's internal rate of return IRR? (Do not round intermediate calculations. Round your answer to 2 decimal places.)   IRR %

  • A project that costs $3,200 to Install will provide annual cash flows of $820 for each...

    A project that costs $3,200 to Install will provide annual cash flows of $820 for each of the next 7 years. a. Calculate the NPV if the opportunity cost of capital is 12%? (Do not round Intermediate calculations. Round your answer to 2 decimal places.) NPV $ b. Is this project worth pursuing? Yes NO c. What is the project's Internal rate of return IRR? (Do not round Intermediate calculations. Round your answer to 2 decimal places.)

  • NPV and IRR A project that costs $712,277.54 to install will provide annual cash flows of...

    NPV and IRR A project that costs $712,277.54 to install will provide annual cash flows of $144,000.00 for each of the next 9 years. a. Calculate the NPV if the discount rate is 7.40%? (Do not round intermediate calculations. Round your answer to 2 decimal places.)   NPV $    b. Is this project worth pursuing? Yes No c. How high can the discount rate be before you would reject the project (i.e. What is the projects IRR)? (Do not round intermediate...

  • NEO A project that costs $3,700 to install will provide annual cash flows of $1150 for...

    NEO A project that costs $3,700 to install will provide annual cash flows of $1150 for each of the next 6 years. a. What is NPV if the discount rate is 11%? (Do not round intermediate calculations. Round your answer to 2 decimal places.) NPV b. How high can the discount rate be before you would reject the project? (Do not round Intermediate calculations. Enter your answer as a percent rounded to 2 decimal places.) Discount rate 5

  • A project that provides annual cash flows of $2,650 for nine years costs $10,900 today. At...

    A project that provides annual cash flows of $2,650 for nine years costs $10,900 today. At a required return of 8 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV At a required return of 24 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2...

  • A project that will provde annual cash flows of $2,750 for nine years costs $9.000 today,...

    A project that will provde annual cash flows of $2,750 for nine years costs $9.000 today, a. At a required return of 10 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 29 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer...

  • A project that provides annual cash flows of $2,620 for eight years costs $9,430 today. a....

    A project that provides annual cash flows of $2,620 for eight years costs $9,430 today. a. At a required return of 8 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 24 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to...

  • A project that will provde annual cash flows of $2,550 for nine years costs $10,500 today....

    A project that will provde annual cash flows of $2,550 for nine years costs $10,500 today. a. At a required return of 11 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 27 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer...

  • A project that will provde annual cash flows of $3,000 for nine years costs $10,000 today....

    A project that will provde annual cash flows of $3,000 for nine years costs $10,000 today. a. At a required return of 10 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 28 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer...

  • The following are the cash flows of two projects: Year Project A Project B 0 −$260...

    The following are the cash flows of two projects: Year Project A Project B 0 −$260        −$260        1 140        160        2 140        160        3 140        160        4 140        a. If the opportunity cost of capital is 11%, calculate NPV for both projects? (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project NPV          A $    B    b. Which of these projects is worth pursuing if you...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT