Question

DRUMMOND’s Camera Shop has prepared the following flexible budget for September and is in the process...

DRUMMOND’s Camera Shop has prepared the following flexible budget for September and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance.

                                                               Flexible                ------------Variances-------------

                                                                Budget                      Price                 Efficiency

            Material A                                   $20,000                  $1,000F                    $3,000U

            Material B                                     30,000                      500U                      1,500F

            Direct manufacturing labor             40,000                      500U                      2,500F

[Please note that Flexible Budget is the same as standard costs of material or labor at actual production. Also Price is the same as Rate (for labor) and Efficiency is the same as Quantity (for material)]

46     The MOST likely explanation of the above variances for Material A is that

                  A)     a lower price than expected was paid for Material A.

                  B)     higher-quality raw materials were used than were planned.

                  C)     the company used a higher-priced supplier.

                  D)     Material A used during September was $2,000 less than expected.

                  E)      none of the above

47.                  The actual amount spent for Material B was

                        A)       $28,000.

                        B)       $29,000.

                        C)       $30,000.

                        D)       $31,000.

                        E)       none of the above

48.             The MOST likely explanation of the above direct manufacturing labor variances is that

                  A)     the average wage rate paid to employees was less than expected.

                  B)     employees did not work as efficiently as expected to accomplish the job.

                  C)     the company may have assigned more experienced employees this month than originally

                           planned.

                  D)     management may have a problem with budget slack and be using lax standards for both labor-wage rates and expected efficiency.

                  E)      none of the above

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Question 46

Option A is correct

Question 47

Amount spent on material B= 30000-500+1500= 29000 Therefore option B is correct

Question 48

Option C is correct.

Add a comment
Know the answer?
Add Answer to:
DRUMMOND’s Camera Shop has prepared the following flexible budget for September and is in the process...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Handley Manufacturing Company has prepared the following flexible budget for August and is in the process...

    Handley Manufacturing Company has prepared the following flexible budget for August and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance. Flexible Variances Budget Price Efficiency Material A $ 50 comma 000$50,000 $ 2 comma 000$2,000F $ 4 comma 000$4,000U Material B 62 comma 00062,000 300300U 1 comma 6001,600F Direct manufacturing labor 80 comma 00080,000 700700U 2 comma 3002,300F The most likely explanation of the above direct manufacturing labor variances...

  • 2. Materials Variance Analysis (30 points) Midend's Camera Shop has prepared the following flexible budget for Sept...

    2. Materials Variance Analysis (30 points) Midend's Camera Shop has prepared the following flexible budget for September and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance. Material A Material B Material C Flexible Budget $15,000 37,000 21,000 Variances Price Efficiency $500F $1,800U 1,600U 900U 1,300U 1,900F a. Calculate the actual amount spent for Material A, B and C. b. Generate three potential explanations for the variances identified for each...

  • Polly's Pizza Manufacturing prepared the a flexible budget for last month. Some of the variance analyses...

    Polly's Pizza Manufacturing prepared the a flexible budget for last month. Some of the variance analyses are reported below. "F" denotes a favorable variance and "U" denotes an unfavorable variance.                          Flexible   Variances                           Budget     Price     Efficiency Direct labor         7,500    112U      750F The actual amount spent for direct manufacturing labor was: Question 20 options: a) $6,638 b) $ 8,128 c) $8,362 d) $6,862

  • 1.Which of the following remains the same when comparing a flexible budget to a master budget?...

    1.Which of the following remains the same when comparing a flexible budget to a master budget? Total sales. Net income. Total variable costs. Total fixed costs. None of the answer choices is correct. 2.When ideal standards are used, which of the following is most likely true? The standards are not likely to be achieved. The standards allow for occasional downtime for equipment. The standards reflect what really happens in the factory. The standards motivate employees to achieve perfection. None of...

  • 1. Prepare the flexible budget using the information provided. Show calculations/explain where the numbers come from....

    1. Prepare the flexible budget using the information provided. Show calculations/explain where the numbers come from. 2. Answer the corresponding questions about the variances of the budget. Class Exercise for Standard Cost BUDGET 10,000 FLEXIBLE Units of output planned and actual ACTUAL 9,000 Direct material units per unit of output units price Labor units per unit of output hours rate Sales 300,000 306,000 Less variable costs of manufacturing Direct Material Direct Labor Factory Overhead Total 120,000 40,000 60,000 220,000 117,000...

  • Standard Cost and Flexible Budget. Brier Company produces car covers. The company's master budget shows the...

    Standard Cost and Flexible Budget. Brier Company produces car covers. The company's master budget shows the following standards information. Expected production for September 5,000 units 29. Direct materials 8 yards per unit at $5 per yard Direct labor 3 hours per unit at $16 per hour Variable manufacturing overhead Required: a. Caleulate the standard cost per unit for direct materials, direct labor, and variable manufacturing overhead using the format shown in Figure 10.1. 3 direct labor hours per unit at...

  • Rain Gear, Inc., produces rain jackets. The master budget shows the following standards information and indicates...

    Rain Gear, Inc., produces rain jackets. The master budget shows the following standards information and indicates the company expected to produce and sell 28,000 units for the year. Variable manufacturing overhead is allocated based on direct labor hours. Direct materials 4 yards per unit at $3 per yard Direct labor 2 hours per unit at $10 per hour Variable mfg OH 2 direct labor hours per unit at $4 per hour Rain Gear actually produced and sold 30,000 units for...

  • Problem 15-21 Determining and interpreting flexible budget variances LO 15-5 Campbell Publications established the following standard...

    Problem 15-21 Determining and interpreting flexible budget variances LO 15-5 Campbell Publications established the following standard price and costs for a hardcover picture book that the company produces. $ Standard price and variable costs Sales price Materials cost Labor cost Overhead cost Selling, general, and administrative costs Planned fixed costs Manufacturing overhead Selling, general, and administrative 36.40 8.10 4.20 5.80 7.10 $131,000 54.000 Assume that Campbell actually produced and sold 34,000 books. The actual sales price and costs incurred follow....

  • Control measures should t of Select one: A. be set by excluding nonfinancial information B. be...

    Control measures should t of Select one: A. be set by excluding nonfinancial information B. be linked by feedback to help learning and future planning C. be kept confidential from employees so that competitors don't have an opportunity to gain a competitive advantage D. be set and not changed until the next budget cycle so as to provide an effective benchmark uestion stion 8 Midend's Camera Shop has prepared the following flexible budget for September and is in the process...

  • Problem 8-21A Determining and interpreting flexible budget variances Use the standard price and cost data supplied...

    Problem 8-21A Determining and interpreting flexible budget variances Use the standard price and cost data supplied in Problem 8-20A. Assume that Narcisco actually produced and sold 32,000 books. The actual sales price and costs incurred follow. Required Determine the flexible budget variances. Provide another name for the fixed cost flexible budget variances. Indicate whether each variance is favorable (F) or unfavorable (U). Identify the management position responsible for each variance. Explain what could have caused the variance. Problem 8-20A Determining...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT