Question

Handley Manufacturing Company has prepared the following flexible budget for August and is in the process...

Handley Manufacturing Company has prepared the following flexible budget for August and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance.

Flexible

Variances

Budget

Price

Efficiency

Material A

$ 50 comma 000$50,000

$ 2 comma 000$2,000F

$ 4 comma 000$4,000U

Material B

62 comma 00062,000

300300U

1 comma 6001,600F

Direct manufacturing labor

80 comma 00080,000

700700U

2 comma 3002,300F

The most likely explanation of the above direct manufacturing labor variances is that​ ________.

A.

the average wage rate paid to employees was less than expected

B.

the company may have assigned more experienced employees this month than originally planned

C.management may have a problem with budget slack and might be using lax standards for both

labor−wage rates and expected efficiency

D.

employees did not work as efficiently as expected to accomplish the job

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The given details regarding Direct Manufacturing Labor Costs are as follows :-

Flexible Budget :- 80,000

Direct Manufacturing Labor Price Variance = 70,700 ( Un-favorable )

Direct Manufacturing Labor Efficiency Variance = 2,300 ( Favorable )

While interpreting the Variance results, we have to understand what scenario or situation any given variance is depicting.

It can be seen that the Direct Manufacturing Labor Price Variance is Unfavorable, which denotes that the Actual Price of Direct Manufacturing Labor was more that the Standard or the budgeted Direct Manufacturing Labor Cost. The increased cost can be due to many factors like, Labor is called specially from a far off location or may be we use excessively skilled labor to get our works done and so we may have t pay Labor costs more than the budgeted once.

It can also be seen that the Direct Manufacturing Labor Efficiency Variance is Favorable, which states that the Actual Quantity Produced is more that the Standard/Estimated Quantity.

Hence, we have to look for the option that can justify the above mentioned logics/explanations.

The suitable Solution looks like the Option B. As it says company may have assigned more experienced labor, which justifies the increased Actual Labor Costs hence giving an un-favorable Direct Manufacturing Labor Variance and also enhanced Actual Production than the standard Quantity, and hence a favorable Labor Efficiency Variance.

  1. Average wage rate if paid less, then the Price Variance should be Favorable but the Price Variance is Un-favorable, hence this is not our solution.
  2. This is our solution.
  3. Budget Slackness is not a justified reason in most of the scenarios as the Budget is always an estimate and it is never meant to be accurate.
  4. It says labor may have not worked as efficiently. But we have a favorable Efficiency Variance hence this explanation also does not fit the Variances given
Add a comment
Know the answer?
Add Answer to:
Handley Manufacturing Company has prepared the following flexible budget for August and is in the process...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • DRUMMOND’s Camera Shop has prepared the following flexible budget for September and is in the process...

    DRUMMOND’s Camera Shop has prepared the following flexible budget for September and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance.                                                                Flexible                ------------Variances-------------                                                                 Budget                      Price                 Efficiency             Material A                                   $20,000                  $1,000F                    $3,000U             Material B                                     30,000                      500U                      1,500F             Direct manufacturing labor             40,000                      500U                      2,500F [Please note that Flexible Budget is the same as standard costs of material or labor at actual production. Also Price is the same...

  • Polly's Pizza Manufacturing prepared the a flexible budget for last month. Some of the variance analyses...

    Polly's Pizza Manufacturing prepared the a flexible budget for last month. Some of the variance analyses are reported below. "F" denotes a favorable variance and "U" denotes an unfavorable variance.                          Flexible   Variances                           Budget     Price     Efficiency Direct labor         7,500    112U      750F The actual amount spent for direct manufacturing labor was: Question 20 options: a) $6,638 b) $ 8,128 c) $8,362 d) $6,862

  • 2. Materials Variance Analysis (30 points) Midend's Camera Shop has prepared the following flexible budget for Sept...

    2. Materials Variance Analysis (30 points) Midend's Camera Shop has prepared the following flexible budget for September and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance. Material A Material B Material C Flexible Budget $15,000 37,000 21,000 Variances Price Efficiency $500F $1,800U 1,600U 900U 1,300U 1,900F a. Calculate the actual amount spent for Material A, B and C. b. Generate three potential explanations for the variances identified for each...

  • 1. Prepare the flexible budget using the information provided. Show calculations/explain where the numbers come from....

    1. Prepare the flexible budget using the information provided. Show calculations/explain where the numbers come from. 2. Answer the corresponding questions about the variances of the budget. Class Exercise for Standard Cost BUDGET 10,000 FLEXIBLE Units of output planned and actual ACTUAL 9,000 Direct material units per unit of output units price Labor units per unit of output hours rate Sales 300,000 306,000 Less variable costs of manufacturing Direct Material Direct Labor Factory Overhead Total 120,000 40,000 60,000 220,000 117,000...

  • Data Table Total Flexible Budget Product Cost Variance Total Direct Materials Variance Total Manufacturing Overhead Variance...

    Data Table Total Flexible Budget Product Cost Variance Total Direct Materials Variance Total Manufacturing Overhead Variance (0) Total Direct Labor Variance (c) Direct Labor Direct Labor Cost Variance Efficiency Variance $ 180 U $ 305 F (b) Direct Materials Efficiency Variance $ 145 U Direct Materials Cost Variance $ 520 F Total Variable Overhead Variance Total Fixed Overhead Variant Fixed Overhead (e) Variable Overhead Cost Variance 5750 Variable Overhead Efficiency Variance $ 600 F Cost Variance $ 125 F Print...

  • o You have been invited to interview for an internship with an international food manufacturing company....

    o You have been invited to interview for an internship with an international food manufacturing company. When you arrive for the interview, you are given the following information related to a fictitious Belgian chocolatier for the month of June. (Click the icon to view the data.) Read the requirements Requirement 1. Calculate the materials efficiency and price variance and the wage and labor efficiency variances for the month of May. In order to calculate the variances complete the following table....

  • Q4) Direct materials and direct manufacturing labor variances. (25 Marks} Rugged Life, Inc., designs and manufactures...

    Q4) Direct materials and direct manufacturing labor variances. (25 Marks} Rugged Life, Inc., designs and manufactures fleece quarter-zip jackets. It sells its jackets to brand-name outdoor Outfitters in lots of one dozen. Rugged Life's May 2017 static budget and actual results for direct inputs are as follows: Static Budget Number of jacket lots (1 lot = 1 300 dozen) Per Lot of Jackets: Direct materials Direct manufacturing labor 18 yards at $4.65 per yard $83.70 2.4 hours at $12.50 per...

  • Carol Lou, Inc. designs and manufactures fleece quarter-zip jackets. It sells its jackets to brand-name outdoor...

    Carol Lou, Inc. designs and manufactures fleece quarter-zip jackets. It sells its jackets to brand-name outdoor Outfitters in lots of one dozen. Carol Lou's May 2017 static budget and actual results for direct inputs are as follows: E (Click the icon to view the data.) (Click the icon to view additional information.) Read the requirements. Requirement 1. Calculate the direct materials and direct manufacturing labor price and efficiency variances in May 2017. What is the total flexible-budget variance for both...

  • 04) Direct materials and direct manufacturing labor variances. {25 Marks) Rugged Life, Inc., designs and manufactures...

    04) Direct materials and direct manufacturing labor variances. {25 Marks) Rugged Life, Inc., designs and manufactures fleece quarter-zip jackets. It sells its jackets to brand-name outdoor outfitters in lots of one dozen. Rugged Life's May 2017 static budget and actual results for direct inputs are as follows: Statie Budget Number of jacket lots (I lot - 1 300 dozen) Per Lot of Jackets: Direct materials 18 yards at 54.65 per yard = $83.70 Direct manufacturing labor 24 hours at $12.50...

  • Q4)Direct materials and direct manufacturing labor variances. (25 Marks) Rugged Life, Inc., designs and manufactures fleece...

    Q4)Direct materials and direct manufacturing labor variances. (25 Marks) Rugged Life, Inc., designs and manufactures fleece quarter-zip jackets. It sells its jackets to brand-name outdoor outfitters in lots of one dozen. Rugged Life's May 2017 static budget and actual results for direct inputs are as follows: Static Budget Number of jacket lots (1 lot = 1 300 ddzen) Per Lot of Jackets: Direct materials 18 yards at $4.65 per yard = $83.70 2.4 hours at $12.50 per hour = $30.00...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT