The Lakeside Company uses a weighted-average process costing system. The following data are available:
Beginning inventory | -0- | ||
Units started in production | 20,000 | ||
Units finished during the period | 16,000 | ||
Units in process
at the end of the period (complete as to materials, ¼ complete as to labor and overhead) |
4,000 |
||
Cost of materials used | $ | 35,200 | |
Labor and overhead costs | $ | 37,400 | |
Total cost of the 4,000 units of the ending inventory:
Multiple Choice
$9,240.
$14,520.
$8,910.
$15,840.
Correct answer----------$9,240
Working
Statement of Equivalent Units(Weighted average) | |||||||
Material | Conversion cost | ||||||
Units | Complete % | Equivalent units | Complete % | Equivalent units | |||
Transferred | 16,000 | 100% | 16,000.0 | 100% | 16,000 | ||
Closing WIP | 4,000 | 100% | 4,000.0 | 25% | 1,000 | ||
Total | 20,000 | Total | 20,000.0 | Total | 17,000 |
.
Cost per Equivalent Units (Weighted average) | ||||
COST | Material | Conversion cost | TOTAL | |
Beginning WIP Inventory Cost | $ 0 | |||
Cost incurred during period | $ 35,200 | $ 37,400 | $ 72,600 | |
Total Cost to be accounted for | $ 35,200 | $ 37,400 | $ 72,600 | |
Total Equivalent Units | 20,000 | 17,000 | ||
Cost per Equivalent Units | $ 1.76 | $ 2.20 |
.
Statement of cost (Weighted average) | |||||
Cost | Equivalent Cost/unit | Ending WIP | |||
Units | Cost Allocated | ||||
Material | $ 1.76 | 4,000 | $ 7,040.00 | ||
Conversion cost | $ 2.20 | 1,000 | $ 2,200.00 | ||
TOTAL | $ 72,600 | TOTAL | $ 9,240 |
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...
The Lakeside Company uses a welghted-average process costing system. The following data are available: -0- 20,000 16,000 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 4,000 $35,200 $37,400 Total cost of the 4,000 units of the ending Inventory: Multiple Choice $9,240. $14,520. $8.910. $15,840.
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 20,000 Units finished during the period 16,000 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,000 Cost of materials used $ 35,200 Labor and overhead costs $ 37,400 Equivalent units of production for labor and overhead are: Multiple Choice 20,000. 17,000. 16,000. 19,000.
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 20,200 Units finished during the period 16,100 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,100 Cost of materials used $ 36,180 Labor and overhead costs $ 41,100 Total cost of the 16,100 units finished is: Multiple Choice $67,477. $71,772. $77,319. $66,852.
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 24,000 Units finished during the period 17,900 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 6,100 Cost of materials used $ 60,500 Labor and overhead costs $ 62,480 Total cost of the 17,900 units finished is: Multiple Choice $102,698. $111,447. $123,011. $109,467.
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 23,800 Units finished during the period 17,900 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 5,900 Cost of materials used $ 59,130 Labor and overhead costs $ 61,110 Cost per equivalent unit of materials is: Multiple Choice $2.48. $2.57. $3.15. $2.82.
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 20,400 Units finished during the period 16,200 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,200 Cost of materials used $ 37,370 Labor and overhead costs $ 39,675 Cost per equivalent unit of labor and overhead is: $2.07. $1.94. $2.30. $2.45.
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 23,000 Units finished during the period 17,500 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 5,500 Cost of materials used $ 53,750 Labor and overhead costs $ 55,755 Cost per equivalent unit of materials is: $2.95. $2.66. $2.42. $2.34.
The Lakeside Company uses a weighted average process costing system. The following data are available: 22,800 17,400 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 5,400 $52,430 $45,060 Cost per equivalent unit of materials is: Multiple Choice O $2.30. O O $2.40. O $2.21. O $198.
The Lakeside Company uses a weighted average process costing system. The following data are available: 23,200 17,500 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 5,700 $55,080 $57,075 Total cost of the 17,500 units finished is:
The Lakeside Company uses a welghted-average process costing system. The following data are available: -- 23,800 17,800 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 6,000 $59,130 $61,110 Total cost of the 17,800 units finished is: Multiple Choice $109,060. $107,080. $120,272. $100,584