Option A ( $ 9,240 ) is the Correct Answer.
Notes
Using Weighted Average Method
Particulars | Units | % Materials | EUP Materials | % Conversion | EUP Conversion |
Units Transferred Out during the Year | 16,000 | 100% | 16,000 | 100% | 16,000 |
Ending Inventory | 4,000 | 100% | 4,000 | 25% | 1,000 |
Total | 20,000 | 20,000 | 17,000 |
EUP Stands for Equivalent Units of Production
EUP Materials = Unit * % Materials
EUP Conversion = Units * % Conversion
Completed as to Conversion = 1/4 * 100% = 25%
Conversion here means Labour and Overhead Costs.
Equivalent Cost per Unit of Materials = 35,200 / 20,000 = $ 1.76 per Unit
For Units in Ending Inventory = 4,000 Units * $ 1.76 per Unit = $ 7,040
Equivalent Units for Conversion Costs = 37,400 / 17,000 = $ 2.2 Per Unit
Cost for Units in Ending Inventory = 1,000 Equivalent Units for Conversion * $ 2.2 per Unit = $ 2,200
Total Costs of Ending Inventory = 7,040 + 2,200
Total Cost of Ending Inventory = $ 9,240
The Lakeside Company uses a welghted-average process costing system. The following data are available: -0- 20,000...
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 20,000 Units finished during the period 16,000 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,000 Cost of materials used $ 35,200 Labor and overhead costs $ 37,400 Total cost of the 4,000 units of the ending inventory: Multiple Choice $9,240. $14,520. $8,910. $15,840.
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 20,000 Units finished during the period 16,000 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,000 Cost of materials used $ 35,200 Labor and overhead costs $ 37,400 Equivalent units of production for labor and overhead are: Multiple Choice 20,000. 17,000. 16,000. 19,000.
The Lakeside Company uses a welghted-average process costing system. The following data are available: -- 23,800 17,800 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 6,000 $59,130 $61,110 Total cost of the 17,800 units finished is: Multiple Choice $109,060. $107,080. $120,272. $100,584
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 20,200 Units finished during the period 16,100 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,100 Cost of materials used $ 36,180 Labor and overhead costs $ 41,100 Total cost of the 16,100 units finished is: Multiple Choice $67,477. $71,772. $77,319. $66,852.
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 24,000 Units finished during the period 17,900 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 6,100 Cost of materials used $ 60,500 Labor and overhead costs $ 62,480 Total cost of the 17,900 units finished is: Multiple Choice $102,698. $111,447. $123,011. $109,467.
The Lakeside Company uses a weighted average process costing system. The following data are available: 22,800 17,400 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 5,400 $52,430 $45,060 Cost per equivalent unit of materials is: Multiple Choice O $2.30. O O $2.40. O $2.21. O $198.
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 23,800 Units finished during the period 17,900 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 5,900 Cost of materials used $ 59,130 Labor and overhead costs $ 61,110 Cost per equivalent unit of materials is: Multiple Choice $2.48. $2.57. $3.15. $2.82.
The Lakeside Company uses a weighted average process costing system. The following data are available: 23,200 17,500 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 5,700 $55,080 $57,075 Total cost of the 17,500 units finished is:
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 20,400 Units finished during the period 16,200 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,200 Cost of materials used $ 37,370 Labor and overhead costs $ 39,675 Cost per equivalent unit of labor and overhead is: $2.07. $1.94. $2.30. $2.45.
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 23,000 Units finished during the period 17,500 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 5,500 Cost of materials used $ 53,750 Labor and overhead costs $ 55,755 Cost per equivalent unit of materials is: $2.95. $2.66. $2.42. $2.34.