Question

1. Truax manufactures and sells two products: Product V9 and Product M6. Data concerning the expected production of each prod

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer)

Calculation of cost of each product under traditional method (using Plant wide rate)

Particulars

Product V9

Product M6

Direct Material

Product V9 (380 units X $ 277.60 per unit)

$ 105,488.00

Product M6 (480 units X $ 170.80 per unit)

     $ 81,984.00

Direct Labour:

Product V9 (3,724 direct labour hours X $ 25.60 per DLH)

     $ 95,334.40

Product M6 (3,264 direct labour hours X $ 25.60 per DLH)

     $ 83,558.40

Overheads:

Product V9 (3,724 direct labour hours X $ 79.5455 per DLH)

$ 296,227.44

Product M6 (3,264 direct labour hours X $ 79.5455 per DLH)

$ 259,636.51

Total Cost

$ 497,049.84

$ 425,178.91

Expected Production (number of units)

380

480

Cost per unit

       $ 1,308.03

           $ 885.79

Therefore total cost for product V9 is $ 1308.03 per unit and for product M6 is $ 885.79 per unit.

Working Notes:

Calculation of single plant wide overhead rate based on direct labour hours

Single plant wide rate = Total estimated overheads/ Total estimated direct labour hours

                                        = $ 555,864/ 6,988 direct labour hours

                                        = $ 79.5455 per direct labour hour.         

Therefore single plant wide overhead rate is $ 79.5455 per direct labour hour.

Allocation of Overheads

Overheads allocated to Product V9 = (Total estimated direct labour hours X overhead rate per direct labour hour)

                                                                 = 3,724 direct labour hours X $ 79.5455 per DLH

                                                                 =$ 296,227.44

Therefore overheads allocated to product V9 are $ 296,227.44.

Overheads allocated to Product M6 = (Total estimated direct labour hours X overhead rate per direct labour hour)

                                                                 = 3,264 direct labour hours X $ 79.5455 per DLH                                                                    

                                                               = $ 259,636.51

Therefore overheads allocated to product M6 are $ 259,636.51

Calculation of cost of each product under Activity Based Costing

Particulars

Product V9

Product M6

Direct Material

Product V9 (380 units X $ 277.60 per unit)

$ 105,488.00

Product M6 (480 units X $ 170.80 per unit)

     $ 81,984.00

Direct Labour:

Product V9 (3,724 direct labour hours X $ 25.60 per DLH)

     $ 95,334.40

Product M6 (3,264 direct labour hours X $ 25.60 per DLH)

     $ 83,558.40

Overheads:

Labour-related

Product V9 (3,724 direct labour hours X $ 13.8317 per DLH)

     $ 51,509.25

Product M6 (3,264 direct labour hours X $ 13.8317 per DLH)

     $ 45,146.67

Product Testing

Product V9 (720 tests X $ 42.3857 per test)

     $ 30,517.70

Product M6 (960 tests X $ 42.3857 per test)

     $ 40,690.27

Order Size

Product V9 (4,300 machine hours X $ 47.2019 per machine hour)

$ 202,968.17

Product M6 (3,920 machine hours X $ 47.2019 per machine hour)

$ 185,031.45

Total Cost

$ 485,817.52

$ 436,410.79

Total Cost (Rounded off)

$ 485,818

$ 436,411

Expected Production (number of units)

380

480

Cost per unit

       $ 1,278.47

           $ 909.19

Therefore total cost for product V9 is $ 1278.47 per unit and for product M6 is $ 909.19 per unit.

Working Note:

Activity Cost Pools

Activity Measures

Total Estimated overhead cost

Total Expected Activity

Cost Per Activity

Labour-related

Direct Labour hours

$ 96,656

6,988 direct labour hours

$ 13.8317 per direct labour hour

Product testing

Number of Tests

$ 71,208

1,680 tests

$ 42.3857 per test

Order size

Number of Machine hours

$ 388,000

8,220 machine hours

$ 47.2019 per machine hour

Total

$ 555,864

Add a comment
Know the answer?
Add Answer to:
1. Truax manufactures and sells two products: Product V9 and Product M6. Data concerning the expected...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1.Truax manufactures and sells two products: Product V9 and Product M6. Data concerning the expected production...

    1.Truax manufactures and sells two products: Product V9 and Product M6. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours Product V9 380 9.8 3,724 Product M6 480 6.8 3,264 Total direct labor-hours 6,988 The direct labor rate is $25.60 per DLH. The direct materials cost per unit for each product is given below: Direct Materials Cost per...

  • Rondeau, Inc., manufactures and sells two products: Product V9 and Product M6. Data concerning the expected...

    Rondeau, Inc., manufactures and sells two products: Product V9 and Product M6. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Production 700 Direct Labor- Hours Per Unit 13.0 10.0 Product V9 Product M6 Total direct labor-hours Total Direct Labor-Hours 9,100 8,000 17,100 800 The direct labor rate is $27.80 per DLH. The direct materials cost per unit for each product is given below: Direct Materials...

  • Salvatori, Inc., manufactures and sells two products: Product A4 and Product Q5. Data concerning the expected...

    Salvatori, Inc., manufactures and sells two products: Product A4 and Product Q5. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours Product A4 650 7.5 4,875 Product Q5 950 4.5 4,275 Total direct labor-hours 9,150 The company has an activity-based costing system with the following activity cost pools, activity measures, and expected activity: Estimated Expected Activity Activity Cost...

  • Fleurant, Inc., manufactures and sells two products: Product W2 and Product P8. Data concerning the expected...

    Fleurant, Inc., manufactures and sells two products: Product W2 and Product P8. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours Product W2 600 6 3,600 Product P8 900 4 3,600 Total direct labor-hours 7,200 The direct labor rate is $42.10 per DLH. The direct materials cost per unit is $208.60 for Product W2 and $145.30 for Product...

  • Snavely, Inc., manufactures and sells two products: Product E1 and Product A7. Data concerning the expected...

    Snavely, Inc., manufactures and sells two products: Product E1 and Product A7. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours Product E1 1,000 10.0 10,000 Product A7 200 5.0 1,000 Total direct labor-hours 11,000 The direct labor rate is $25.00 per DLH. The direct materials cost per unit for each product is given below: Direct Materials Cost...

  • Mahaley, Inc., manufactures and sells two products: Product Q9 and Product F0. Data concerning the expected...

    Mahaley, Inc., manufactures and sells two products: Product Q9 and Product F0. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours Product Q9 900 9.0 8,100 Product F0 900 7.0 6,300 Total direct labor-hours 14,400 The direct labor rate is $22.80 per DLH. The direct materials cost per unit for each product is given below: Direct Materials Cost...

  • Mckenny, Inc., manufactures and sells two products: Product P9 and Product X2. Data concerning the expected...

    Mckenny, Inc., manufactures and sells two products: Product P9 and Product X2. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Production 200 100 Direct Labor- Hours Per Unit 6.0 5.0 Total Direct Labor- Hours 1,200 500 1,700 Product P9 Product x2 Total direct labor-hours The direct labor rate is $28.20 per DLH. The direct materials cost per unit is $140.60 for Product P9 and $107.50...

  • Mahaley, Inc., manufactures and sells two products: Product Q9 and Product F0. Data concerning the expected...

    Mahaley, Inc., manufactures and sells two products: Product Q9 and Product F0. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours Product Q9 810 8.1 6,561 Product F0 810 6.1 4,941 Total direct labor-hours 11,502 The direct labor rate is $21.90 per DLH. The direct materials cost per unit for each product is given below: Direct Materials Cost...

  • Fleurant, Inc., manufactures and sells two products: Product W2 and Product P8. Data concerning the expected...

    Fleurant, Inc., manufactures and sells two products: Product W2 and Product P8. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours Product W2 500 6 3,000 Product P8 600 5 3,000 Total direct labor-hours 6,000 The direct labor rate is $47.10 per DLH. The direct materials cost per unit is $213.60 for Product W2 and $150.30 for Product...

  • Fleurant, Inc., manufactures and sells two products: Product W2 and Product P8. Data concerning the expected...

    Fleurant, Inc., manufactures and sells two products: Product W2 and Product P8. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Direct Labor-Hours Production Per Unit 400 500 Product W2 Product P8 Total direct labor-hours Total Direct Labor-Hours 2,000 2,000 4,000 The direct labor rate is $37.10 per DLH. The direct materials cost per unit is $203.60 for Product W2 and $140.30 for Product P8. The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT