(15): The answer is option “b” – Project Y.
Explanation: The table below shows the payback computation and we can see that payback for X is 3 years, for project Y is 2 years and for Z is 3 years.
Year | Project X | Cumulative cash flow | Project Y | Cumulative cash flow | Project Z | Cumulative cash flow |
0 | -8,000.00 | -8,000.00 | -1,600.00 | -1,600.00 | -8,000.00 | -8,000.00 |
1 | 1,600.00 | -6,400.00 | 0.00 | -1,600.00 | 1,600.00 | -6,400.00 |
2 | 1,600.00 | -4,800.00 | 1,600.00 | 0.00 | 1,600.00 | -4,800.00 |
3 | 4,800.00 | 0.00 | 3,200.00 | 3,200.00 | 4,800.00 | 0.00 |
4 | 0.00 | 0.00 | 4,800.00 | 8,000.00 | 8,000.00 | 8,000.00 |
(16): The answer is option “d” – the payback rule will bias the firm against accepting long term projects because cash flows that arrive after the payback period is ignored.
Explanation: The payback rule is biased in favor of short term investments and projects as only the cash flows that occur till the payback time are considered and rest are ignored and not considered at all.
(17): The answer is option “b” – 16.38%
Explanation: At 16% we are getting a positive NPV and at 16.38% we are getting an NPV of -1.73 which is very close to 0.
Year | Cash flow | 1+r | PVIF | PV |
0 | -8,500.00 | 1.1638 | 1.0000 | -8,500.00 |
1 | 3,500.00 | 0.8593 | 3,007.39 | |
2 | 4,000.00 | 0.7383 | 2,953.27 | |
3 | 4,000.00 | 0.6344 | 2,537.61 | |
NPV | -1.73 |
At 16.368% we get a NPV of 0
Year | Cash flow | 1+r | PVIF | PV |
0 | -8,500.00 | 1.16368 | 1.0000 | -8,500.00 |
1 | 3,500.00 | 0.8593 | 3,007.70 | |
2 | 4,000.00 | 0.7385 | 2,953.89 | |
3 | 4,000.00 | 0.6346 | 2,538.41 | |
NPV | 0.00 |
MULTIPLE CHOICES os the market exceeds the earning per share. s used to calculate the number...
on the market excceds the earning per share s used to calculate the number of times the price being paid for on the market exceeds the dividend per share. s a measure of confidence in the ability of the company to maintain its earnings in future The P/E ratio represents a d. the value of a share of stock in the market oltiplier pplied to current earnings to determine Table I: Net cash flows for three Project Z Project X...
0 4800 8000 15. Given that you wish to use the payback rule with a cut-off period of two years, which projects in Table 1 would you accept? a. Project X b. Project Y. c. Project Z. d. None of the above. 16. Which of the following statements is true regarding the payback rule? The payback rule states that a project should be accepted if its payback period is more than a specified cutoff period. The payback rule emphasizes cash...
t lll the market. Table I: Net cash flows for three projects Year Projeet X -8000 1600 1600 4800 Project Z Projeet Y -1600 0 1600 3200 4800 0 8000 1600 1600 4800 8000 0 15, Given that you wish to use the payback rule with a cut-off period of two years, which projects in Table 1 would you accept? a. Project X b. Project Y c. Project Z d. None of the above.
Refer to the following financial statements and answer the following questions hints:- 13. cash provided (used) by operating activities, investing activities, and financing activities. 14. cash-based net income. 15. estimate of uncollectible accounts receivable. 16. calculate and interpret accounts receivable ratio (most recent and prior period). hints:- 2:12 PM Wed Apr 15 39%). A 51.04cdn.com PART II NIKE, Inc. Consolidated Statements of Income in mWors, except per share data) Revenues Cost of sales Gross profit Demand creation expense Operating overhead...