Question

The following six months of data were collected on electricity cost and the number of machine...

The following six months of data were collected on electricity cost and the number of machine hours in a factory.


Month
Electricity
cost
Machine
hours
June $25,160   4,500
July 26,170 4,810
August 27,250 5,120
September 26,680 5,010
October 27,950 5,430
November 27,500 5,190

Refer to Figure 3-13. An independent variable value used in calculating the cost line using the high-low method is:

a.$27,950

b.4,000

c.5,430

d.$25,160

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Pageno Answert Given that, The Electricity cost and the number of machine hours in a factory. | Electricity COSE T Machine 1

Add a comment
Know the answer?
Add Answer to:
The following six months of data were collected on electricity cost and the number of machine...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Moving to another question will save this response. Question 1 When a mixed cost is graphed...

    Moving to another question will save this response. Question 1 When a mixed cost is graphed the Y-intercept corresponds to the step cost. price of the units sold. fixed cost. variable rate. -> Moving to another question will save this response. OSC Question 2 Which of the following would be found on the balance sheet of a manufacturer?! work in process raw materials finished goods All of the these are correct Status: The following 6 months of data were collected...

  • The method of least squares Select one: a. analyzes a cost relationship by plotting the data...

    The method of least squares Select one: a. analyzes a cost relationship by plotting the data points on a graph. is the least accurate method. C. can easily be calculated by hand. uses the results of regression analysis to construct a cost formula. Figure 3-2 Lassiter Toys, Inc. Cost of Materials $20,000 00,000 200,000 300,000 40,000 60,000 Refer to Figure 3-2. The cost behavior of the materials cost is Select one: a. variable b. discretionary C. committed d. fixed Managerial...

  • Sunland, Inc., has collected the following information on its cost of electricity: Machine Hours Total Electricity...

    Sunland, Inc., has collected the following information on its cost of electricity: Machine Hours Total Electricity Costs 520 $230 January February $290 540 March $190 380 April $220 450 May $260 640 $340 June 700 July $170 330 $280 August 540 September 260 $114 October $360 750 November 850 $350 December $300 600 (a) Your answer is incorrect. Try again Using the high-low method, compute the variable cost of electricity per machine hour. (Round unit cost to 2 decimal places,...

  • The controller of Cullumber Production has collected the following monthly expense data for analyzing the cost...

    The controller of Cullumber Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs. January February March April May June July August September October November December Total Total Electricity Costs Machine Hours $2,700 290 2,980 350 3,590 480 4,620 690 3,160 460 5,000 780 4,110 620 3,910 510 5,120 680 4,200 620 3,200 350 7,290 800 (a) Determine the fixed- and variable-cost components using the high-low method. Fixed-costst 4 Variable-costs जी (b) What electricity...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow:    Month Machine Hours Electricity Costs January 2,900 $ 18,600 February 3,300 $ 21,400 March 2,300 $ 13,700 April 3,500 $ 23,400 May 4,200 $ 28,450 June 3,700 $ 22,400 July 4,500 $ 24,950 August 3,900 $ 22,950 September 2,400 $ 15,900 October 4,100 $ 26,400 November...

  • Machine hours and electricity costs for Wells Industries for last year were as follows: Machine Electricity...

    Machine hours and electricity costs for Wells Industries for last year were as follows: Machine Electricity Month Hours Costs January 2,000 $ 9,200 February 2,320 10,500 March 1,520 6,750 April 2,480 11,500 May 3,040 14,125 June 2,640 11,000 July 3,280 12,375 August 2,800 11,375 September 1,600 7,750 October 2,960 13,000 November 3,760 15,500 December 3,360 13,875 Required: Show your Calculations! A. Using the high-low method, develop an estimate of variable electricity costs per machine hour. B. Using the high-low method,...

  • Figure 3-11. The following four months of data were collected on utility cost and the number...

    Figure 3-11. The following four months of data were collected on utility cost and the number of labor hours in a factory. Utility Labor Month cost hours January $22,100 3,975 February 24,600 5,430 March 23,500 4,400 April 20,140 3,200 Refer to Figure 3-11. Select the correct set of high and low months.

  • Fromme's Frocks has the following machine hours and production costs for the last six months of...

    Fromme's Frocks has the following machine hours and production costs for the last six months of last year: Month Machine Hours Production Cost July 16,500 $ 12,150 August 15,000 12,300 September 13,000 9,650 October 17,000 12,230 November 16,300 11,767 December 13,600 9,967 If Fromme expects to incur 12,100 machine hours in January, what will be the estimated total production cost using the high-low method?

  • The controller of Standard Industries has collected the following monthly expense data for analyzing the cost...

    The controller of Standard Industries has collected the following monthly expense data for analyzing the cost behavior of electricity costs. Total Total Electricity Costs Machine Hours January $2,500 300 February   3,000 350 March   3,600 500 April   4,500 690 May   3,200 400 June   4,900 700 July   4,100 650 August   3,800 520 September   5,100 680 October   4,200 630 November   3,300 350 December   6,100 720 Instructions (a)   Determine the fixed- and variable-cost components using regression analysis (We recommend the use of Excel.) (b)  ...

  • Hagler's Toupees has the following machine hours and production costs for the last six months of...

    Hagler's Toupees has the following machine hours and production costs for the last six months of last year: Month July August September October November December Machine Hours 15,900 14,100 12.100 16,100 15,400 12,700 Production Cost 12,795 11.460 10,180 12,800 12,292 10,402 If Hagler expects to incur 14,600 machine hours in January, what will be the estimated total production cost using the high-low method? Multiple Choice $11,810.00 $13,165.83 $11,780.00 $12,515.00

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT