Machine hours and electricity costs for Wells Industries for
last year were as follows:
Machine |
Electricity |
|
Month |
Hours |
Costs |
January |
2,000 |
$ 9,200 |
February |
2,320 |
10,500 |
March |
1,520 |
6,750 |
April |
2,480 |
11,500 |
May |
3,040 |
14,125 |
June |
2,640 |
11,000 |
July |
3,280 |
12,375 |
August |
2,800 |
11,375 |
September |
1,600 |
7,750 |
October |
2,960 |
13,000 |
November |
3,760 |
15,500 |
December |
3,360 |
13,875 |
Required: Show your Calculations!
A. | Using the high-low method, develop an estimate of variable electricity costs per machine hour. |
B. | Using the high-low method, develop an estimate of fixed electricity costs per month. |
C. | Using the high-low method, develop a cost function for monthly electricity costs. |
D. | Estimate electricity costs for a month in which 3,000 machine hours are worked. |
Question 41 options:
Machine | Electicity | |||||
hours | cost | |||||
high | 3,760 | 15,500 | ||||
low | 1,520 | 6,750 | ||||
Difference | 2,240 | 8,750 | ||||
A | Variable cost per MH =8750/2240 | |||||
3.91 | ||||||
B | Fixed electicity costs per month | |||||
15,500 - (3760*3.91) | ||||||
798.4 | ||||||
C | Cost Function | |||||
y = a + bx | ||||||
total cost (y) = 798.40 + 3.91x | ||||||
total electricity cost = 798.40 +3.91 machine hours | ||||||
d | Estimated Electricity cost | |||||
798.40 +3.91*3000 | ||||||
12528.4 | answer | |||||
Machine hours and electricity costs for Wells Industries for last year were as follows: Machine Electricity...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Electricity Hours Costs 2,500 $18,400 2,900 21,000 1,900 13,500 3,100 23,000 3,800 28, 250 3,300 22,000 4,100 24,750 3,500 22,750 2,000 15,500 3,700 26,000 4,700 31,000 4,200 27,750 Summary Output Regression Statistics Multiple...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 2,600 $ 19,250 February 3,000 $ 22,700 March 2,000 $ 14,350 April 3,200 $ 24,700 May 3,900 $ 29,100 June 3,400 $ 23,700 July 4,200 $ 25,600 August 3,600 $ 23,600 September 2,100 $ 17,200 October 3,800 $ 27,700 November...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 2,100 $ 19,000 February 2,500 $ 22,200 March 1,500 $ 14,100 April 2,700 $ 24,200 May 3,400 $ 28,850 June 2,900 $ 23,200 July 3,700 $ 25,350 August 3,100 $ 23,350 September 1,600 $ 16,700 October 3,300 $ 27,200 November...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 3,500 $ 18,900 February 3,900 $ 22,000 March 2,900 $ 14,000 April 4,100 $ 24,000 May 4,800 $ 28,750 June 4,300 $ 23,000 July 5,500 $ 25,250 August 4,500 $ 23,250 September 3,000 $ 16,500 October 4,700 $ 27,000 November 6,800...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 2,500 $ 19,200 February 2,900 $ 22,600 March 1,900 $ 14,300 April 3,100 $ 24,600 May 3,800 $ 29,050 June 3,300 $ 23,600 July 4,100 $ 25,550 August 3,500 $ 23,550 September 2,000 $ 17,100 October 3,700 $ 27,600 November 4,700...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,500 2,900 1,900 3,100 3,800 3,300 4,100 3,500 2,000 3,700 4,700 4,200 Electricity Costs $ 18,400 $ 21,000 $ 13,500 $ 23,000 $ 28,250 $ 22,000 $ 24,750 $ 22,750 $ 15,500...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 2,900 $ 18,600 February 3,300 $ 21,400 March 2,300 $ 13,700 April 3,500 $ 23,400 May 4,200 $ 28,450 June 3,700 $ 22,400 July 4,500 $ 24,950 August 3,900 $ 22,950 September 2,400 $ 15,900 October 4,100 $ 26,400 November...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,600 3,000 2,000 3,200 3,900 3,400 4,200 3,600 2,100 3,800 4,800 4,300 Electricity Costs $19, 250 $22,700 $14,350 $24,700 $29,100 $23,700 $25,600 $23,600 $17,200 $27,700 $32,700 $28,600 Summary Output Regression Statistics Multiple...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 3,100 $ 18,700 February 3,500 $ 21,600 March 2,500 $ 13,800 April 3,700 $ 23,600 May 4,400 $ 28,550 June 3,900 $ 22,600 July 4,700 $ 25,050 August 4,100 $ 23,050 September 2,600 $ 16,100 October 4,300 $ 26,600 November...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,500 2,900 1,900 3,100 3,800 3,300 4,100 3,500 2,000 3,700 4,700 4,200 Electricity Costs $19, 200 $22,600 $14,300 $24,600 $29,050 $23,600 $25,550 $23,550 $17, 100 $27,600 $32,600 $28,550 Summary Output Regression Statistics...