Question

Chapter 4 Assignment i Saved Required information Greenwood Company manufactures two products-14,000 units of Product Y and 6

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Activity Driver Rate
Activity Total Overhead Cost Total Number Of Activities Activity Driver rate
Machining $                      1,98,000 10000 Machine Hours $                         19.80 Per machine hour
Machine Setup $                         86,400 180 Steups $                             480 per setup
Production Design $                         82,000 2 products $                       41,000 per product
General Factory $                      2,48,000 10000 DLHs $                         24.80 per DLHs
Overhead allocated to each product.
Total Overhead Cost For Product Y
Activity Rate Number of activity Overhead Cost
Machining 19.8 7800 $                   1,54,440
Machine Setup 480 50 $                       24,000
Production Design 41000 1 $                       41,000
General Factory 24.8 7800 $                   1,93,440
Total Overhead Cost $                   4,12,880
Add a comment
Know the answer?
Add Answer to:
Chapter 4 Assignment i Saved Required information Greenwood Company manufactures two products-14,000 units of Product Y...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • iment Saved Required information Greenwood Company manufactures two products-14,000 units of Product Y and 6,000 units...

    iment Saved Required information Greenwood Company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Estimated Expected Activity Overhead Activity Cost Pool Machining Machine setups Production design...

  • Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 198,000...

  • Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 198,000...

  • Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number...

  • Required information Greenwood Company manufactures two products-14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number...

  • Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number...

  • Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number...

  • Required information Greenwood Company manufactures two products-14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number...

  • Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The...

    Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 209,000 10,000 MHs...

  • Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7,000 units of Product...

    Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z Estimated Overhead Expected Activity 11,000 MHs Activity Cost Pool Machining Machine setups Production design...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT