You are analyzing the following two mutually exclusive projects and have developed the following information. Please calculate the IRRs for the two projects and the crossover rate. (6 points) Which project should you accept if the cost of capital is 5%, and which project should you accept if the cost of capital is 10%? (4 points)
year project A project B
0 -1100 -900
1 400 700
2 500 100
3 100 100
4 400 200
IRR A: ___________ IRR B: ___________ Crossover Rate: ____________ If WACC=5%, accept _______ If WACC=10%, accept _______
Using financial calculator to calculate
CF0=-1100;CF1=400;CF2=500;CF3=100;CF4=400;CPT IRR =11.13%
Using financial calculator to calculate
CF0=-900;CF1=700;CF2=100;CF3=100;CF4=200;CPT IRR =12.22%
Incremental Cash Flow
CF0=-1100+900=-200
CF1 =400-700 =-300
CF2=500-100=400
CF3=100-100=0
CF4=400-200=200
CF0=-200;CF1=-300;CF2=400;CF3=0;CF4=200;CPT IRR =9.36%
If WACC =5%
NPV of Project A
=-1100+400/1.05+500/1.05^2+100/1.05^3+400/1.05^4=149.93
NPV of Project B
=-900+700/1.05+100/1.05^2+100/1.05^3+200/1.05^4=108.29
At 5% Accept Project A
If WACC =10%
NPV of Project A
=-1100+400/1.10+500/1.10^2+100/1.10^3+400/1.10^4=25.20
NPV of Project B
=-900+700/1.10+100/1.10^2+100/1.10^3+200/1.10^4=30.74
At 10% Accept Project B
You are analyzing the following two mutually exclusive projects and have developed the following information. Please...
You are analyzing the following two mutually exclusive projects and have developed the following information: Year Project A Cash Flows Project B Cash Flows $-85,718 $-76,929 $30,787 $24,319 $38,572 $32,693 $29,313 $26,810 What is the incremental IRR (1.e., crossover rate)? (Answer in percentage terms and round answer to 2 decimals)
5. You are analyzing the following two mutually exclusive projects and have developed the following information. What is the crossover rate? Project A Project B YEAR Cash Flow Cash Flow 0 $-75,000 $-75,000 1 $24,800 $22,000 2 $29,500 $27,500 3 $43,500 $51,300
You are analyzing the following two mutually exclusive projects and have developed the following information. What is the crossover rate? Year Project A Cash Flow Project B Cash Flow $75,000 $26,300 $29,500 $45,300 $75,000 $24,000 $26,900 $51,300 14.32 percent 13.33 percent O 15.20 percent O 14.60 percent 13.17 percent
4 points Saved You are analyzing the following two mutually exclusive projects and have developed the following information. What is the crossover rate? Year Project A Cash Flow $75,000 $24,800 $29,500 $45,300 Project B Cash Flow $75,000 $22,000 $27,500 $51,300 A. 14.96 percent B. 13.33 percent C. 14.32 percent D.15.20 percent
2. A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 4 $900 $0 $10 $400 $10 $800 Project S $1,000 Project L $1,000 The company's WACC is 1 1%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) $250 $250
You are analyzing two mutually exclusive projects with the cash flows shown below. The cash flows are in millions. Both projects are equally risky. Your costs of capital are 12%. Year Project 1 Project 2 0 -$140 -$90 1 $50 $40 2 $45 $35 3 $40 $30 4 $35 $25 5 $30 $20 6 $25 $15 7 $20 $10 8 $15 $5 9 $10 $0 10 $5 -$5 Compute the NPVs of the two projects. b. Compute the IRRs of...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 1 2 3 Project S Project L - $1,000 $897.60 - $1,000 $10 $240 $260 $ 10 $400 $10 $803.38 The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 2 3 Project S - $1,000 $890.56 $250 $10 $10 Project L - $1,000 $0 $250 $400 $799.39 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 Project S -$1,000 $874.54 $250 $10 $10 Project L -$1,000 $5 $260 $400 $799.76 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $875.68 $260 $15 $5 Project L -$1,000 $10 $240 $400 $785.54 The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.