A company constructs a building for its own use Construction began on January 1 and ended on December 30. The expenditures fo

0 0
Add a comment Improve this question Transcribed image text
Answer #1


Average date Jan 1. Mar 31. Jun 30. Oct 30. calculation of average accumulated expenditure expenditure weight 700000 x 12/12

Add a comment
Know the answer?
Add Answer to:
A company constructs a building for its own use Construction began on January 1 and ended...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A company constructs a building for its own use. Construction began on January 1 and ended...

    A company constructs a building for its own use. Construction began on January 1 and ended on December 30. The expenditures for construction were as follows: January 1, $540,000; March 31, $640,000; June 30, $440,000; October 30, $720,000. To help finance construction, the company arranged a 7% construction loan on January 1 for $780,000. The company’s other borrowings, outstanding for the whole year, consisted of a $5 million loan and a $7 million note with interest rates of 9% and...

  • A company constructs a building for its own use. Construction began on January 1 and ended...

    A company constructs a building for its own use. Construction began on January 1 and ended on December 30. The expenditures for construction were as follows: January 1, $560,000, March 31, $660.000, June 30, $460.000, October 30, $780,000. To help finance construction, the company arranged a 9% construction loan on January 1 for $820,000. The company's other borrowings, outstanding for the whole year, consisted of a $2 million loan and a $4 million note with interest rates of 11% and...

  • A company constructs a building for its own use. Construction began on January 1 and ended...

    A company constructs a building for its own use. Construction began on January 1 and ended on December 30. The expenditures for construction were as follows: January 1, $500,000; March 31, $600,000; June 30, $400,000; October 30, $600,000. To help finance construction, the company arranged a 7% construction loan on January 1 for $700,000. The company's other borrowings, outstanding for the whole year, consisted of a $3 million loan and a $5 million note with interest rates of 8% and...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The build...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,800,000 at 7% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $9,000,000, 12% bonds $6,000,000, 7% long-term note Construction expenditures incurred during 2018 were as follows: January 1 March 31 June 30 September 30 December 31 $ 780,000 1,380,000...

  • A company constructs a bulding for its own use Construction began on January and ended on...

    A company constructs a bulding for its own use Construction began on January and ended on December 30 The expendtures for construction were as follows January 8620000 March 3t 5720000 5 520 000 October 30 5960000 To help finance construction the company arranged a construction toon on January 1for 5940.000 The company's other borrowings. outstanding for the whole year compted of a 33 milion loan and a 55 meson note with interest rates of as and ot respectively. Assuming the...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,500,000 at 10% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $8,000,000, 15% bonds $2,000,000, 10% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 660,000 March 31 1,260,000 June 30 872,000 September 30 660,000...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,700,000 at 9% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $6,000,000, 14% bonds $4,000,000, 93 long-term note Construction expenditures incurred during 2018 were as follows: January 1 March 31 June 30 September 30 December 31 $ 620,000 1,220,000...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,500,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $9,000,000, 9% bonds $6,eee, eee, 8% long-term note Construction expenditures incurred during 2018 were as follows: January 1 March 31 June 30 September 30 December 31 $1,000,000 1,600,000...

  • On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The only interest-bearing debt the company had outstanding during 2018 was long-term bonds with a book value of $10,100,000 and an effective interest rate of 9%. Construction expenditures incurred during 2018 were as follows: January 1 March 1 July 31 September 30 December 31 $ 510,000 606, 000 486,000 610,000 310,000 Required: Calculate the amount of...

  • On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $2,000,000 at 13% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: points $5.829.oe. 17% bonds $3.880.880.13% long-term note Construction expenditures incurred during 2021 were as follows: $ January 1 March 31 June 30 September 30 December 31 820,000 1,420.000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT