A company constructs a bulding for its own use Construction began on January and ended on December 30 The expendtures for con

1 0
Add a comment Improve this question Transcribed image text
Answer #1

666 Answe: The interest to be Capitalized is $109,000 . Average accumulated expenditures! - Date | Expenditures weight Averag

Add a comment
Know the answer?
Add Answer to:
A company constructs a bulding for its own use Construction began on January and ended on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A company constructs a building for its own use Construction began on January 1 and ended...

    A company constructs a building for its own use Construction began on January 1 and ended on December 30. The expenditures for construction were as follows January 1. $700,000, March 31 $800,000. June 30, $600,000 October 30 $1,200,000To help finance construction, the company arranged a 8% construction loan on January 1 for $1.100,000. The company's other borrowings. outstanding for the whole year consisted of a $7 million loan and a $9 million note with interest rates of 10% and 6%,...

  • A company constructs a building for its own use. Construction began on January 1 and ended...

    A company constructs a building for its own use. Construction began on January 1 and ended on December 30. The expenditures for construction were as follows: January 1, $500,000; March 31, $600,000; June 30, $400,000; October 30, $600,000. To help finance construction, the company arranged a 7% construction loan on January 1 for $700,000. The company's other borrowings, outstanding for the whole year, consisted of a $3 million loan and a $5 million note with interest rates of 8% and...

  • A company constructs a building for its own use. Construction began on January 1 and ended...

    A company constructs a building for its own use. Construction began on January 1 and ended on December 30. The expenditures for construction were as follows: January 1, $540,000; March 31, $640,000; June 30, $440,000; October 30, $720,000. To help finance construction, the company arranged a 7% construction loan on January 1 for $780,000. The company’s other borrowings, outstanding for the whole year, consisted of a $5 million loan and a $7 million note with interest rates of 9% and...

  • A company constructs a building for its own use. Construction began on January 1 and ended...

    A company constructs a building for its own use. Construction began on January 1 and ended on December 30. The expenditures for construction were as follows: January 1, $560,000, March 31, $660.000, June 30, $460.000, October 30, $780,000. To help finance construction, the company arranged a 9% construction loan on January 1 for $820,000. The company's other borrowings, outstanding for the whole year, consisted of a $2 million loan and a $4 million note with interest rates of 11% and...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The build...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,800,000 at 7% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $9,000,000, 12% bonds $6,000,000, 7% long-term note Construction expenditures incurred during 2018 were as follows: January 1 March 31 June 30 September 30 December 31 $ 780,000 1,380,000...

  • On January 1, 2016 Walker company began construction of its own building. Construction was completed on...

    On January 1, 2016 Walker company began construction of its own building. Construction was completed on September 30, 2017. Walker incurred the following building construction costs: Payments for Construction 2016 January 1, 2016: $300,000 June 1, 2016: $600,000 October 1, 2016: $800,000 Payments for Construction in 2017 May 1, 2017: $675,000 September 30, 2017: $450,000 Walker had 3 loans outstanding during this entire period from January 1, 2016 through December 31 2017: $500,000 specific construction loan with interest rate of...

  • On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The only interest-bearing debt the company had outstanding during 2018 was long-term bonds with a book value of $10,100,000 and an effective interest rate of 9%. Construction expenditures incurred during 2018 were as follows: January 1 March 1 July 31 September 30 December 31 $ 510,000 606, 000 486,000 610,000 310,000 Required: Calculate the amount of...

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,350,000 1, 080, 000 1, 280,000 1,080,000 342, 000 675, 000 972, 000 On January 1, 2018, the company obtained a $3,800,000 construction loan...

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,350,000 1, 080, 000 1, 280,000 1,080,000 342, 000 675, 000 972, 000 On January 1, 2018, the company obtained a $3,800,000 construction loan...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,500,000 at 10% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $8,000,000, 15% bonds $2,000,000, 10% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 660,000 March 31 1,260,000 June 30 872,000 September 30 660,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT