Factory Overhead Controllable Variance Bellingham Company produced 3,100 units of product that required 6 standard direct lab

0 0
Add a comment Improve this question Transcribed image text
Answer #1

VARIABLE FACTORY OVERHEAD CONTROLLABLE VARIANCE = (ACTUAL VARIABLE FACTORY OVERHEAD - STANDARD VARIABLE FACTORY OVERHEAD)

= $104360 - $5.40*6*3100

= $3920 Unfavorable

Add a comment
Know the answer?
Add Answer to:
Factory Overhead Controllable Variance Bellingham Company produced 3,100 units of product that required 6 standard direct...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Factory Overhead Controllable Variance Bellingham Company produced 5,400 units of product that required 5.5 standard...

    1. Factory Overhead Controllable Variance Bellingham Company produced 5,400 units of product that required 5.5 standard direct labor hours per unit. The standard variable overhead cost per unit is $6.00 per direct labor hour. The actual variable factory overhead was $170,360. Determine the variable factory overhead controllable variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. 2. Factory Overhead Volume Variance Bellingham Company produced 5,100 units of product...

  • Factory Overhead Controllable Variance Bellingham Company produced 3,000 units of product that required 6.5 sta...

    Factory Overhead Controllable Variance Bellingham Company produced 3,000 units of product that required 6.5 standard direct labor hours per unit. The standard variable overhead cost per unit is $5.60 per direct labor hour. The actual variable factory overhead was $113,350. Determine the variable factory overhead controllable variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

  • Factory Overhead Controllable Variance Bellingham Company produced 4,100 units of product that required 4.5 standard hours...

    Factory Overhead Controllable Variance Bellingham Company produced 4,100 units of product that required 4.5 standard hours per unit. The standard variable overhead cost per unit is $3.80 per hour. The actual variable factory overhead was $67,450. Determine the variable factory overhead controllable variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. $  

  • Factory Overhead Volume Variance Bellingham Company produced 3,600 units of product that required 6 standard direct...

    Factory Overhead Volume Variance Bellingham Company produced 3,600 units of product that required 6 standard direct labor hours per unit. The standard fixed overhead cost per unit is $2.50 per direct labor hour at 19,900 hours, which is 100% of normal capacity. Determine the fixed factory overhead volume variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number Favorable

  • Bellingham Company produced 6,900 units of product that required 6.5 standard hours per unit. The standard...

    Bellingham Company produced 6,900 units of product that required 6.5 standard hours per unit. The standard variable overhead cost per unit is $5.90 per hour. The actual variable factory overhead was $260,645. Determine the variable factory overhead controllable variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. 23-2 Practice Exercises Factory Overhead Controllable Variance Bellingham Company produced 6,900 units of product that required 6.5 standard hours per unit....

  • Direct Materials Variances Bellingham Company produces a product that requires 6 standard pounds per unit. The standard...

    Direct Materials Variances Bellingham Company produces a product that requires 6 standard pounds per unit. The standard price is $10 per pound. If 6,300 units required 36,300 pounds, which were purchased at $10.3 per pound, what is the direct materials (a) price variance, (b) quantity variance, and (c) total direct materials cost variance? Enter a favorable variance as negative number using a minus sign and an unfavorable variance as a positive number. 10,890 Unfavorable a. Direct materials price variance b....

  • Factory Overhead Volume Variance Bellingham Company produced 2,100 units of product that required 1.5 standard dire...

    Factory Overhead Volume Variance Bellingham Company produced 2,100 units of product that required 1.5 standard direct labor hours per unit. The standard fixed overhead cost per unit is $2.70 per direct labor hour at 2,950 hours, which is 100% of normal capacity. Determine the fixed factory overhead volume variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number

  • Bellingham Company produced 2,300 units of product that required 2 standard hours per unit. The standard...

    Bellingham Company produced 2,300 units of product that required 2 standard hours per unit. The standard variable overhead cost per unit is $4.80 per hour. The actual variable factory overhead was $21,550. Determine the variable factory overhead controllable variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. $  

  • Bellingham Company produced 2,300 units of product that required 2 standard hours per unit. The standard...

    Bellingham Company produced 2,300 units of product that required 2 standard hours per unit. The standard variable overhead cost per unit is $4.80 per hour. The actual variable factory overhead was $21,550. Determine the variable factory overhead controllable variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. $  

  • Direct Materials Variances Bellingham Company produces a product that requires 15 standard pounds per unit. The...

    Direct Materials Variances Bellingham Company produces a product that requires 15 standard pounds per unit. The standard price is $8 per pound. If 5,600 units required 87,400 pounds, which were purchased at $8.24 per pound, what is the direct materials (a) price variance, (b) quantity variance, and (c) total direct materials cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct materials price variance b. Direct...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT