Question

Highlander Cutlery manufactures kitchen knives. One of the employees, whose job is to cut out wooden knife handles, worked 51 hours during a week in January. The employee earns $15 per hour for a 40-hour week, and overtime is paid after 40 hours. For additional hours the employee is paid an overtime rate of $20 per hour. The employee’s time was spent as follows:

Regular duties involving cutting out knife handles 43 hours
General shop cleanup duties 7 hours
Idle time due to power outage 1 hour

1. Calculate the total cost of the employee’s wages during the week described above.

2.Determine the portion of this cost to be classified in each of the following categories:

Direct labor b. Manufacturing overhead (idle time) c. Manufacturing overhead (overtime premium) Manufacturing overhead (indir

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Sol - O Regular hours = Hox $15 - $600 Overtime hours = (51-40) x $20 RX 20 = $ 220 Therefore total cost of employees wages

Add a comment
Know the answer?
Add Answer to:
Highlander Cutlery manufactures kitchen knives. One of the employees, whose job is to cut out wooden...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Highlander Cutlery manufactures kitchen knives. One of the employees, whose job is to cut out wooden...

    Highlander Cutlery manufactures kitchen knives. One of the employees, whose job is to cut out wooden knife handles, worked 53 hours during a week in January. The employee earns $16 per hour for a 40-hour week, and overtime is paid after 40 hours. For additional hours the employee is paid an overtime rate of $21 per hour. The employee’s time was spent as follows: Regular duties involving cutting out knife handles 45 hours General shop cleanup duties 5 hours Idle...

  • Kaleidoscope Cutlery manufactures kitchen knives. One of the employees, whose job is to cut out wooden...

    Kaleidoscope Cutlery manufactures kitchen knives. One of the employees, whose job is to cut out wooden knife handles, worked 49 hours during a week in January. The employee earns $14 per hour for a 40-hour week. For additional hours the employee is paid an overtime rate of $19 per hour. The employee's time was spent as follows: Regular duties involving cutting out knife 1 hours 6 hours 2 hours handles General shop cleanup duties Idle time due to power outage...

  • Highlander Cutlery manufactures kitchen knives. One of the 48 hours during a week in January. The...

    Highlander Cutlery manufactures kitchen knives. One of the 48 hours during a week in January. The paid an overtime rate of $18 per hour. The employee's time was spent as tollows worked employee is employee earns $10 per hour for a 42-hour week. For additional hours, the Regular duties involving cutting out knife handles General shop cleanup duties 38 hours 9 hours 1 hour Idle time due to power outage

  • [The following information applies to the questions displayed below. Kaleidoscope Cutlery manufactures kitchen knives. One of...

    [The following information applies to the questions displayed below. Kaleidoscope Cutlery manufactures kitchen knives. One of the employees, whose job is to cut out wooden knife handles, worked 49 hours during a week in January. The employee earns $14 per hour for a 40-hour week. For additional hours the employee is paid an overtime rate of $19 per hour. The employee's time was spent as follows: Regular duties involving cutting out knife handles General shop cleanup duties Idle time due...

  • PROBLEM 2-14/Classification of Labour Costs ILO1] Big Sky Equipment manufact ures and sells camping equipment. Employees...

    PROBLEM 2-14/Classification of Labour Costs ILO1] Big Sky Equipment manufact ures and sells camping equipment. Employees in the production department are paid $30 per hour but receive $45 per hour for each hour worked in excess of 40 hours per week. Required: 1. Calculate the total wages for the week if an employee works 50 hours. Of the total, how much would the company allocate to direct labour cost? To manufacturing overhead cost? In a different week, suppose an employee...

  • Jan Davis is employed by Wesley Limited. Last week she worked 54 hours assembling one of...

    Jan Davis is employed by Wesley Limited. Last week she worked 54 hours assembling one of the company's products. Wesley's employees work a 40-hour week and Davis is paid $26 per hour. Employees are paid time and a half for any hours worked in excess of the standard 40 hours. Assume the overtime is the result of an overall increase in demand for all products. Required: 1. Allocate Davis's wages for the week between direct labour cost and manufacturing overhead...

  • Petrell Inc. is a wholesale distributor supplying a wide range of high-end cooking knives for the...

    Petrell Inc. is a wholesale distributor supplying a wide range of high-end cooking knives for the professional chef. Petrell has an enviable reputation for quality of its products. The demand for Petrell ’s products is so great that at times Petrell cannot satisfy the demand and must delay or refuse some orders, in order to maintain its production quality. Additionally, Petrell purchases some of its products from outside suppliers in order to meet the demand. These suppliers are carefully chosen...

  • Jan Davis is employed by Wesley Limited. Last week she worked 55 hours assembling one of...

    Jan Davis is employed by Wesley Limited. Last week she worked 55 hours assembling one of the company’s products. Wesley’s employees work a 40-hour week and Davis is paid $28 per hour. Employees are paid time and a half for any hours worked in excess of the standard 40 hours. Assume the overtime is the result of an overall increase in demand for all products. Required: 1. Allocate Davis’s wages for the week between direct labour cost and manufacturing overhead...

  • Exercise 2-12 Classification of Labour Costs [LO1) Jan Davis is employed by Wesley Limited. Last week...

    Exercise 2-12 Classification of Labour Costs [LO1) Jan Davis is employed by Wesley Limited. Last week she worked 56 hours assembling one of the company's products, Wesley's employees work a 40-hour week and Davis is paid $30 per hour Employees are paid time and a half for any hours worked in excess of the standard 40 hours. Assume the overtime is the result of an overall increase in demand for all products, Required: 1. Allocate Davis's wages for the week...

  • Whether to Work Overtime or Hire Additional Employees The Fair Labor Standards Act requires employers to...

    Whether to Work Overtime or Hire Additional Employees The Fair Labor Standards Act requires employers to pay nonexempt status employees an overtime rate at least equal to 1.5 times the normal hourly wage for each hour worked beyond the 40​-hour workweek period. ACME manufacturing has just signed a lucrative contract to produce the casings for flashlights. The contract spans five years. During this​ time, ACME must increase its total manufacturing output by 25 percent. To meet this added​ demand, the​...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT