Answer :- Calculation of predetermined overhead rate for 2020:-
Predetermined Overhead Rate =
= Total manufacturing overhead cost / direct labor cost *100
= $882,000 / $735,000 *100
= 120%
If you have any query ask in comment section. If you like the answer plz rate. Thanks
Job No Direct Materials $10.500 Direct Labor $5.250 26.250 21000 40.950 31500 A Your answer is...
Send to Gradebook Question 13 View Policies Current Attempt in Progress Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,000, direct labor $12.600, and manufacturing overhead $16.800. As of January 1, Job 49 had been completed at a cost of $94.500...
CALCULATOR STANDARD VIEW PRINTER VERSION BACK Problem 15-01A Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prio January 1 on this job were as follows: direct materials $23,800, direct labor $14,280, and manufacturing overhead $19,040. As of January 1, Job 49 had been completed at a cost of $107,100 aw was part of...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,400, direct labor $12,840, and manufacturing overhead $17,120. As of January 1, Job 49 had been completed at a cost of $96,300 and was part of finished goods inventory. There was a $16,050...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,400, direct labor $14,040, and manufacturing overhead $18,720. As of January 1, Job 49 had been completed at a cost of $105,300 and was part of finished goods inventory. There was a $17,550...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,200, direct labor $13,920, and manufacturing overhead $18,560. As of January 1, Job 49 had been completed at a cost of $104,400 and was part of finished goods inventory. There was a $17,400...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,600, direct labor $12,960, and manufacturing overhead $17,280. As of January 1, Job 49 had been completed at a cost of $97,200 and was part of finished goods inventory. There was a $16,200...
A job cost sheet of Crane Company is given below. 2.000 JOB NO. ITEM 7/2 FOR Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 700 7/31 Manufacturing Overhead Date 7/10 12 900 15 400 480 360 22 300 24 1,620 1,520 27 31 500 600 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Your answer is partially correct. Answer the following questions. (1) What...
Problem 15-01A Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $25,000, direct labor $15,000, and manufacturing overhead $20,000. As of January 1, Job 49 had been completed at a cost of $112,500 and was part of finished goods inventory. There was...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,400, direct labor $12,240, and manufacturing overhead $16,320. As of January 1, Job No. 49 had been completed at a cost of $91,800 and was part of finished goods inventory. There was...
Problem 15-01A Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,600, direct labor $12,960, and manufacturing overhead $17,280. As of January 1, Job 49 had been completed at a cost of $97,200 and was part of finished goods inventory. There was...