Question

Waterways uses time and material pricing when it bids on irrigation projects. Budgeted data for the coming year are as follow

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1
Budgeted cost per labor hour 59.80 =358800/6000
Add: Profit margin 15.00
Labor rate 74.80 per hour
2
Material loading charges 19.70% =122140/620000
Add: Profit on parts 16.00%
Material loading charge 35.70%
Add a comment
Know the answer?
Add Answer to:
Waterways uses time and material pricing when it bids on irrigation projects. Budgeted data for the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 9 View Policies Current Attempt in Progress Waterways uses time and material pricing when it bids on irrigatio...

    Question 9 View Policies Current Attempt in Progress Waterways uses time and material pricing when it bids on irrigation projects. Budgeted data for the coming year are as follows. WATERWAYS CORPORATION Budgeted Costs for Irrigation Projects Material Time Loading Charges Charges Labor wages (5900 hours) $237770 Supervisor's salary $61000 Clerical and accountant wages 63130 4000 Irrigation supplies manager 41000 Overhead 54280 22050 Total $355180 $128050 Waterways has budgeted for 5900 labor hours. It desires a $13 profit margin per hour...

  • WATERWAYS CORPORATION Budgeted Costs for Irrigation Projects Time Charges Material Loading Charges Labor wages (5,700 hours)...

    WATERWAYS CORPORATION Budgeted Costs for Irrigation Projects Time Charges Material Loading Charges Labor wages (5,700 hours) $238,260 Supervisor’s salary $62,000 Clerical and accountant wages 58,140 4,000 Irrigation supplies manager 39,000 Overhead 53,010 21,720    Total $349,410 $126,720 Waterways has budgeted for 5,700 labor hours. It desires a $13 profit margin per hour of labor and 15% profit on materials. It estimates the total invoice cost of materials in the coming year will be $660,000. A.Compute the rate per hour of labor....

  • TIME AND MATERIAL PRICING! • Total budgeted Time Charges are $345,600. • Total budgeted Material Loading...

    TIME AND MATERIAL PRICING! • Total budgeted Time Charges are $345,600. • Total budgeted Material Loading Charges are $165,060. Total expected labor hours are 12,000 hours. Total expected materials cost is $1,260,000. Profit margin per hour on labor is $40. Profit margin on materials is 80%. • Determine the total price of a job that requires 150 hours of labor and $60,000 in parts.

  • Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is availa...

    Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available for Second Chance. Time Charges $238,000 Material Loading Charges Technicians' wages and benefits Parts manager's salary and benefits Office employee's salary and benefits Other overhead Total budgeted costs 49,000 35,000 $322,000 $40,100 7,430 27.440 $74,970 The company desires a $37 profit margin per hour of labor and a 20.00% profit margin on parts. It has budgeted for 7,000 hours of repair time in...

  • Sheridan Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available...

    Sheridan Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available for Sheridan. Time Charges Material Loading Charges Technicians' wages and benefits $221,200 -        Parts manager's salary and benefits -        $40,200 Office employee's salary and benefits 39,500 6,840 Other overhead 23,700 23,040 Total budgeted costs $284,400 $70,080 The company desires a $37 profit margin per hour of labor and a 20.00% profit margin on parts. It has budgeted for 7,900 hours of repair time in...

  • Practice Problem 1 Sutton’s Electronic Repair Shop has budgeted the following time and material for 2020....

    Practice Problem 1 Sutton’s Electronic Repair Shop has budgeted the following time and material for 2020. SUTTON’S ELECTRONIC REPAIR SHOP Budgeted Costs for the Year 2020 Time Charges Material Loading Charges Shop employees’ wages and benefits $99,640 ― Parts manager’s salary and benefits ― $25,400 Office employee’s salary and benefits 17,860 13,360 Overhead (supplies, depreciation, advertising, utilities) 28,200 19,380 Total budgeted costs $145,700 $58,140 Sutton’s budgets 4,700 hours of repair time in 2020 and will bill a profit of $14...

  • Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2017 is...

    Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2017 is available for Second Chance. Time Charges Material Loading Charges Technicians' wages and benefits $237,000 - Parts manager's salary and benefits - $39,100 Office employee's salary and benefits 71,100 9,169 Other overhead 39,500 19,300 Total budgeted costs $347,600 $67,569 The company desires a $34.00 profit margin per hour of labor and a 21.00% profit margin on parts. It has budgeted for 7,900 hours of repair...

  • Bonita Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available...

    Bonita Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available for Bonita Time Charges $237,000 Material Loading Charges Technicians' wages and benefits Parts manager's salary and benefits Office employee's salary and benefits Other overhead Total budgeted costs 71.100 39,500 $347.600 $39,100 8,900 19,200 $67,200 The company desires a $34 profit margin per hour of labor and a 21.00% profit margin on parts. It has budgeted for 7,900 hours of repair time in the coming...

  • Practice Problem 1 Sutton's Electronic Repair Shop has budgeted the following time and material for 2020....

    Practice Problem 1 Sutton's Electronic Repair Shop has budgeted the following time and material for 2020. SUTTON'S ELECTRONIC REPAIR SHOP Budgeted Costs for the Year 2020 Time Charges Material Loading Charges Shop employees' wages and benefits $101,050 Parts manager's salary and benefits $25,400 Office employee's salary and benefits 20,210 17,650 Overhead (supplies, depreciation, advertising, utilities) 24,440 16,800 Total budgeted costs $145,700 $59,850 Sutton's budgets 4,700 hours of repair time in 2020 and will bill a profit of $14 per labor...

  • Sutton's Electronic Repair Shop has budgeted the followingg time and material for 2020. SUTTON'S ELECTRONIC REPAIR...

    Sutton's Electronic Repair Shop has budgeted the followingg time and material for 2020. SUTTON'S ELECTRONIC REPAIR SHOP Budgeted Costs for the Year 2020 Material Loading Charges Time Charges $118,800 Shop employees' wages and benefits Parts manager's salary and benefits $25,400 21,600 15,400 Office employee's salary and benefits 27,000 17,340 Overhead (supplies, depreciation, advertising, utilities) $167,400 $58,140 Total budgeted costs Sutton's budgets 5,400 hours of repair time in 2020 and will bill a profit of $14 per labor hour along with...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT