WATERWAYS CORPORATION Budgeted Costs for Irrigation Projects Time Charges Material Loading Charges Labor wages (5,700 hours)...


WATERWAYS CORPORATION
Budgeted Costs for Irrigation Projects
Time
Charges
Material
Loading
Charges
Labor wages (5,700 hours) $238,260
Supervisor’s salary $62,000
Clerical and accountant wages 58,140 4,000
Irrigation supplies manager 39,000
Overhead 53,010 21,720
   Total $349,410 $126,720


Waterways has budgeted for 5,700 labor hours. It desires a $13 profit margin per hour of labor and 15% profit on materials. It estimates the total invoice cost of materials in the coming year will be $660,000.

A.Compute the rate per hour of labor. (Round answer to 2 decimal places, e.g. 52.75.)
labor rate $74.3

B.Compute the material loading charge.

material loading charge = 35.20% (this is wrong)

C.

Waterways has received a request for a bid to do a parkway for the city. The irrigation manager estimates that it will take about a month to complete the project and require 530 hours of labor and $84,000 of materials. Compute the total estimated bid for the parkway project. (Round answer to 0 decimal places, e.g. 5,275.)

Total estimated bid for the parkway project $ ???????

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans:

A. Calculate the rate per hour of labor as shown below:

Rate Per Hour of labor

=Total Direct labor cost/Total direct labor hours+Desired Margin per labour Hour

=$349,410/5700+13

=61.3+13

=74.30

Therefore the direct labor rate per hour is $74.30

B. Calculate the Material loading charge as shown below:

Material loading charges=Total material Loading charges/Estimated cost of materials + Desired Margin on Materials

=$126,720/$660,000+15%

=.192+.15

=.342

=34.20%

The Material Loading charge is 34.20%

C. Calculate the estimated bid for the Project

Estimated Bid=Materials costs +Labor costs+ Margin on materials and labor

=84,000+84,000+34.20/530 Hours*74.30

=112,728+39,379

=$152,107

The estimated bid for the Project is $152,107

Add a comment
Know the answer?
Add Answer to:
WATERWAYS CORPORATION Budgeted Costs for Irrigation Projects Time Charges Material Loading Charges Labor wages (5,700 hours)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 9 View Policies Current Attempt in Progress Waterways uses time and material pricing when it bids on irrigatio...

    Question 9 View Policies Current Attempt in Progress Waterways uses time and material pricing when it bids on irrigation projects. Budgeted data for the coming year are as follows. WATERWAYS CORPORATION Budgeted Costs for Irrigation Projects Material Time Loading Charges Charges Labor wages (5900 hours) $237770 Supervisor's salary $61000 Clerical and accountant wages 63130 4000 Irrigation supplies manager 41000 Overhead 54280 22050 Total $355180 $128050 Waterways has budgeted for 5900 labor hours. It desires a $13 profit margin per hour...

  • Waterways uses time and material pricing when it bids on irrigation projects. Budgeted data for the...

    Waterways uses time and material pricing when it bids on irrigation projects. Budgeted data for the coming year are as follows. WATERWAYS CORPORATION Budgeted Costs for Irrigation Projects Time Charges $243,000 Material Loading charges Labor wages (6,000 hours) Supervisor's salary Clerical and accountant wages Irrigation supplies manager Overhead 58,800 $57,000 3,000 41,000 21,140 $122, 140 57,000 $358,800 Total Waterways has budgeted for 6,000 labor hours. It desires a $15 profit margin per hour of labor and 16% profit on materials....

  • TIME AND MATERIAL PRICING! • Total budgeted Time Charges are $345,600. • Total budgeted Material Loading...

    TIME AND MATERIAL PRICING! • Total budgeted Time Charges are $345,600. • Total budgeted Material Loading Charges are $165,060. Total expected labor hours are 12,000 hours. Total expected materials cost is $1,260,000. Profit margin per hour on labor is $40. Profit margin on materials is 80%. • Determine the total price of a job that requires 150 hours of labor and $60,000 in parts.

  • Practice Problem 1 Sutton’s Electronic Repair Shop has budgeted the following time and material for 2020....

    Practice Problem 1 Sutton’s Electronic Repair Shop has budgeted the following time and material for 2020. SUTTON’S ELECTRONIC REPAIR SHOP Budgeted Costs for the Year 2020 Time Charges Material Loading Charges Shop employees’ wages and benefits $99,640 ― Parts manager’s salary and benefits ― $25,400 Office employee’s salary and benefits 17,860 13,360 Overhead (supplies, depreciation, advertising, utilities) 28,200 19,380 Total budgeted costs $145,700 $58,140 Sutton’s budgets 4,700 hours of repair time in 2020 and will bill a profit of $14...

  • 1. Gibco Service has budgeted the following time-and-material for 2019: Budgeted Costs For 2019 Time Charges...

    1. Gibco Service has budgeted the following time-and-material for 2019: Budgeted Costs For 2019 Time Charges $38,000 Material Charges Painters' wages and benefits Service manager's salary and benefits Office employee's salary and benefits Cost of paint Overhead (supplies, utilities, etc.) 12,000 $24,000 3.000 60,000 7,500 11,000 Gibco budgets 4,200 hours of paint time in 2019 and will charge a profit of $10 per hour on the labour rate, in addition to a 25% mark-up on the cost of paint. On...

  • Sutton's Electronic Repair Shop has budgeted the followingg time and material for 2020. SUTTON'S ELECTRONIC REPAIR...

    Sutton's Electronic Repair Shop has budgeted the followingg time and material for 2020. SUTTON'S ELECTRONIC REPAIR SHOP Budgeted Costs for the Year 2020 Material Loading Charges Time Charges $118,800 Shop employees' wages and benefits Parts manager's salary and benefits $25,400 21,600 15,400 Office employee's salary and benefits 27,000 17,340 Overhead (supplies, depreciation, advertising, utilities) $167,400 $58,140 Total budgeted costs Sutton's budgets 5,400 hours of repair time in 2020 and will bill a profit of $14 per labor hour along with...

  • just e8.9 5.200 24UR The company desin eted for 7.600 hours of repair Total budgeted costs $281.200 $75,500 "pan...

    just e8.9 5.200 24UR The company desin eted for 7.600 hours of repair Total budgeted costs $281.200 $75,500 "pany desires a $30 profit margin per hour of labor and a 20% profit margin on parts. It has budg- Po hours of repair time in the coming year, and estimates that the total invoice cost of parts and materials in 2020 will be $400,000. Instructions a. Compute the rate charged per hour of labor. Compute the material loading percentage. (Round to...

  • 1) Compute the labor rate per hour, 2) Compute the material loading percentage 3) Compute the...

    1) Compute the labor rate per hour, 2) Compute the material loading percentage 3) Compute the total estimated bill, Question 2 Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and video systems for homes. On newly constructed homes it provides bids using time-and-material pricing. The following budgeted cost data are available. Time Charges Material Loading Charges Technicians' wages and benefits $140,700 Parts manager's salary and benefits Office employee's salary and benefits 30,820 Other overhead 18,760 Total budgeted...

  • Vaughn Manufacturing has the following budgeted costs for the next year: Time Charges Material Charges Shop...

    Vaughn Manufacturing has the following budgeted costs for the next year: Time Charges Material Charges Shop employees’ wages and benefits $125000 $- Parts manager’s salary and benefits - 45000 Office employee’s salary and benefits 25000 15000 Other overhead 20000 40000 Invoice cost of parts and materials - 400000 Total budgeted costs $170000 $500000 The material loading charge to be used next year assuming a 40% markup on material cost is 20%. 40%. 80%. 66%.

  • P22-3B Armstrong Bike Repair Shop has budgeted the following time and material for 2017 Armstrong Bike...

    P22-3B Armstrong Bike Repair Shop has budgeted the following time and material for 2017 Armstrong Bike Repair Shop Budgeted Costs for the Year 2017 Time Material Charges Loading Charges Shop employees' wages and benefits $36.000 Parts supervisor's salary and benefits $20,000 Office employee's salary and benefits 15,000 10,000 Overhead (supplies, depreciation, advertising, utilities) 19,000 15,000 Total budgeted costs $70.000 $45.000 Armstrong budgets 2,500 hours of repair time in 2017 and will bill a profit of $5 per labor hour along...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT