Question

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600
Estimated costs to complete as of year-end 5,810,000 1,826,000 0
Billings during the year 2,030,000 4,444,000 3,526,000
Cash collections during the year 1,815,000 3,900,000 4,285,000


Westgate recognizes revenue over time according to percentage of completion.

3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.)

I need partial balance sheet current assets and current liabilities

pleaseeee I need the answer urgent

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks!
Westgate Construction Company
Workings Calculation of Gross Profit
Particulars 2021 2022 2023
Contract Price         10,000,000       10,000,000         10,000,000 A
Cost Incurred during the year           2,490,000          3,984,000           2,008,600 C
Cost Incurred to date           2,490,000          6,474,000           8,482,600
(Cost incurred to date of the present year less Cost incurred to date of the previous year)
Estimated cost to complete           5,810,000          1,826,000                         -   D
Estimated total cost           8,300,000          8,300,000           8,482,600 E=C+B
(Cost Incurred to date+ Estimated cost to complete )
Percentage complete 30.00% 78.00% 100.00% F=B/E
(Cost Incurred to date/Estimated total cost)
Revenue to be recognized           3,000,000          4,800,000           2,200,000 G
(Contract Price*Percentage complete)- revenue previously recognized
Year 2021: 30% completed. Revenue recognized = 30% x $ 10,000,000 = $ 3,000,000.
Year 2022: 77% completed. Revenue recognized = 78% x $ 10,000,000 – $ 3,000,000 (previously recognized) = $ 4,800,000.
Year 2023: 100% completed. Revenue recognized = 100% x $ 10,000,000 – $ 3,000,000- $ 4,780,000 (previously recognized) = $ 2,200,000.
Gross Profit/(Loss)              510,000             816,000              191,400 H=G-C
Billings during the year     2,030,000.00    4,444,000.00     3,526,000.00
Cash collections during the year     1,815,000.00    3,900,000.00     4,285,000.00
Ans to 3 Workings for Balance Sheet
CIP (Work-in-progress)
Balance Sheet (Partial) 2021 2022 Account Amount ($)
Current Assets: Cash                           2,490,000.00
CIP (Work-in-progress)     3,000,000.00    7,800,000.00 Gross Profit                               510,000.00
         3,000,000         7,800,000 Balance at the end of 2021                           3,000,000.00
Current Liabilities: Cash                           3,984,000.00
Billing on CIP     2,030,000.00    4,444,000.00 Gross Profit                               816,000.00
    2,030,000.00 4,444,000.00 Balance at the end of 2022                           7,800,000.00
Billing on CIP
Account Amount ($)
Accounts Receivable                           2,030,000.00
Balance at the end of 2021                           2,030,000.00
Accounts Receivable                           4,444,000.00
Balance at the end of 2022                           6,474,000.00
Add a comment
Know the answer?
Add Answer to:
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. Problem...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 4....

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $ 2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 2023 $2,008,600 0 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. Problem...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008, 600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion....

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,490,000 5,810,000 2,030,000 1,815,000 2019 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 3....

  • [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...

    [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000...

  • ! Required information [The following information applies to the questions displayed below.] In 2021, the Westgate...

    ! Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT