In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2021 | 2022 | 2023 | |||||||
Cost incurred during the year | $ | 2,490,000 | $ | 3,984,000 | $ | 2,008,600 | |||
Estimated costs to complete as of year-end | 5,810,000 | 1,826,000 | 0 | ||||||
Billings during the year | 2,030,000 | 4,444,000 | 3,526,000 | ||||||
Cash collections during the year | 1,815,000 | 3,900,000 | 4,285,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.)
I need partial balance sheet current assets and current liabilities
pleaseeee I need the answer urgent
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks! |
Westgate Construction Company | |||||
Workings | Calculation of Gross Profit | ||||
Particulars | 2021 | 2022 | 2023 | ||
Contract Price | 10,000,000 | 10,000,000 | 10,000,000 | A | |
Cost Incurred during the year | 2,490,000 | 3,984,000 | 2,008,600 | C | |
Cost Incurred to date | 2,490,000 | 6,474,000 | 8,482,600 | ||
(Cost incurred to date of the present year less Cost incurred to date of the previous year) | |||||
Estimated cost to complete | 5,810,000 | 1,826,000 | - | D | |
Estimated total cost | 8,300,000 | 8,300,000 | 8,482,600 | E=C+B | |
(Cost Incurred to date+ Estimated cost to complete ) | |||||
Percentage complete | 30.00% | 78.00% | 100.00% | F=B/E | |
(Cost Incurred to date/Estimated total cost) | |||||
Revenue to be recognized | 3,000,000 | 4,800,000 | 2,200,000 | G | |
(Contract Price*Percentage complete)- revenue previously recognized | |||||
Year 2021: 30% completed. Revenue recognized = 30% x $ 10,000,000 = $ 3,000,000. | |||||
Year 2022: 77% completed. Revenue recognized = 78% x $ 10,000,000 – $ 3,000,000 (previously recognized) = $ 4,800,000. | |||||
Year 2023: 100% completed. Revenue recognized = 100% x $ 10,000,000 – $ 3,000,000- $ 4,780,000 (previously recognized) = $ 2,200,000. | |||||
Gross Profit/(Loss) | 510,000 | 816,000 | 191,400 | H=G-C | |
Billings during the year | 2,030,000.00 | 4,444,000.00 | 3,526,000.00 | ||
Cash collections during the year | 1,815,000.00 | 3,900,000.00 | 4,285,000.00 | ||
Ans to 3 | Workings for Balance Sheet | ||||
CIP (Work-in-progress) | |||||
Balance Sheet (Partial) | 2021 | 2022 | Account | Amount ($) | |
Current Assets: | Cash | 2,490,000.00 | |||
CIP (Work-in-progress) | 3,000,000.00 | 7,800,000.00 | Gross Profit | 510,000.00 | |
3,000,000 | 7,800,000 | Balance at the end of 2021 | 3,000,000.00 | ||
Current Liabilities: | Cash | 3,984,000.00 | |||
Billing on CIP | 2,030,000.00 | 4,444,000.00 | Gross Profit | 816,000.00 | |
2,030,000.00 | 4,444,000.00 | Balance at the end of 2022 | 7,800,000.00 | ||
Billing on CIP | |||||
Account | Amount ($) | ||||
Accounts Receivable | 2,030,000.00 | ||||
Balance at the end of 2021 | 2,030,000.00 | ||||
Accounts Receivable | 4,444,000.00 | ||||
Balance at the end of 2022 | 6,474,000.00 |
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. Problem...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 4....
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $ 2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 2023 $2,008,600 0 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. Problem...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008, 600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion....
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,490,000 5,810,000 2,030,000 1,815,000 2019 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 3....
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000...
! Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000...