Solution 3:
Predetermined overhead rate = $824000/ 16000 = $51.50 per machine hour
Cost of jobs in Production as of March 31 = Cost of Job 66 + cost of Job 67
= 44000+65000+(2000*51.50) + 15000+8800+(500*51.50) = $261,550
Solution 4:
The finished goods inventory increase by = Cost of Job 64 = $84100 + 21000+35000+(1200*51.50) = $201,900
Solution 5:
Applied overhead = Total machine hours used *$51.51
= (1200+700+2000+500) *$51.50 = $226,600
Actual Overhead cost = 32300+60200+5200+139700 = $237,400
The overhead was underapplied by = $237400- 226600 = $10,800
3. ?? 4.?? 5.?? The following information applies to the questions displayed below. Stellar Sound, Inc....
Required information [The following information applies to the questions displayed below.] Stellar Sound, Inc. which uses a job-order costing system, had two jobs in process at the start of 20x1: job no. 64 ($84,100) and job no. 65 ($53,500). The following information is available: a. The company applies manufacturing overhead on the basis of machine hours (based on practical capacity). Budgeted overhead and machine activity for the year were anticipated to be $792,000, and 16,000 hours, respectively. b. The company...
Required information [The following information applies to the questions displayed below.] Stellar Sound, Inc. which uses a job-order costing system, had two jobs in process at the start of 20x1: job no. 64 ($84,100) and job no. 65 ($53,400). The following information is available: a. The company applies manufacturing overhead on the basis of machine hours (based on practical capacity). Budgeted overhead and machine activity for the year were anticipated to be $824,000, and 16,000 hours, respectively. b. The company...
Required information [The following information applies to the questions displayed below.] Stellar Sound, Inc. which uses a job-order costing system, had two jobs in process at the start of 20x1: job no. 64 ($84,100) and job no. 65 ($53,300). The following information is available: a. The company applies manufacturing overhead on the basis of machine hours (based on practical capacity). Budgeted overhead and machine activity for the year were anticipated to be $824,000, and 16,000 hours, respectively. b. The company...
Required information [The following information applies to the questions displayed below.) Stellar Sound, Inc. which uses a job-order costing system, had two jobs in process at the start of 20x1: job no. 64 ($84,100) and job no. 65 ($53,400). The following information is available: a. The company applies manufacturing overhead on the basis of machine hours (based on practical capacity). Budgeted overhead and machine activity for the year were anticipated to be $792,000, and 16,000 hours, respectively. b. The company...
Stellar Sound, Inc. which uses a job-order costing system, had two jobs in process at the start of 20x1: job no. 64 ($84,100) and job no. 65 ($53,500). The following information is available: a. The company applies manufacturing overhead on the basis of machine hours (based on practical capacity). Budgeted overhead and machine activity for the year were anticipated to be $792,000, and 16,000 hours, respectively. b. The company worked on four jobs during the first quarter. Direct materials used,...
Can someone help me determine the correct responses to this muli-part question?? Stellar Sound, Inc. which uses a job-order costing system, had two jobs in process at the start of 20x1: job no. 64 ($84,200) and job no. 65 ($53,500). The following information is available: a. The company applies manufacturing overhead on the basis of machine hours (based on practical capacity). Budgeted overhead and machine activity for the year were anticipated to be $792,000, and 16,000 hours, respectively. b. The...
Stellar Sound, Inc. which uses a job-order costing system, had two jobs in process at the start of 20x1: job no. 64 ($84,100) and job no. 65 ($53,300). The following information is available: a. The company applies manufacturing overhead on the basis of machine hours (based on practical capacity). Budgeted overhead and machine activity for the year were anticipated to be $840,000, and 16,000 hours, respectively. b. The company worked on four jobs during the first quarter. Direct materials used,...
Was manufacturing overhead under- or overapplied for the first quarter of the year? By how much? (Do not round intermediate calculations.) Required information [The following information applies to the questions displayed below.] Stellar Sound, Inc. which uses a job-order costing system, had two jobs in process at the start of 20x1: job no. 64 ($84,000) and job no. 65 ($53,300). The following information is available: a. The company applies manufacturing overhead on the basis of machine hours (based on practical...
Can someone help me find the cost of jobs still in production as of March 31?? Ive seen multiple responses to this problem online that are incorrect Required information [The following information applies to the questions displayed below.] Stellar Sound, Inc. which uses a job-order costing system, had two jobs in process at the start of 20x1: job no. 64 ($84,200) and job no. 65 ($53,500). The following information is available: a. The company applies manufacturing overhead on the basis...
1. Determine the company's predetermined overhead application rate. (Round your answer to 2 decimal places.) 3. Determine the cost of jobs still in production as of March 31. (Round your answer to 2 decimal places.) Cost of the jobs in production 4. Did the finished-goods inventory increase or decrease during the first quarter? By how much? (DO not round intermediate calculations.) The finished-goods inventory by 5. Was manufacturing overhead under-or overapplied for the first quarter of the year? By how...