Question

Dont tell me weve lost another bid exclaimed Sandy Kovallas, president of Lerko Products, Incm afraid so, replied Doug Ma
The company uses a plantwide overhead rate to apply manufacturing overhead cost to jobs. Required: 1. Assuming the use of a p
b. Determine the amount of manufacturing overhead cost that would have been applied to the Hastings job, Manuachung von COSE
a. Compute the underapplied or overapplied overhead for the year, assuming that a plantwide overhead rate is used. b. Compute


Dont tell me weve lost another bidra exclaimed Sandy Kovalas, president of Lenko Products, inc. Im so repiled Doug Martin,
a.Compute the rate for the current year. Predetermined overhead rate of direct labour cost b. Determine the amount of manufac
4. Assume that it is customary in the industry to bid Jobs at 150% of total manufacturing cost (direct materials, direct labo
b. Compute the underapplied or overapplied overhead for the year, assuming that departmental overhead rates are used. Cutting
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1-a) Predetermined overhead rate= Total manufacturing overhead/Total direct labor

= $1440000*100/900000= 160% of direct labor cost

b) Applied manufacturing costs= Actual total direct labor costs*Predetermined overhead rate

= $21200*160%= $33920

2-a) Cutting department= $540000*100/300000= 180%

Machining department= $800000*100/200000= 400%

Assembly department= $100000*100/400000= 25%

b)

Cutting department ($6500*180%) $11700
Machining department ($1700*400%) 6800
Assembly department (13000*25%) 3250
Total manufacturing overhead cost applied $21750

4-a)

Direct materials $18500
Direct labor 21200
Manufacturing overhead applied 33920
Total manufacturing costs $73620
Bid price of the jobs ($73620*1.50) $110430

b)

Direct materials $18500
Direct labor 21200
Manufacturing overhead applied 21750
Total manufacturing costs $61450
Bid price of the jobs ($61450*1.50) $92175

5-a) Manufacturing overhead applied= Actual total direct labor costs*Predetermined overhead rate

= $870000*160%= $1392000

Overapplied or underapplied overhead= Manufacturing overhead applied-Actual manufacturing overhead

= $1392000-1482000= $90000 underapplied

Underapplied overhead cost $90000

b) Cutting Department

Manufacturing overhead applied= $320000*180%= $576000

Overapplied or underapplied overhead= Manufacturing overhead applied-Actual manufacturing overhead

= $576000-560000= $16000 overapplied

Machining Department

Manufacturing overhead applied= $210000*400%= $840000

Overapplied or underapplied overhead= Manufacturing overhead applied-Actual manufacturing overhead

= $840000-830000= $10000 overapplied

Assembly Department

Manufacturing overhead applied= $340000*25%= $85000

Overapplied or underapplied overhead= Manufacturing overhead applied-Actual manufacturing overhead

= $85000-92000= $7000 underapplied

Cutting Overapplied Overhead cost $16000
Machining Overapplied Overhead cost $10000
Assembly Underapplied Overhead cost $7000
Total plant Overapplied Overhead cost $19000

Total plant overhead cost= Overapplied of Cutting+Overapplied of Machining-Underapplied of Assembly

= $16000+10000-7000= $19000 overapplied

Add a comment
Know the answer?
Add Answer to:
"Don't tell me we've lost another bid exclaimed Sandy Kovallas, president of Lerko Products, Incm afraid...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • "Don't tell me we've lost another bid!” exclaimed Janice Hudson, president of Prime Products Inc. “I'm...

    "Don't tell me we've lost another bid!” exclaimed Janice Hudson, president of Prime Products Inc. “I'm afraid so,” replied Doug Martin, the operations vice president. “One of our competitors underbid us by about $11,000 on the Hastings job." "I just can't figure it out," said Hudson. "It seems we're either too high to get the job or too low to make any money on half the jobs we bid. What's happened?" Prime Products manufactures specialized goods to customers' specifications and...

  • "Don't tell me we've lost another bid!" exclaimed Janice Hudson, president of Prime Products Inc. "I'm...

    "Don't tell me we've lost another bid!" exclaimed Janice Hudson, president of Prime Products Inc. "I'm afraid so," replied Doug Martin, the operations vice president. "One of our competitors underbid us by about $13,000 on the Hastings job." "I just can't figure it out," said Hudson. "It seems we're either too high to get the job or too low to make any money on half the jobs we bid. What's happened?" Prime Products manufactures specialized goods to customers' specifications and...

  • "Don't tell me we've lost another bid!" exclaimed Janice Hudson, president of Prime Products Inc. "I'm...

    "Don't tell me we've lost another bid!" exclaimed Janice Hudson, president of Prime Products Inc. "I'm afraid so," replied Doug Martin, the operations vice president. "One of our competitors underbid us by about $12,000 on the Hastings job." "I just can't figure it out," said Hudson. “It seems we're either too high to get the job or too low to make any money on half the jobs we bid. What's happened?" Prime Products manufactures specialized goods to customers' specifications and...

  • "Don't tell me we've lost another bid!" exclaimed Janice Hudson, president of Prime Products Inc. "I'm...

    "Don't tell me we've lost another bid!" exclaimed Janice Hudson, president of Prime Products Inc. "I'm afraid so," replied Doug Martin, the operations vice president. "One of our competitors underbid us by about $11,000 on the * Hastings job." "I just can't figure it out," said Hudson. "It seems we're either too high to get the job or too low to make any money on half the jobs we bid. What's k happened?" Prime Products manufactures specialized goods to customers'...

  • "Don't tell me we've lost another bid!" exclaimed Sandy Kovallas, president of Lenko Products, Inc. "I'm...

    "Don't tell me we've lost another bid!" exclaimed Sandy Kovallas, president of Lenko Products, Inc. "I'm afraid so," replied Doug Martin, the operations vice president. "One of our competitors underbid us by about $9,800 on the Hastings job." "I just can’t figure it out," said Kovallas. "It seems we’re either too high to get the job or too low to make any money on half the jobs we bid anymore. What’s happened?"      Lenko Products manufactures specialized goods to customers'...

  • Don't tell me we've lost another bid!" exclaimed Janice Hudson, president of Prime Products Inc. "I'm...

    Don't tell me we've lost another bid!" exclaimed Janice Hudson, president of Prime Products Inc. "I'm afraid so," repl he operations vice president. "One of our competitors underbid us by about $10,000 on the Hastings job." "I just can aid Hudson. "It seems we're either too high to get the job or too low to make any money on half the jobs we bid. Wh Prime Products manufactures specialized goods to customers' specifications and operates a job-order costing system overhead...

  • “Don’t tell me we’ve lost another bid!” exclaimed Janice Hudson, president of Prime Products Inc. “I’m...

    “Don’t tell me we’ve lost another bid!” exclaimed Janice Hudson, president of Prime Products Inc. “I’m afraid so,” replied Doug Martin, the operations vice president. “One of our competitors underbid us by about $13,000 on the Hastings job.” “I just can’t figure it out,” said Hudson. “It seems we’re either too high to get the job or too low to make any money on half the jobs we bid. What’s happened?” Prime Products manufactures specialized goods to customers’ specifications and...

  • Don't tell me we've lost another bid!" exclaimed Janice Hudson, president of Prime Products Inc. "I'm...

    Don't tell me we've lost another bid!" exclaimed Janice Hudson, president of Prime Products Inc. "I'm afraid so," replied Doug Martin, the operations vice-president. One of our competitors underbid us by about $11,000 on the Hastings job." "1 just can't figure it out," said Hudson. "lt seems we're either too high to get the job or too low to make any money on half the jobs we bid. What's happened? Prime Products manufactures specialized goods to customers' specifications and operates...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $2,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid. Teledex Company manufactures products to customers' specifications and operates a job order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $4,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and operates a job order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT