Plantwide predetermined overhead rate = ( Estimated total fixed manufacturing overhead / Estimated total machine hours ) + Estimated variable manufacturing overhead per machine hour = ( 344000 / 40000 ) + 3.90 | 12.50 | per MH |
Amount of overhead applied to M759 = Machine hours required * Plantwide predetermined overhead rate = 60 * 12.50 | 750 |
Beat Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Beat Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 40,000 Total fixed manufacturing overhead cost $ 344,000 Variable manufacturing overhead per machine-hour $ 3.90 Recently, Job M759 was completed. It required 60 machine-hours. The amount of overhead applied to Job M759 is closest to: (Round your intermediate calculations to 2 decimal places.) Garrison 16e Rechecks...
Harootunian Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine- hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine hour 80,000 $312,000 $ 2.10 Recently, Job T629 was completed with the following characteristics: Number of units in the job Total machine-hours 50 200 The predetermined overhead rate is closest to: Multiple Choice o $8.10...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 32,300 Total fixed manufacturing overhead cost $ 581,400 Variable manufacturing overhead per machine-hour $ 2.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 40 Direct materials $ 630 Direct labor cost $ 1,260 The amount of...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 32,000 $352,000 $ 3.00 Recently, Job T687 was completed with the following characteristics: 10 Number of units in the job Total machine-hours Direct materials Direct labor cost 40 $ 675 $1,350 The amount of overhead...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 33,000 Total fixed manufacturing overhead cost $ 660,000 Variable manufacturing overhead per machine-hour $ 6.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 40 Direct materials $ 715 Direct labor cost $ 1,430 The amount of...
Spang Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 20,000 $176,000 2.20 Recently, Job P505 was completed with the following characteristics Total machine-hours Direct materials Direct labor cost 200 $ 540 $7,200 The amount of overhead applied to Job P505 is closest to: Multiple...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 30,700 $337, 700 $ 4.00 Recently, Job T687 was completed with the following characteristics: 10 Number of units in the job Total machine-hours Direct materials Direct labor cost 20 $ 575 $1,150 The amount of overhead...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 30,500 Total fixed manufacturing overhead cost $ 610,000 Variable manufacturing overhead per machine-hour $ 6 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 690 Direct labor cost $ 1,370 The amount of...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 33,000 Total fixed manufacturing overhead cost $ 660,000 Variable manufacturing overhead per machine-hour $ 6 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 40 Direct materials $ 715 Direct labor cost $ 1,430 The amount of...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 30,900 Total fixed manufacturing overhead cost $154,500 Variable manufacturing overhead per machine-hour $3 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 rect materials $740 Direct labor cost $1,480 The amount of overhead applied to Job...