Waterways has two major public park projects to provide with comprehensive irrigation in one of its service locations this mo
Set up the job cost sheets for Job No. 357 and Job No. K52. Determine the total cost for each manufacturing special order for


PR A CA U 33,00. Dec. 2 Dec. 12 Dec. 13 Dec. 18 Dec. 21 Dec. 31 Issued $40,300 of direct materials from the companys Invento
0 0
Add a comment Improve this question Transcribed image text
Answer #1

PARTICULARS J57 K52

RAW MATERIAL $6412 $3206

LABOUR $186 $93

OVERHEAD(MACHINE)       $2424(404*6HRS)   $3434(404*8.5HRS)

TOTAL COST $9022 $6733

UNIT PRODUCED 200 100

UNIT COST 45.11 67.33

WORKINGS

1) MACHINE HOURS- 2115

OVERHEAD COST- $ 854460

MACHINE HOURS RATE- $854460/2115= $404 PER HOUR

2)  FIXED COST ARE NOT ALLOCATED TO SPECIAL ORDER SO SALARY, WATERBILL AND SO ON ARE NOT ALLOWED TO BE ALLOCATED TO SPECIAL ORDER.

Add a comment
Know the answer?
Add Answer to:
Waterways has two major public park projects to provide with comprehensive irrigation in one of its...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Waterways has two major public park projects to provide with comprehensive irrigation in one of its...

    Waterways has two major public park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company's inventory on December 2 for $5,094; on December 8 for $1,056; and on December...

  • Waterways has two major public park projects to provide with comprehensive irrigation in one of its...

    Waterways has two major public park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special- order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company's inventory on December 2 for $5,031; on December 8 for $1,065; and on...

  • Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service...

    Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company's inventory on December 2 for $5,106; on December 8 for $1,056; and on December 14...

  • NE Waterways Problem 02 a-c Waterways has two major public park projects to provide with comprehensive...

    NE Waterways Problem 02 a-c Waterways has two major public park projects to provide with comprehensive irrigation in one of its service locations this month. Job 357 and Job K52 Involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company's Inventory on December 2 for $5,067; on December 8...

  • Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service...

    Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company’s inventory on December 2 for $5,091; on December 8 for $1,050; and on December 14...

  • Waterways Problem 02 a-c (Part Level Submission) Waterways has two major public park projects to provide...

    Waterways Problem 02 a-c (Part Level Submission) Waterways has two major public park projects to provide with comprehensive irrigation in one of its service locations this month. Job 357 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December Raw materials were requisitioned from the company's inventory on December 2 for $5,097; on...

  • Waterways Problem 02 a-c Waterways has two major public-park projects to provide with comprehensive irrigation in...

    Waterways Problem 02 a-c Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company’s inventory on December 2 for $5,097; on December 8 for $1,065;...

  • Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations th...

    Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company’s inventory on December 2 for $5,064; on December 8 for $1,068; and on December 14...

  • Question 2 View Policies Current Attempt in Progress Waterways has two major public park projects to...

    Question 2 View Policies Current Attempt in Progress Waterways has two major public park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December Raw materials were requisitioned from the company's inventory on December 2 for $5067;...

  • Waterways Problem 02 a-c (Part Level Submission) Waterways has two major public-park projects to provide with...

    Waterways Problem 02 a-c (Part Level Submission) Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company’s inventory on December 2 for $5,091; on December...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT