CEPEDA CORPORATION | ||||
Cost of Goods manufactured Schedule | ||||
For the Month Ended June 2020 | ||||
Particulars | $ | $ | $ | |
Work in process inventory, December 1 | 3,300 | |||
Direct Materials used | 22,180 | |||
Direct Labor | 41,330 | |||
Add: | Factory overhead | |||
Indirect Factory labor | 4,760 | |||
Factory Utilities | 410 | |||
Depreciation, factory equipment | 1,600 | |||
Maintenance, factory equipment | 1,980 | |||
Indirect Materials | 2,400 | |||
Factory manager's salary | 3,530 | |||
Total Factory overhead | 14,680 | |||
Total manufacturing costs incurred during June | 78,190 | |||
Total manufacturing costs | 81,490 | |||
Less: | Work in process inventory, 6/30/20 | 4,420 | ||
Cost of goods manufactured | 77,070 |
Feel free to ask any clarification, if required. Kindly
provide feedback by thumbs up, if satisfied. It will be highly
appreciated.
Thank you.
Exercise 1-12 (Video) (Part Level Submission) Cepeda Corporation has the following cost records for June 2020....
Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,760 Factory utilities $470 Direct materials used 22,680 Depreciation, factory equipment 1,540 Work in process, 6/1/20 3,540 Direct labor 42,930 Work in process, 6/30/204,880 Maintenance, factory equipment 1,850 Finished goods, 6/1/20 5,940 Indirect materials 2,820 Finished goods, 6/30/20 7,940 Factory manager's salary 3,120 (a) Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule Save for Later
Exercise 14-12 Cepeda Corporation has the following cost records for June 2020. Indirect factory labor Direct materials used Work in process, 6/1/20 Work in process, 6/30/20 Finished goods, 6/1/20 Finished goods, 6/30/20 $5,000 Factory utilities 22,910 Depreciation, factory equipment 3,690 Direct labor 4,170 Maintenance, factory equipment 5,350 Indirect materials 8,480 Factory manager's salary $430 1,790 41,860 1,960 2,540 3,330 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule << ব য য...
*Exercise 10-12 (Part Level Submission) Cepeda Corporation has the following cost records for June 2017 Indirect factory labor Direct materials used Work in process, 6/1/17 Work in process, 6/30/17 Finished goods, 6/1/17 Finished goods, 6/30/17 $4,500 20,000 3,000 3,800 5,000 7,500 Factory utilities Depreciation, factory equipment Direct labor Maintenance, factory equipment Indirect materials Factory manager's salary $400 1,400 40,000 1,800 2,200 3,000 *(a) Prepare a cost of goods manufactured schedule for June 2017. CEPEDA CORPORATION Cost of Goods Manufactured Schedule...
help with read part Cepeda Corporation has the following cost records for June 2020. Indirect factory labor Direct materials used Work in process, 6/1/20 Work in process, 6/30/20 Finished goods, 6/1/20 Finished goods, 6/30/20 $5,440 22,340 3,100 4,760 5,900 7,690 Factory utilities Depreciation, factory equipment Direct labor Maintenance, factory equipment Indirect materials Factory manager's salary $480 1,500 41,010 1,840 2,820 3,640 (a) Prepare an income statement through gross profit for June 2020 assuming sales revenue is $87,610. CEPEDA CORPORATION Income...
Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,600 Factory utilities $410 1.500 Direct materials used 21,000 Depreciation, factory equipment 41,000 Work in process. 6/1/20 Work in process, 6/30/20 3,100 Direct labor 3.900 Maintenance, factory equipment 1.810 Finished goods, 6/1/20 Finished goods, 6/30/20 5.100 7,600 Indirect materials Factory manager's salary 2,100 3,100 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule
Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $5.330 Factory utilities $440 Direct materials used Work in process, 6/1/20 22,580 3,910 Depreciation, factory equipment Direct labor 1,640 42,770 Work in process, 6/30/20 Finished goods, 6/1/20 Finished goods, 6/30/20 4,680 5,510 ,270 Maintenance, factory equipment Indirect materials Factory manager's salary 1,940 2.430 3.210 8 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule
Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $5,150 Factory utilities $500 Direct materials used 22,360 Depreciation, factory equipment 1,620 Work in process, 6/1/20 3,480 Direct labor 42,170 Work in process, 6/30/20 4,620 Maintenance, factory equipment 2,000 5,660 Indirect materials 2,600 Finished goods, 6/1/20 Finished goods, 6/30/20 7,680 Factory manager's salary 3,340 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule $ We were unable to transcribe...
*Exercise 10-12 (Part Level Submission) Cepeda Corporation has the following cost records for June 2017 3 40,000 Indirect factory abor Direct materials used Work in process, 6/1/17 Work in process, 6/30/17 Finished goods, 6/1/17 Finished goods. 6/30/17 4.500 20.000 .000 3,800 5.000 7.500 Factory i s Depreciation factory equipment Direct labor Maintenance factory equipment Indirect materials Factory manager's salary 1.800 2.000 *(a) Your answer is correct. Prepare a cost of goods manufactured schedule for June 2017. CEPEDA CURELIIKIN For the...
part B) Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,690 Factory utilities $430 Direct materials used 22,410 Depreciation factory equipment 1,770 Work in process, 6/1/20 3,970 Direct labor 42,100 Work in process, 6/30/20 4,410 Maintenance, factory equipment 1,910 2,810 Finished goods, 6/1/20 Finished goods, 6/30/20 5,650 Indirect materials 8,030 Factory manager's salary 3,930 Your Answer Correct Answer Your answer is correct. Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost...
E14.12 (LO 3) Cepeda Corporation has the following cost records for June 2020. Prepare a cost of goods manufactured schedule and a partial income statement Excel Indirect factory labor Direct materials used Work in process, 6/1/20 Work in process, 6/30/20 Finished goods, 6/1/20 Finished goods, 6/30/20 $ 4,500 20,000 3,000 3,800 5,000 7,500 Factory utilities Depreciation, factory equipment Direct labor Maintenance, factory equipment Indirect materials Factory manager's salary $ 400 1,400 40,000 1,800 2,200 3,000 Instructions a. Prepare a cost...