Question

Income Statement Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle Compan

ppmcu UVCCU 1720 During August, four more jobs were started. Information on costs added to the seven jobs during the month is

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans.

Working Notes

1.

Predetermined overhead = Overhead / Labor cost

We can take data of any job's opening work in progress. (taking data of Job 70)

Predetermined overhead rate = $1,520 / $1,900 = $0.80

2.

Computation of ending balance of each job

Job 70 Job 71 Job 72 Job 73 Job 74 Job 75 Job 76
Direct Material $2,500 ($1,700 + $800) $3,235 ($2,000 + $1,235) $4,350 ($850 + $3,500) $5,000 $300 $560 $80
Direct Labor $2,900 ($1,900 + $1000) $2,700 ($1,300 + $1,400) $3,100 ($900 + $2,200) $1,800 $600 $850 $170
Applied Overhead ($0.80 * Direct Labor) $2,320 $2,160 $2,480 $1,440 $480 $680 $136
Total Balance $7,720 $8,095 $9,930 $8,240 $1,380 $2,090 $386

3.

Cost of goods sold =

Cost of goods sold for August consists of Jobs 72 and 75:

Cost of Job 72 .................$ 9,930

Cost of Job 75 ................ $ 2,090

Cost of goods sold ........ $ 12,020

4.

Sales Revenue = Cost of goods sold * (1 + 0.15)

Sales Revenue = $12,020 * (1.15) = $ 13,823

Carlie Company
Income Statement
For the month of August
Sales $           13,823.00
Cost of Goods Sold $           12,020.00
Gross Margin $             1,803.00
Selling and Administrative Expenses $             1,300.00
Operating Income $                 503.00
Add a comment
Know the answer?
Add Answer to:
Income Statement Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Income Statement Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August...

    Income Statement Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle Company's work-in-process inventory consisted of three jobs with the following costs: Job 70 Job 71 Job 72 Direct materials $1,700 $2,000 $850 Direct labor 1,900 1,300 900 Applied overhead 1,330 910 630 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job 70 Job 71 Job 72 Job 73 Job...

  • Income Statement Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August...

    Income Statement Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle Company's work-in-process inventory consisted of three jobs with the following costs: Job 70 Job 71 Job 72 Direct materials $1,500 $2,000 $850 Direct labor 1,900 1,300 900 Applied overhead 1,520 1,040 720 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Direct materials Job 70 $800 1,000 Job 71 $1,235...

  • Income Statement Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August...

    Income Statement Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle Company’s work-in-process inventory consisted of three jobs with the following costs: Job 70 Job 71 Job 72 Direct materials $1,700 $2,000 $850 Direct labor 1,900 1,300 900 Applied overhead 1,520 1,040 720 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job 70 Job 71 Job 72 Job 73 Job...

  • Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle...

    Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle Company's work-in-process inventory consisted of three jobs with the following costs: Job Job 70 Job 71 72 Direct materials $1,500 $2,000 $850 Direct labor 1,900 1,400 900 Applied overhead 1,520 1,120 720 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job Job Job Job Job 71 Job 72 Job 73 70...

  • Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle...

    Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle Company's work-in-process inventory consisted of three jobs with the following costs: Job 70 Job 71 Job 72 Direct materials $1,700 $850 Direct labor 1,900 1,94 $2,000 1,200 960 900 Applied overhead 1,520 720 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job 70 Job 71 Job 72 Job 73 Job 74...

  • on august 1st, Carole or Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit...

    on august 1st, Carole or Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle Company's work-in-process inventory consisted of three jobs with the following costs: Job 70 Job 72 Direct materials Job 71 $2,000 1,300 $1,600 1,900 $850 Direct labor 900 Applied overhead 1,425 975 675 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job 70 Job 71 Job 72...

  • Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle...

    Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle Company’s work-in-process inventory consisted of three jobs with the following costs: Job 70 Job 71 Job 72 Direct materials $1,500 $2,000 $850 Direct labor 1,900 1,200 900 Applied overhead 1,520 960 720 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job 70 Job 71 Job 72 Job 73 Job 74 Job...

  • Exercise 5.14 Cost, Unit Cost Predetermined Overhead Rate, Application of Overhead to Jobs, Job OBJECTIVE wiest...

    Exercise 5.14 Cost, Unit Cost Predetermined Overhead Rate, Application of Overhead to Jobs, Job OBJECTIVE wiest i Cairle Company's work-in-process inventory consisted of three jobs with the following costs: On August 1, Company Job 72 Direct materials Direct labor Applied overhead Job 70 $1,600 1,900 1,425 Job 71 $2,000 1,300 975 $850 900 675 more jobs were started. Information on costs added to the seven jobs dur- Job 70 Job 71 Job 72 Job 73 Job 74Job 75 Job 76...

  • On August 1, Cairle Company’s work-in-process inventory consisted of three jobs with the following costs: Job...

    On August 1, Cairle Company’s work-in-process inventory consisted of three jobs with the following costs: Job 70 Job 71 Job 72 Direct materials $1,600 $2,000 $850 Direct labor 1,900 1,300 900 Applied overhead 1,425 975 675 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job 70 Job 71 Job 72 Job 73 Job 74 Job 75 Job 76 Direct materials $800 $1,235 $3,550 $5,000 $300 $560 $80...

  • On August 1, Cairle Company’s work-in-process inventory consisted of three jobs with the following costs: Job...

    On August 1, Cairle Company’s work-in-process inventory consisted of three jobs with the following costs: Job 70 Job 71 Job 72 Direct materials $1,700 $2,000 $850 Direct labor 1,900 1,200 900 Applied overhead 1,330 840 630 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job 70 Job 71 Job 72 Job 73 Job 74 Job 75 Job 76 Direct materials $800 $1,235 $3,600 $5,000 $300 $560 $80...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT