Question

Required information E4-3, E4-4 and E4-5 Gable Company uses three activity cost pools. Each pool has a cost driver. InformatiRequired 1 Required 2 Classify each activity as facility, product, batch, or unit level. Machining Design Setup

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Requirement 1

Activity rate
Machining $               4.10 Per Machine hour
Designing costs $               9.40 Per design hour
Setup costs $          143.40 Per batch

Requirement 2

Classification
Machining Batch level
Designing costs Product level
Setup costs Batch level

Working

Calculation of Activity rates
Activity Cost Pool Activity driver Overhead Cost (A) Expected Activity (B) Activity rate (A/B)
Machining Number of Machine hour $ 345,220 84200 $               4.10 Per Machine hour
Designing costs Number of design hour $ 79,900 8500 $               9.40 Per design hour
Setup costs Number of batch $ 70,983 495 $          143.40 Per batch
Add a comment
Know the answer?
Add Answer to:
Required information E4-3, E4-4 and E4-5 Gable Company uses three activity cost pools. Each pool has...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information E4-3, E4-4 and E4-5 Gable Company uses three activity cost pools. Each pool has...

    Required information E4-3, E4-4 and E4-5 Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of pool Cost Driver $398,200 Number of machine hours 89,725 Number of design hours 70,413 Number of batches Estimated Cost Driver 90,500 9,250 490 E4-3 (Algo) Calculating Activity Rates, Classifying Activities (LO 4-2, 4.4) Required: 1. Compute the activity rate for each activity 2. Classify each...

  • Check my work 1 Required information Gable Company uses three activity cost pools. Each pool has...

    Check my work 1 Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: 1 points Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $345, 220 Number of machine hours 79,900 Number of design hours 70,983 Number of batches Estimated Cost Driver 84,200 8,500 495 eBook Hint Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch,...

  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $ 250,680 Number of machine hours 61,600 Number of design hours 66,482 Number of batches Estimated Cost Driver 71,600 7.ee 465 Required: 1. Compute the activity rate for each activity 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...

  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $171,100 Number of machine hours 45,100 Number of design hours 66,123 Number of batches Estimated Cost Driver 59,000 5,500 465 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...

  • Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...

    Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Rate per Machine Hour Activity Machining Design Costs Setup per Design...

  • Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...

    Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Rate per Machine Hour Activity Machining Design Costs Setup per Design...

  • Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...

    Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $280,460 Number of machine hours 67,500 Number of design hours 70,070 Number of batches Estimated Cost Driver 75,800 7,500 490 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your answers in...

  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $183,300 Number of machine hours 47,725 Number of design hours 71,150 Number of batches Estimated Cost Driver 61,100 5,750 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...

  • Required information 14-3, E4-4 and 54-5 Gable Company uses three activity cost pools. Each pool has...

    Required information 14-3, E4-4 and 54-5 Gable Company uses three activity cost pools. Each pool has a cost driver Information for Gable Company follows: Total Estimated Activity Cost Cost of Cost Pools Pool Cost Driver Driver BAE Number of Machining $345, 220 84,200 machine hours Designing 79,900 Number of design ign 8,500 costs hours Setup costs 70 982 Number of 10,903 batches 495 E4-4 (Algo) Assigning Costs Using Activity Rates (LO 4-4) Suppose that Gable Company manufactures three products, A....

  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT