ANTUAN COMPANY | |||||
Flexible Overhead Budgets | |||||
For Month Ended October 31 | |||||
Flexible Budget | Flexible Budget for | ||||
Variable Amount per Unit | Total Fixed Cost | 65% of capacity | 75% of capacity | 85% of capacity | |
Sales (in units) | 13,000 | 15,000 | 17,000 | ||
Variable overhead costs | |||||
Indirect materials | 2.00 | 26,000 | 30,000 | 34,000 | |
Indirect labor | 5.00 | 65,000 | 75,000 | 85,000 | |
Power | 2.00 | 26,000 | 30,000 | 34,000 | |
Repairs and maintenance | 2.00 | 26,000 | 30,000 | 34,000 | |
Total variable overhead costs | 11.00 | 143000 | 165000 | 187000 | |
Fixed overhead costs | |||||
Depreciation—Building | 25,000 | 25,000 | 25,000 | 25,000 | |
Depreciation—Machinery | 72,000 | 72,000 | 72,000 | 72,000 | |
Taxes and insurance | 18,000 | 18,000 | 18,000 | 18,000 | |
Supervision | 219,500 | 219,500 | 219,500 | 219,500 | |
Total fixed overhead costs | 334500 | 334500 | 334500 | 334500 | |
Total overhead costs | 477500 | 499500 | 521500 |
Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0...
Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) Direct labor (1.8 hrs. @ $11.00 per hr.) Overhead (1.8 hrs. @ $18.50 per hr.) Total standard cost $24.00 19.80 33.30 $77.10 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory's capacity of 20,000 units per month. Following are the company's budgeted overhead costs per month at the...
Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) Direct labor (1.8 hrs. @ $11.00 per hr.) Overhead (1.8 hrs. @ $18.50 per hr.) Total standard cost $24.00 19.80 33.30 $77.10 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory capacity of 20,000 units per month. Following are the company's budgeted overhead costs per month at the...
Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $4.00 per Ib.) $ 16.00 Direct labor (1.7 hrs. @ $10.00 per hr.) 17.00 Overhead (1.7 hrs. @ $18.50 per hr.) 31.45 Total standard cost $ 64.45 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month. Following are the company’s budgeted overhead costs per month...
Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) $ 24.00 Direct labor (1.8 hrs. @ $12.00 per hr.) 21.60 Overhead (1.8 hrs. @ $18.50 per hr.) 33.30 Total standard cost $ 78.90 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month. Following are the company’s budgeted overhead costs per month...
Antuan Company set the following standard costs for one unit of its product. Direct materials (3.0 Ibs. @ $5.00 per Ib.) $ 15.00 Direct labor (1.8 hrs. @ $11.00 per hr.) 19.80 Overhead (1.8 hrs. @ $18.50 per hr.) 33.30 Total standard cost $ 68.10 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month. Following are the company’s budgeted overhead costs per month...
Antuan Company set the following standard costs for one unit of its product. Direct materials (5.0 Ibs. @ $5.00 per Ib.) $ 25.00 Direct labor (1.8 hrs. @ $12.00 per hr.) 21.60 Overhead (1.8 hrs. @ $18.50 per hr.) 33.30 Total standard cost $ 79.90 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month. Following are the company’s budgeted overhead costs per month...
Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) $ 24.00 Direct labor (1.8 hrs. @ $12.00 per hr.) 21.60 Overhead (1.8 hrs. @ $18.50 per hr.) 33.30 Total standard cost $ 78.90 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month. Following are the company’s budgeted overhead costs per month...
Antuan Company set the following standard costs for one unit of its product. Direct materials (3.0 Ibs. @ $4.00 per Ib.) Direct labor (1.7 hrs. @ $11.00 per hr.) Overhead (1.7 hrs. @ $18.50 per hr.) Total standard cost $12.00 18.70 31.45 $62.15 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory's capacity of 20,000 units per month. Following are the company's budgeted overhead costs per month at the...
Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) $ 24.00 Direct labor (1.8 hrs. @ $12.00 per hr.) 21.60 Overhead (1.8 hrs. @ $18.50 per hr.) 33.30 Total standard cost $ 78.90 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month. Following are the company’s budgeted overhead costs per month...
Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) $ 24.00 Direct labor (1.8 hrs. @ $12.00 per hr.) 21.60 Overhead (1.8 hrs. @ $18.50 per hr.) 33.30 Total standard cost $ 78.90 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month. Following are the company’s budgeted overhead costs per month...