(LO 1 2 ), AN Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2022 are as follows.

Overhead Cost PoolsAmount
Purchasing$75,000
Handling materials82,000
Production (cutting, milling, finishing)210,000
Setting up machines105,000
Inspecting90,000
Inventory control (raw materials and finished goods)126,000
Utilities180,000
Total budgeted overhead costs$868,000

For the last 4 years, Shaker Stairs Co. has been charging overhead to products on the basis of machine hours. For the year 2022,100,000 machine hours are budgeted.


Jeremy Nolan, owner-manager of Shaker Stairs Co., recently directed his accountant, Bill Seagren, to implement the activity-based costing system that he has repeatedly proposed. At Jeremy Nolan's request, Bill and the production foreman identify the following cost drivers and their usage for the previously budgeted overhead cost pools.

Activity Cost PoolsCost DriversCost Drivers
PurchasingNumber of orders600
Handling materialsNumber of moves8,000
Production (cutting, milling, finishing)Direct labor hours100,000
Setting up machinesNumber of setups1,250
InspectingNumber of inspections6,000
Inventory control (raw materials and finished goods)Number of components168,000
UtilitiesSquare feet occupied90,000

Steve Hannon, sales manager, has received an order for 250 stairways from Community Builders, Inc., a large housing development contractor. At Steve's request, Bill prepares cost estimates for producing components for 250 stairways so Steve can submit a contract price per stairway to Community Builders. He accumulates the following data for the production of 250 stairways.

image.png

Instructions

(a) Compute the predetermined overhead rate using traditional costing with machine hours as the basis.

(b) What is the manufacturing cost per stairway under traditional costing? (Round to the nearest cent.) Cost/stairway $ 1,365.84

(c) What is the manufacturing cost per stairway under the proposed activity-based costing? (Round to the nearest cent. Prepare all of the necessary schedules.)

Cost/stairway $ 1,139.80

(d) Which of the two costing systems is preferable in pricing decisions and why?

3 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

a Predetermined Overhead Rate 8.68 per machine hour = Estimated Overhead Esimated machine hour =868000 100000 b Calculations

Add a comment
Know the answer?
Add Answer to:
Assign overhead costs using traditional costing and A B C; compare results.
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Shaker Stairs Co.designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles,...

    Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows.Overhead Cost PoolsAmountPurchasing$75,000Handling materials82,000Production (cutting, milling, finishing)210,000Setting up machines100,000Inspecting96,000Inventory control (raw materials and finished goods)126,000Utilities450,000Total budgeted overhead costs$1,139,000For the last 4 years, Shaker Stairs Co. has been charging overhead to products on the basis...

  • Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components...

    Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Amount Purchasing $75,000 Handling materials 82,000 Production (cutting, milling, finishing) 220,000 Setting up machines 105,000 Inspecting 114,000 Inventory control (raw materials and finished goods) 126,000 Utilities 360,000 Total budgeted overhead...

  • Problem 4-3A a-b, c1-c3 (Video) (Part Level Submission) Shaker Stairs Co. designs and builds factory-made premium...

    Problem 4-3A a-b, c1-c3 (Video) (Part Level Submission) Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Amount Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted...

  • P17-3A--- Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway...

    P17-3A--- Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2017 are as follows. Overhead Cost Pools Amount Purchasing $ 75,000 Handling materials 82,000 Production (cutting, milling, finishing) 210,000 Setting up machines 105,000 Inspecting 90,000 Inventory control (raw materials and finished goods) 126,000 Utilities 180,000 Total...

  • Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components...

    Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Amount Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities $75,000 82,000 210,000 100,000 96,000 126,000 270,000 Total budgeted overhead...

  • Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components...

    Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted overhead costs Amount $75,000 82,000 220,000 100,000 120,000 126,000...

  • Problem 17-03A a-b, c-c (Part Level Submission) Shaker Stars Co, designs and builds factory made premium...

    Problem 17-03A a-b, c-c (Part Level Submission) Shaker Stars Co, designs and builds factory made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, handrais permit installation of starways of varying lengths and widths. All are of white oak wood Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Purchaung Handing materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utaties Total budgeted overhead costs...

  • Shaker Stairs Co.designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles,...

    Shaker Stairs Co.designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted overhead costs Amount $75,000 82,000 220,000 105,000 108,000 126,000 270,000...

  • ACCT212 SEM 191-ASSIGNM QUESTION Thakin Stairs Co. designs and builds factory-made premium wooden stairways for homes....

    ACCT212 SEM 191-ASSIGNM QUESTION Thakin Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2014 are as follows. Amount Overhead Cost Pools $ 69,000 Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities 82,000 210,000 95,000 90,000...

  • using P4-3A Shaker Stairs Co. designs and builds factory-made premium wooden stai ABC omes. The manufactured...

    using P4-3A Shaker Stairs Co. designs and builds factory-made premium wooden stai ABC omes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2017 are as follows. Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted overhead costs Amount $ 75,000 82,000 210,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT