1. Allocation of costs to the Activity Cost pools
Removing Asbestos | Estimating and Job Setup | Working on Nonroutine Jobs | Other | Total | |
Wages and Salaries |
$201000 ($ 402000x50%) |
$60300 ($ 402000x15%) |
$80400 ($ 402000x20%) |
$60300 ($ 402000x15%) |
$402000 |
Disposal Fees |
$442200 ($737000x60%) |
0 |
$294800 ($737000x40%) |
0 | $737000 |
Equipment Depreciation |
$52000 ($104000x50%) |
$10400 ($104000x10%) |
$15600 ($104000x15%) |
$26000 ($104000x25%) |
$104000 |
Onsite Supplies |
$44800 ($64000x70%) |
$12800 ($64000x20%) |
$6400 ($64000x10%) |
0 | $64000 |
Office Expenses |
$33000 ($330000x10%) |
$115500 ($330000x35%) |
$82500 ($330000x25%) |
$99000 ($330000x30%) |
$330000 |
Licensing and insurance |
$138000 ($460000x30%) |
0 |
$230000 ($460000x50%) |
$92000 ($460000x20%) |
$460000 |
Total Cost | $911000 | $199000 | $709700 | $277300 | $2097000 |
2. Computation of Activity rates for the activity cost pools
Acivity Cost Pool | Total Cost | Activity Measure | Total Activity | Cost Per Activity |
Removing Asbestos | $911000 | Thousands of Square Feet | 1000 thousands Square Feet | $911 |
Estimating and Job Setup | $199000 | Number of Jobs | 500 Jobs | $398 |
Working on Nonroutine Jobs | $709700 | Number of Nonroutine Jobs | 100 Non-Routine Jobs | $7097 |
Other | $277300 | None | Estimating and setup cost (i.e 500 jobs) | $554.6 |
3. Detemine Total Cost and average cost per thousand square feet
a. A routine 1000 square foot asbestos removal.
* Removing Asbestos = $ 911
*Estimating and Job Setup = $ 398
*Other =$555
Total Cost =$1864
Average Cost per thousand Square feet = $1.864
b. A routine 2000 square foot asbestos removal.
* Removing Asbestos = $ 911
*Estimating and Job Setup = $ 398
*Other =$555
Total Cost =$1864
Average Cost per thousand Square feet = $0.932
c. A nonroutine 1000 square foot asbestos removal.
* Removing Asbestos = $ 911
*working on nonroutine jobs = $ 7097
*Other =$ 555
Total Cost =$ 8563
Average Cost per thousand Square feet = $8.563
Mercer Asbestos Removal Company removes potentially toxic asbestos Insulation and related products from bulldings. There has...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work such as removal of asbestos insulation around heating pipes in older homes and nonroutine work such as removing asbestos contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos Insulation and related products from bulldings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos Insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos contaminated celling plaster in industrial buildings. The on-site supervision believe that nonroutine work is far more expensive than routine...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has E been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine...