Fogerty Company makes two products-titanium Hubs and Sprockets. Data regarding the two products follow:
Additional information about the company follows:
a. Hubs require $22 In direct materials per unit, and Sprockets require $15.
b. The direct labor wage rate is S17 per hour.
c. Hubs require special equipment and are more complex to manufacture than Sprockets.
d. The ABC system has the following activity cost pools:
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.
(1)
Activity Cost Pool |
Estimated OH |
Activity |
Activity Rate |
Machine Setup |
$17955 |
171 setups |
$105 per setup |
Special Processing |
$90000 |
3600 machine hours |
$25 per MH |
General factory |
$163200 |
26400 DLH |
(2)
Hubs |
Sprockets |
|
DM |
$22 |
$15 |
DL |
(25000 * 0.6 * $17)/25000 =$10.20 |
(57000 * 0.2 * $17)/57000 =$3.40 |
Overhead: |
||
Machine Setup |
($105 * 95)/25000 =$0.40 |
($105 * 76)/57000 =$0.14 |
Special Processing |
($25 * 3600)/25000 =$3.60 |
- |
General |
($92727/25000) =$3.71 |
(70473/57000) =$1.24 |
Cost per unit |
$39.91 |
$19.78 |
General factory for Hubs = $163200 * 15000/26400 = $92727
General factory for Sprockets = $163200 * 11400/26400 = $70473
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Fogerty Company makes two products-titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor- Hours per Annual Unit Production 0.90 27,000 units 0.50 41,000 units Hubs Sprockets Additional information about the company follows: a. Hubs require $36 in direct materials per unit, and Sprockets require $12. b. The direct labor wage rate is $19 per hour. c. Hubs require special equipment and are more...
Fogerty Company makes two products-titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor- Hours Annual per Unit Production 10,000 units 56,000 units Hubs 0.90 Sprockets 0.50 Additional information about the company follows: a. Hubs require $34 in direct materials per unit, and Sprockets require $16. b. The direct labor wage rate is $18 per hour. c. Hubs require special equipment and are more complex to manufacture than Sprockets. d. The ABC system has the following activity cost...
Fogerty Company makes two products-titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor- Hours per Unit 0.50 0.10 Annual Production 14,000 units 46,000 units Hubs Sprockets Additional information about the company follows: a. Hubs require $33 in direct materials per unit, and Sprockets require $19. b. The direct labor wage rate is $15 per hour. c. Hubs require special equipment and are more complex to manufacture than Sprockets. d. The ABC system has the following activity cost...
Fogerty Company makes two products-titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor- Hours per Annual Unit Production 0.60 28,000 units 0.20 54,000 units Hubs Sprockets Additional information about the company follows: a. Hubs require $31 in direct materials per unit, and Sprockets require $17. b. The direct labor wage rate is $11 per hour. C. Hubs require special equipment and are more complex to manufacture than Sprockets d. The ABC system has the following activity cost...
Fogerty Company makes two products-titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor- Hours per Annual Unit Production 0.60 16,000 units 0.20 57,000units Hubs Sprockets Additional information about the company follows: 0. Hubs require $36 in direct materials per unit, and Sprockets require $14. a. The direct labor wage rate is $17 per hour. b. Hubs require special equipment and are more complex to manufacture than Sprockets. c. The ABC system has the following activity cost pools:...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.70 20,000 units Sprockets 0.30 60,000 units Additional information about the company follows: Hubs require $27 in direct materials per unit, and Sprockets require $19. The direct labor wage rate is $14 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.60 17,000 units Sprockets 0.20 54,000 units Additional information about the company follows: Hubs require $34 in direct materials per unit, and Sprockets require $18. The direct labor wage rate is $16 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.70 12,000 units Sprockets 0.30 52,000 units Additional information about the company follows: Hubs require $33 in direct materials per unit, and Sprockets require $11. The direct labor wage rate is $15 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.50 24,000 units Sprockets 0.10 57,000 units Additional information about the company follows: Hubs require $27 in direct materials per unit, and Sprockets require $11. The direct labor wage rate is $19 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Activity Cost Pool (Activity...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.90 25,000 units Sprockets 0.50 46,000 units Additional information about the company follows: Hubs require $31 in direct materials per unit, and Sprockets require $10. The direct labor wage rate is $13 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...