Given the following cost and activity observations for Bounty Company's utilities, use the high-low method to...

Given the following cost and activity observations for Bounty Company's utilities, use the high-low method to calculate Bounty's variable utilities cost per machine hour. Round to the nearest cent.

Cost Machine Hours

March $3,091 14,557

April 2,637 9,654

May 2,804 11,926

June 3,899 18,355

0 1
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Variable cost under High-Low method = (Cost at highest level of machine hours - Cost at lowest level of machine hours) / (Highest machine hours - Lowest Machine hours)

Variable cost under High-Low method = ($3,899 - $2,637) / (18,355-9,654)

Variable cost under High-Low method = $1,262 / 8,701

Variable cost under High-Low method = $0.1

You can reach me over comment box if you have any doubts. Please rate this answer

Add a comment
Know the answer?
Add Answer to:
Given the following cost and activity observations for Bounty Company's utilities, use the high-low method to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT