Given the following cost and activity observations for Bounty Company's utilities, use the high-low method to...

Given the following cost and activity observations for Bounty Company's utilities, use the high-low method to calculate Bounty's variable utilities cost per machine hour. Round to the nearest cent.

Cost

Machine Hours

March $3,050 15,063
April 2,613 9,686
May 2,892 12,392
June 3,843 18,245

a.$0.14

b.$1.01

c.$0.97

d.$1.58

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Variable cost per unit=[Total cost at highest level-Total cost at lowest level]/(Highest level-Lowest level)

=(3843-2613)/(18245-9686)

which is equal to

=$0.14 per machine hour(Approx).

Add a comment
Know the answer?
Add Answer to:
Given the following cost and activity observations for Bounty Company's utilities, use the high-low method to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT