Question

Star Company’s accountants estimate total overhead for each month will be $64,000. They will allocate overhead...

Star Company’s accountants estimate total overhead for each month will be $64,000. They will allocate overhead on the basis of direct labour cost. During the current month, three jobs were worked on:

Job 745, Job 746, Job 747

Direct material: $36,000, $56,000, $24,000

Direct labour $56,000, $72,000, $40,000,

Job 745 was completed and sold, Job 746 was completed and Job 747 is still in process.

Budgeted direct labour cost for the month was $160,000 and actual overhead was $65,800.

Assuming overhead was $2,000 underapplied and that this amount is considered material, the balance of work in process after allocation of the underapplied overhead based on overhead charged to the accounts during the period is:

0 0
Add a comment Improve this question Transcribed image text
Answer #1

(b) (c)=(a) + (b) (d) Job Status Direct material Cost without Overhead Direct labor Overhead Applied (c) + (d) Total cost inc

Add a comment
Know the answer?
Add Answer to:
Star Company’s accountants estimate total overhead for each month will be $64,000. They will allocate overhead...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Star Company’s accountants estimate total overhead for each month will be $64,000. They will allocate overhead...

    Star Company’s accountants estimate total overhead for each month will be $64,000. They will allocate overhead on the basis of direct labour cost. During the current month, three jobs were worked on: Job 745 Job 746 Job 747 Direct material $36,000 $56,000 $24,000 Direct labour $56,000 $72,000 $40,000 Job 745 was completed and sold, Job 746 was completed and Job 747 is still in process. Budgeted direct labour cost for the month was $160,000 and actual overhead was $65,800. Assuming...

  • Please explain both question. Thanks a lot. FULL SCREEN PRINTER VERSION BACK estbank, Question 103 tar...

    Please explain both question. Thanks a lot. FULL SCREEN PRINTER VERSION BACK estbank, Question 103 tar Company's accountants estimate total overhead for each month will be $64,000. They will allocate overhead on the basis of direct labour cost. During the current month, three jobs were work Direct material Direct labour Job 745 $36,000 $56,000 ob 746 $56,000 $72,000 lob 742 $24,000 $40,000 Job 745 was completed and sold, Job 746 was completed and Job 747 is still in process, Budgeted...

  • Problem 15-4A Overhead allocation and adjustment using a predetermined overhead rate LO P3, P4 At the...

    Problem 15-4A Overhead allocation and adjustment using a predetermined overhead rate LO P3, P4 At the beginning of the year, Learer Company’s manager estimated total direct labor cost assuming 55 persons working an average of 2,000 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for the year. Indirect labor $ 261,200 Factory supervision 156,000 Rent on factory building 152,000 Factory utilities 100,000 Factory insurance expired 80,000 Depreciation—Factory equipment...

  • Problem 3-14 Schedule of Cost of Goods Manufactured; Overhead Analysis (LO3-3, LO3-4) Gitano Products operates a...

    Problem 3-14 Schedule of Cost of Goods Manufactured; Overhead Analysis (LO3-3, LO3-4) Gitano Products operates a job order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $127,400 of manufacturing overhead for an estimated allocation base of $91.000 direct material dollars to be used in production. The company has provided the following...

  • Sai Company uses a job order cost system and applies manufacturing overhead costs to jobs using...

    Sai Company uses a job order cost system and applies manufacturing overhead costs to jobs using a predetermined overhead rate based on direct labour-hours. The following data were extracted from the company's accounting records for Year 6 Estimated Actual Manufacturing overhead costs $50,000 $54,000 Direct labour-hours 20,000 24,000 hours hours Job #461 was completed during the year and the following costs had been incurred on that job: Direct materials $4,000 $1,500 (at $5 per direct Direct labour labour hour) What...

  • Please show work, thank you! 1. Compute the predetermined overhead rate for the year. 2.Compute the...

    Please show work, thank you! 1. Compute the predetermined overhead rate for the year. 2.Compute the amount of underapplied or overapllied overhead for the year. Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production(not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $113,100 of manufacturing overhead for an estimated allocation base of $87000 direct material dollars...

  • 1. Predetermined overhead rate: 130% 2. Underapplied overhead 3,800 3. Prepare a schedule of cost of...

    1. Predetermined overhead rate: 130% 2. Underapplied overhead 3,800 3. Prepare a schedule of cost of goods manufactured for the year. Assume all raw materials used in production as direct materials. 4. Compute the unadjusted cost of goods sold for the year. Do not include any underapplied or overapplied overhead in your answer. Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production(not on the basis of raw...

  • Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis...

    Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $120,900 of manufacturing overhead for an estimated allocation base of $93,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: Purchase of raw materials $ 136,000 Direct...

  • Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis...

    Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $124,600 of manufacturing overhead for an estimated allocation base of $89,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: Purchase of raw materials $ 131,000 Direct...

  • The following journal entry records the application of manufacturing overhead for the month of August: Work...

    The following journal entry records the application of manufacturing overhead for the month of August: Work in process $90359     Manufacturing overhead $90359 The overhead is applied on the basis of direct labour-hours. During August, 16518 direct labour-hours were incurred. The budgeted direct labour-hours for the month was 11690 hours. Job Z used 13715 direct labour-hours during August. What will the job cost sheet for Job Z show for manufacturing overhead cost added during August? a. $75026 b. $106011 c....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT