Star Company’s accountants estimate total overhead for each month will be $64,000. They will allocate overhead on the basis of direct labour cost. During the current month, three jobs were worked on: Job 745 Job 746 Job 747 Direct material $36,000 $56,000 $24,000 Direct labour $56,000 $72,000 $40,000 Job 745 was completed and sold, Job 746 was completed and Job 747 is still in process. Budgeted direct labour cost for the month was $160,000 and actual overhead was $65,800. Assuming overhead was $100 underapplied and that this amount is considered immaterial, the final adjusted balance of cost of goods sold is:
$92,100 |
$211,900 |
$114,500 |
$79,900 |
Only Job 745 is sold. Cost of goods sold arises only for Job 745.
Overhead rate = 64,000 / 160,000 = 40%
Total cost of Job 745 = $36,000 + $56,000 + ($56,000 X 40%) + $100 = $114,500
3rd option.
Star Company’s accountants estimate total overhead for each month will be $64,000. They will allocate overhead...
Star Company’s accountants estimate total overhead for each month will be $64,000. They will allocate overhead on the basis of direct labour cost. During the current month, three jobs were worked on: Job 745, Job 746, Job 747 Direct material: $36,000, $56,000, $24,000 Direct labour $56,000, $72,000, $40,000, Job 745 was completed and sold, Job 746 was completed and Job 747 is still in process. Budgeted direct labour cost for the month was $160,000 and actual overhead was $65,800. Assuming...
Please explain both question. Thanks a lot.
FULL SCREEN PRINTER VERSION BACK estbank, Question 103 tar Company's accountants estimate total overhead for each month will be $64,000. They will allocate overhead on the basis of direct labour cost. During the current month, three jobs were work Direct material Direct labour Job 745 $36,000 $56,000 ob 746 $56,000 $72,000 lob 742 $24,000 $40,000 Job 745 was completed and sold, Job 746 was completed and Job 747 is still in process, Budgeted...
Problem 15-4A Overhead allocation and adjustment using a predetermined overhead rate LO P3, P4 At the beginning of the year, Learer Company’s manager estimated total direct labor cost assuming 55 persons working an average of 2,000 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for the year. Indirect labor $ 261,200 Factory supervision 156,000 Rent on factory building 152,000 Factory utilities 100,000 Factory insurance expired 80,000 Depreciation—Factory equipment...
In December 2016, Learer Company’s manager estimated next year’s total direct labor cost assuming 35 persons working an average of 2,000 hours each at an average wage rate of $40 per hour. The manager also estimated the following manufacturing overhead costs for 2017. Indirect labor $ 329,200 Factory supervision 354,000 Rent on factory building 150,000 Factory utilities 98,000 Factory insurance expired 78,000 Depreciation—Factory equipment 756,000 Repairs expense—Factory equipment 70,000 Factory supplies used 78,800 Miscellaneous production costs 46,000 Total estimated overhead...
1. Predetermined overhead rate: 130%
2. Underapplied overhead 3,800
3. Prepare a schedule of cost of goods manufactured for the
year. Assume all raw materials used in production as direct
materials.
4. Compute the unadjusted cost of goods sold for the year. Do
not include any underapplied or overapplied overhead in your
answer.
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production(not on the basis of raw...
[The following information applies to the questions displayed below] Widmer Watercraft's predetermined overhead rate for the year 2017 is 200% of direct labor. Information on the company's production activities during May 2017 follows. a. Purchased raw materials on credit, $220,000. b. Materials requisitions record use of the following materials for the month. Job 136 Job 137 Job 138 Job 139 Job 140 Total direct materials Indirect materials Total materials used 49, See 33,5ee 19,600 23,eee 6. Bee 132,400 20,50e 152.900...
At the beginning of the year, Learer Company’s manager estimated
total direct labor cost assuming 40 persons working an average of
2,000 hours each at an average wage rate of $40 per hour. The
manager also estimated the following manufacturing overhead costs
for the year.
Indirect labor
$
324,200
Factory supervision
355,000
Rent on factory building
145,000
Factory utilities
93,000
Factory insurance expired
73,000
Depreciation—Factory equipment
750,000
Repairs expense—Factory equipment
65,000
Factory supplies used
73,800
Miscellaneous production costs
41,000
Total...
Please show work, thank you!
1. Compute the predetermined overhead rate for the year.
2.Compute the amount of underapplied or overapllied overhead
for the year.
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production(not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $113,100 of manufacturing overhead for an estimated allocation base of $87000 direct material dollars...
13 overhead rate LO P3, P4 2016, Learer Company's manager estimated next year's total direct labor cost assuming 45 persons working an average of 2,000 hours each at an average wage rate of $25 per hours The manager also estimated the following manufacturing over points costs for 2017. Factory supervision Rent on factory bullding 94,0 Factory insurance expired Repairs expense-Factory equipeent Factory supplies used Miscellaneous production costs Total estinated averhead costs 66,000 At the end of 2017, records show the...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $113,100 of manufacturing overhead for an estimated allocation base of $87,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: $ 138,000 $ 83,000 $ Purchase of...